“The Subcontractor shall not without the prior written consent of the Contractor sub-let any portion of the subcontract works or any portion of the design of the subcontract works.”
“The Subcontractor in subcontracting any portion of the subcontract works to a Sub-subcontractor: • procures that the terms of each sub-subcontract are compatible with the terms of this subcontract; and • as a precondition to payment of any sum related to their work provides to the Contractor within 7 days from the earlier of commencement of their work or the execution of the relevant sub-subcontract a certified copy of the sub-subcontract and compatible with the terms of this subcontract (save for particulars of the sub-subcontract sum or fee), together with evidence of the professional indemnity insurance (or where applicable product liability insurance) held by such sub-subcontractor complying with the terms of the sub-subcontract and the requirements of this subcontract.” • procures that the terms of each sub-subcontract are compatible with the terms of this subcontract; and • as a precondition to payment of any sum related to their work provides to the Contractor within 7 days from the earlier of commencement of their work or the execution of the relevant sub-subcontract a certified copy of the sub-subcontract and compatible with the terms of this subcontract (save for particulars of the sub-subcontract sum or fee), together with evidence of the professional indemnity insurance (or where applicable product liability insurance) held by such sub-subcontractor complying with the terms of the sub-subcontract and the requirements of this subcontract.”
“Where this subcontract requires that a certified copy of any document or deed is provided by the Subcontractor, that certified copy shall be a true copy of the original including all appendices, schedules and attachments…Each document (whether provided in hard copy or via an electronic copy) must be certified as a true copy by a solicitor or a director of the Subcontractor.”
“SBS invites and seeks by remedy that the Adjudicator: a Confirms whether IPS have installed a compliant installation that is in accordance with the Subcontract and which if any milestones should be certified as accepted. b Advises whether IPS have acted negligently in respect to the catastrophic failure that occurred by installing incorrect fittings that were entirely unsuitable. c Values the works and addresses whether SBS should make payment to IPS or whether IPS should make payment to SBS. d Directs that payment should be made in accordance with the decision that has been reached. e If a payment is awarded to IPS advises if all pre-requisites for payment have been complied with in respect to insurances and provision of sub-subcontract conditions etc to enable payment to be made without being in breach of the Subcontract. f For the avoidance of doubt SBS seeks reasons for the Adjudicator’s Decision.” f For the avoidance of doubt SBS seeks reasons for the Adjudicator’s Decision.”
“It is SBS’s position that the requirements for any payment have not been met and accordingly any award of payment to IPS from SBS (which is denied and not accepted) can therefore not be made.”
“If in the unlikely event that payment is to be awarded to IPS it is entirely appropriate and relevant to consider if the pre-conditions for payment have been met.”
“Redress Sought [21] The Redress sought includes the request that the Adjudicator “advises” in respect to the negligence claim. HD This is a reference to Hill Dickinson, solicitors for Isoplus. challenged that a) I am not empowered to ‘advise’ the Parties, and b) that only the Adjudicator’s Decisions are binding, not any advice. As such any advice will not be enforceable. [22] I considered the point raised regarding enforceability to be a valid concern and invited SBS to comment and confirm that they wished me to proceed with the negligence claim. The response from SBS was that they considered this to be a “play on words” and requested that I consider alternative descriptions of the redress sought such as inform notify or make known. [23] SBS are not legally represented and are not required to be for the purposes of adjudication. However, they should note that when making my Decision I am required to apply the law as appropriate. I agree with HD that SBS are not entitled to subsequently amend the wording of the Notice and that the wording of the redress sought is important when it comes to my jurisdiction. [24] I have been asked to ‘advise’ in respect of the negligence claim and that is what I shall do, but with the caveat that SBS have been notified that any such advice may not be enforceable.”
“[167] The Responding Party acknowledges that in paragraph 7.2 of the Response that the Adjudicator is empowered to decide on any ‘pre-requisites’ to payment. [168] The only general precondition to payment I can see in the Subcontract is in clause 51.4 which relates to the issue of a valid VAT invoice. [169] In respect of subcontracting however clause 21.4 does require that the terms of each sub-subcontract are compatible with the terms of the Subcontract, that a certified copy of the sub-subcontract be provided along with evidence of the sub-subcontractor’s professional indemnity insurance. IPS has not commented on this provision which is stated to be a precondition to payment of any sum related to the work of the sub-subcontractor. [170] I am satisfied on a balance of probabilities that compliance with clause 21.4 is required as a precondition to payment of any sums related to a sub-subcontractor. Based on the information provided I am not able to confirm whether IPS have complied with this obligation.”
