“8.88 Secondly as articulated by 3CL it is clear that by reviewing the document that it was intended to be a Pay Less Notice”
“23. If an adjudicator has it in mind to determine a point wholly or partly on the basis of material that has not been put before him by the parties, he must give them an opportunity to make submissions on it. For example, he should not arrive at a rate for particular work using a pricing guide to which no reference had been made during the course of the referral without giving the parties an opportunity to comment on it. 24. By contrast, there is no rule that a judge, arbitrator or adjudicator must decide a case only by accepting the submissions of one party or the other. An adjudicator can reach a decision on a point of importance on the material before him on a basis for which neither party has contended, provided that the parties were aware of the relevant material and that the issues to which it gave rise had been fairly canvassed before the adjudicator. It is not unknown for a party to avoid raising an argument on one aspect of its case if that would involve making an assertion or a concession that could be very damaging to another aspect of its case.”
“26. Mr Cleaver relied on ABB Ltd v BAM Nuttall Ltd[2013] EWHC 1983 (TCC) ;[2013] BLR 529 ; 149 Con LR 172, another decision of Akenhead J, in which the court emphasised that the court should be slow to speculate upon what an adjudicator would, should, or could have done or decided if he had not gone on the particular frolic of which complaint is made. In that case, the adjudicator determined important parts of the dispute by reference to a particular clause which had not featured in submissions or in exchanges between the parties and the adjudicator. At the summary judgment application, the party seeking to enforce the decision argued that, on the merits of the relevant point, the adjudicator’s decision was substantively correct as a matter of construction. Akenhead J considered that “it is not really for the court to rule on this as it should have been for the adjudicator, having raised it (which he did not before his decision) and heard argument on it to decide this type of point. I am satisfied that there is at least a respectable and probably convincing argument that [the clause does not apply].”
“23.1. No waiver by J & B Hopkins of any breach of the Sub-Contract by the Sub-Contractor shall be a waiver of any subsequent breach of the same or of any other provision of the Sub-Contract. No failure by J & B Hopkins to exercise any right or remedy arising under the Sub-Contract or at law shall be a waiver of its right to exercise such rights arising subsequently.”
“Whilst it is clear that, for performance of a provision in a contract to be a condition precedent to the performance of another provision, it is not necessary for the relevant provision to use the express words ‘condition precedent’ or something similar, nonetheless the court has to consider whether on the proper construction of the contract that is the effect of the provisions.”
“It is a matter of fact and degree as to whether the information and supporting documentation supplied in respect of any claim within an application is sufficient to comply with the substantiation requirement in section 462. However, although deficiency in substantiation of a claim might justify rejection of such claim, in part or in full, it would not of itself render the application invalid.”
“in support of our application we attach the following: 1 [copies of insurance certificates for: 1.1 [..] 2 photographs of [..] as evidence of the completion of the Milestone; and 3 [detail any other supporting information as may be stated in the Employer's Requirements and/or any Order and/or the Payment Schedule, or any other information as may be reasonably required by the Employer].”
“45. Where parties to a transaction proceed on the basis of an underlying assumption on which they have conducted their dealings between them, neither will be allowed to go back on that assumption when it would be unfair or unjust to do so: Amalgamated Property Company v Texas Bank[1982] 1 QB 84 (CA) per Lord Denning pp.121-122; Brandon LJ pp.131. 46. The essential requirements of estoppel by convention were set out in the cases of Mears Ltd v Shoreline Housing Partnership Ltd[2015] EWHC 1396 per Akenhead J at Para.51; and HM Revenue & Customs v Benchdollar Ltd[2009] EWHC 1310 per Briggs J at Para.52. There must be a shared assumption communicated between the parties in question. The party claiming the benefit of the convention must have relied on the assumption. It must be unconscionable or unjust to permit the other party to assert the true position. The estoppel by convention can come to an end and will not apply to future dealings once the common assumption is revealed to be erroneous.”
“application date end of month … valuations monthly as per attached payment schedule end of month. Payment terms 30 days from invoice as per attached payment schedule. S/C payment cert must be issued with invoice”
“I do not consider, even aside from the fact that it predates the amendments to the Act, that that case drives a different conclusion. Alstom was a case where the due date was ascertained by reference to a certificate, and the final date for payment was then seven days after that. It was not therefore at all at odds with what I have noted above”
“30.3.6 The final date for payment of an amount due in an Interim Payment shall be 14 days from the receipt by [RBSTB] of [VHE’s] Application for Interim Payment or within 28 days from the date of receipt by [RBSTB] from [VHE] of a copy of each Application for Interim Payment together with an appropriate VAT invoice… whichever is the later.”
“Section 110(1)(b) provides that every construction contract shall provide for a final date for payment in relation to any sum which becomes due, and that the parties are free to agree how long the period is to be between the date on which a sum becomes due and the final date for payment. It is not, as I understand it, in dispute that here clause 30.3.6 (paragraph 3 above) complied with that requirement, and I so find”
“59. Accordingly, I consider that the alternative construction is correct with the result that, where there has been no payment notice under clause 7.4, the final date for payment is either 30 days from the due date for payment or 30 days from the issue of a VAT invoice, whichever is later. Where there has been a payment notice, the final date for payment is the later of either 30 days from the due date for payment or the receipt by the Client of a revised VAT invoice which corresponds with the sum stated in the payment notice. 60. For these reasons, since no VAT invoice has been issued in respect of the sum claimed, VL’s claim must fail on this ground also.”