“9.1. The Sub-Contractor shall be entitled to payment by instalments. 9.2. It is a condition precedent to payment that the Sub-Contractor shall make monthly applications (“Interim Application”) for payment to the Contractor on the dates specified in Appendix 6. Such applications for payment must specify the sum that the Sub-Contractor considers to be due to him and the basis on which that sum has been calculated identifying: (1) The total value of the work properly executed (including the value of any materials or goods intended for incorporation into the works in a priced Schedule format provided the same had been delivered to or adjacent to the site); and (2) Variations, if any, carried out pursuant to clause 8 of this Agreement itemised separately and fully substantiated and costs referenced to instructions issued; and (3) Any other amounts properly due to the Sub-Contractor under this Agreement. 9.3. The payments shall be in accordance with Appendix 6. 9.4. Interim payments shall be due at regular intervals calculated from the date when the first payment was due. The final date for payment shall be in accordance with Appendix 6”
“In the event that Interim Payments become due beyond the dates set out in the schedule above then the Due Dates shall continue to occur at the same intervals as set out above and dates for submission of applications, valuations, Payment Notices, Pay Less Notices and Final Date for Payment shall occur at the same time from the Due Date as for every month as set out above. For the avoidance of doubt if applications are not received from the Sub-Contractor 7 days prior to the Valuation Date then the Sub-Contractor shall not be entitled to any payment, whether or not a payment notice is served by the Sub-Contractor until the procedure set out above is repeated in relation to the next Valuation Date.”
“23.1. No waiver by J & B Hopkins of any breach of the Sub-Contract by the Sub-Contractor shall be a waiver of any subsequent breach of the same or of any other provision of the Sub-Contract. No failure by J & B Hopkins to exercise any right or remedy arising under the Sub-Contract or at law shall be a waiver of its right to exercise such rights arising subsequently.” (c) Appendix 5, paragraph (5)(b), which set out “the normal Working Hours for the site” indicated that, on Sunday, the site was “closed”
“Please see attached our initial summary of your application number 14 dated 21/3/21 and issued 22/3/21. We note that you have issued two applications for the period, the first being application 13, dated and issued 15/3/21 are we to assume number 14 supersedes the aforementioned application 13?”
“A full and formal sub-contract payment or payless notice should be issued in due course and in accordance with the dates set out within appendix 6 of the Sub-contract.”
“26. First, the use of the words "condition precedent" in clause 9.2. Those words are followed by a reference saying that the Sub-Contractor “shall” make monthly applications and that those applications should be made on the date specified in the Appendix. 27. Next at the date of the contract21st March 2021 was going to be a Sunday. It was always going to be a Sunday. It was known to all concerned or capable of being known by all concerned that it would be a Sunday. 28. Next, the dates in the second column in Appendix 6, the dates when the applications were to be made, are not all the 21st day of the relevant month. They are all there or thereabouts but for example in cycle 16 the date is 18th February and in other cycles, it is the 19th of the month, in others 20th and in others the 21st… 33. Mr Edwards did say that the consequence of the interpretation that the Payment Application has to be on 21st March would lead to an unfair result. He says that as a consequence and applying normal principles the court should hesitate before adopting an interpretation which comes to an unfair result in the absence of clear words. However, although the consequence of an interpretation requiring the notice to be on the Sunday is an unusual one it is not one in my judgment which leads to an unfair result such as to cause the court to say clear words are needed before that conclusion can be reached.”
‘pay now, argue later’
“The task of the adjudicator is to find an interim solution that meets the needs of the case. Parliament may be taken to a recognise that, in an interim solution, the contractor (or sub-contractor) or his sub-contractors will be driven into insolvency through a wrongful withholding of payments properly due. The statutory scheme provides a means of meeting the legitimate cash-flow requirements of contractors and their sub-contractors. The need to have the ‘right’ answer has been subordinated to the need to have an answer quickly.”