“[171] Based on my findings I therefore: a) Confirm that IPS have installed a compliant installation that is in accordance with the Subcontract and that milestones 1-17 should be certified as accepted. b) Advise that SBS has not demonstrated on the balance of probability that IPS have acted negligently in respect to the ‘catastrophic’ failure that occurred by installing incorrect fittings that were entirely unsuitable. c) Value the works in the sum of£838,400.71 and find that SBS should make payment to IPS in the sum of£323,502.32 . d) Direct that payment should be made in accordance with the Decision that has been reached. e) Advise that I am not able to confirm that all pre-requisites for payment have been complied with in respect to payment for sub-subcontract works.” a) Confirm that IPS have installed a compliant installation that is in accordance with the Subcontract and that milestones 1-17 should be certified as accepted. b) Advise that SBS has not demonstrated on the balance of probability that IPS have acted negligently in respect to the ‘catastrophic’ failure that occurred by installing incorrect fittings that were entirely unsuitable. c) Value the works in the sum of£838,400.71 and find that SBS should make payment to IPS in the sum of£323,502.32 . d) Direct that payment should be made in accordance with the Decision that has been reached. e) Advise that I am not able to confirm that all pre-requisites for payment have been complied with in respect to payment for sub-subcontract works.”
“SUMMARY OF DECISIONS [173] Having carefully considered the Parties’ submissions and the documents submitted to me in the Adjudication and for all the reasons set out above I confirm that: IPS have installed a compliant installation; Milestones 1- 17 should be certified as accepted; The works are valued in the sum of£838,400.71 ; That SBS should make payment to IPS in the sum of£323,502.32 ; That SBS shall be liable for my fees in the sum of£10,600.00 excluding VAT. SUMMARY OF ADVICE [174] Having carefully considered the Parties’ submissions and the documents submitted to me in the Adjudication and for all the reasons set out above I advise that: SBS has not demonstrated on the balance of probability that IPS have acted negligently in respect to the ‘catastrophic’ failure that occurred by installing incorrect fittings that were entirely unsuitable; Advise that I am not able to confirm that all pre-requisites for payment have been complied with in respect to payment for sub-subcontract works.”
“The Claimant seeks a declaration that: a. Clause 21.4 provides for pre-requisites for payment for the sub-subcontract works and that the Defendant has not complied with the pre-requisites. b. As a result, no further payment is due to the Defendant and the Court should decline to enforce the Decision.”
“If it obtains the declarations sought, they will take precedence over the Adjudicator’s decision, with the effect that no sum will be due to the Defendant.”
“The proper approach to parallel proceedings was outlined by O'Farrell J in Structure Consulting Limited v Maroush Food Production Limited[2017] EWHC 962 (TCC) . The judge should usually give judgment on the claim based on the adjudicator's decision and then – to the extent possible – endeavour to sort out the Part 8 proceedings. The same point was made in Hutton Construction Limited v Wilson Properties (London) Ltd[2017] EWHC 517 (TCC) ;[2017] BLR 344 , where the judge said that the Part 8 claim should be dealt with after the enforcement, unless the point raised was straightforward and self-contained, and the parties were agreed that it could be dealt with at the enforcement application without adding to the time estimate.”
“However, in cases where an adjudicator has made a clear error (but has acted within his jurisdiction), it may on occasions be appropriate to bring proceedings under Part 8 for a declaration as a pre-emptive response to an anticipated application to enforce the decision. In light of this guidance, a practice had grown up of applications to enforce an adjudicator’s decision being met by an application for a declaration that the adjudicator had erred often without proceedings under Part 8 being commenced. This approach was disruptive and not in accordance with the spirit of the TCC’s procedure for the enforcement of adjudicator’s decisions. It is emphasised, therefore, that such cases are limited to those where: a) There is a short and self-contained issue which arose in the adjudication and which the defendant continues to contest; b) That issue requires no oral evidence, or any other elaboration beyond that which is capable of being provided during the interlocutory hearing for enforcement; c) The issue is one which, on a summary judgment application, it would be unconscionable for the court to ignore; and further that there should in all cases be proper proceedings for declaratory relief.”
“Warnings have continued to be given as to the over-liberal and inappropriate use of Part 8 in adjudication cases: see Jefford J in Merit Holdings Ltd v Michael J Lonsdale Ltd[2017] EWHC 2450 (TCC) ; [2017] 174 Con LR 92, and Ms Joanna Smith QC (as she then was) in Victory House General Partner Linted v RGB P&C Limited[2018] EWHC 102 (TCC) .”
“A claimant may, unless any enactment, rule or practice direction states otherwise, use the Part 8 procedure where they seek the court’ decision on a question which is unlikely to involve a substantial dispute of fact.”
“[298] It is trite law that, if one party’s obligation to do something under a contract is contingent upon the happening of a particular event, the circumstances of the event must be identified unambiguously in the contract. It must be clear beyond doubt how and in what circumstances the relevant obligation has been triggered…”
“The Sub-subcontracts provided by HD4 October 2022 are in no way compatible with the SBS IPS S/C”