“The Adjudicator is requested to review and decide the matters pertaining to the Referring Party’s claim for the breaches and subsequent Final Account for outstanding monies/late payment considered due for the works to the Moulescoomb project in the sum of£455,526.53 plus VAT or other such sums as the Adjudicator shall determine ….”
“2. This Witness Statement is made in support of the Defendant’s Application for a Stay of Execution of the Approved Judgment [HT-2022-000444] dated15 February 2023 . “3. I make this Statement from the facts and matters within my own knowledge, which are contained within the files maintained by the Defendant in respect of this matter. Where I refer to facts and matters outside my own knowledge, I identify the source of those facts and matters. I confirm that the contents of this Statement are true to the best of my knowledge and belief. “4, I make this statement to support that everything [which] is stated in the Defendants [A&V] submissions in relation to the Approved Judgment and Cost is true.”
“Ground 1: “Pending the outcome of the High Court “Sealed”
“The Defendant is unable to pay to the Claimant the judgment sum of£110,880.88 if ordered to do so [please refer to appendix 3 below] “Ground 3: “The Defendant will be forced to stop trading and go into insolvency if ordered to pay the judgment sum of£110,880.88 [please refer to appendix 4 below] “Ground 4: “The Defendant cannot afford to refer this dispute to a Court of Arbitration if A&V must pay the summary judgment first in the sum of£110,880.88 . “Ground 5: “The Defendants’ rights and the fair opportunity to refer this dispute to a Court of Arbitration will be prevented if A&V must pay the summary judgment sum first.”
“Brief details of claim “1. The Claimant issued its Letter of Claim dated2 December 2022 in accordance with Pre-Action Protocol for Construction and Engineering Disputes via email and post on2 December 2022 . “2. The Letter of Claim was received by the Defendant on5 December 2022 via the post office. “3. The Defendant acknowledge[d] receipt of the Letter of Claim via email on16 December 2022 . “4. In Accordance with paragraph 8.5 of the Protocol the Defendant should have [sent] a letter of response to the Claimant within 28 days from the date of receipt of the Letter of Claim (on or before2 January 2023 ) “5. Today’s date is9 January 2023 (7 days behind the allowed timeframe) and the Defendant has not provided any Response, Defence or Counterclaim. The Defendant failed to comply with the Protocol. 6. The Defendant has not complied with the Protocol. It has made no payments to the Claimant in respect to the Final Account. “The Claimant therefore seeks Judgment in Default to be entered against the Defendant. “Value “1.£276,917.63 plus VAT and Court Fee (sum due for the Final Account of the Sub-Contract) “2.£34,800 (sum due for [Adjudicator] Mr Keith Blizzard for Adjudication 1) “3.£9,600 (legal cost incurred by the Claimant in Part 8 proceedings related to Final Account) “4.£7,140 (legal cost incurred by the Claimant in Enforcement proceedings related to Final Acc) “5.£21,840 (legal cost incurred by the Claimant in Court of Appeal proceedings related to F. Acc)”
“The Parties: “The Claimant is and was at all material times a mechanical sub-contractor. “The Defendant is and was at all material times a mechanical and electrical services contractor. “Summary: “The Claimant is entitled to and hereby seeks Judgment in Default to be entered against the Defendant and claims all the sums 1,2,3,4 and 5 shown in Value above as a debt due under the Sub-Contract, and the cost of [these] proceedings to be paid by the Defendant. “Further to the Claimant Final Account letter dated26 May 2022 (letter attached) matters of the Final Account have not been satisfactorily concluded between the parties. The Defendant has not provided any meaningful response to the Claimant and matters of the Final Account only being commented upon by the Defendant in Adjudication 3. The Claimant have sought to proceed to refer the matter to the Courts and issued its Letter of Claim on2nd December 2022 via email and recorded delivery and in accordance with the Pre-Action Protocol for Construction and Engineering Disputes (letter attached). The Defendant acknowledges receipt of the Letter of Claim via email on16 December 2022 (email/letter attached). In accordance with paragraph 8.5 of the Protocol, the Defendant should have sent a letter of response to the Claimant within 28 days from the date of receipt of the Letter of Claim respectively on or before2 January 2023 . To date9 January 2023 (7 days behind the allowed timeframe) the Defendant has not provided any response, defence or counterclaim. The Defendant has failed to comply with the Pre-Action Protocol for Construction and Engineering Disputes. In Accordance with paragraph 8.6 of the Protocol the Claimant is now permitted to commence proceedings against the Defendant without further compliance with the Protocol as no response has been received by the Claimant within 28 days. “The true value of the Sub-Contract works was£675,687.27 and based on the Defendant’s previous payments to date (£364,909.64 ) this notes a total sum due and outstanding of£276,917.63 plus VAT. “Failure to comply with the Protocol “As a result of the Defendant’s failure to comply with the Pre-Action Protocol for Construction and Engineering Disputes, the Claimant is now entitled to commence proceedings without further compliance with the Protocol. “The Claimant is entitled to and hereby seeks Judgment in Default to be entered against the Defendant and claims all the sums 1,2,3,4 and 5 shown in Value above as a debt due under the Sub-Contract, and the costs of [these] proceedings to be paid by the Defendant.”
“An application for: “(1) A stay of these proceedings unless and until the Claimant complies with an adjudicator’s decision in the Defendant’s favour on the final account. The Defendant has already obtained a judgment from the Court enforcing the decision. “(2) Summary judgment and/or strike our underCPR 3.4 (2) of the whole, alternatively parts of, the Particulars of Claim on the Claim Form because the Claimant does not have a better than arguable case and/or there are no reasonable grounds for bringing the claim those parts of Claim Form. The Defendant’s attention is drawn toCPR 24.5 (1). “(3) If the claim for the final account sum is pursued on a true value basis, strike out of paragraph 1 under “Value” on the Claim Form underCPR 3.4 (2)(b) and/or (c) because the lack of particulars is likely to obstruct the just disposal of the proceedings and/or a failure to comply with the CPR rules. In the alternative, JBH seeks an order requiring the Claimant to [serve an] amended CPR compliant Particulars of Claim. “(4) Security for costs underCPR 25.12 , namely an order that the Claimant gives security for the Defendant’s costs of these proceedings up [to] the first CMCC by paying into court the sum of£30,000 , or such other sum as the court deems fit, within 7 days of the order. The application is made because the Defendant considers that the condition inCPR 25.13 (2)(c) is satisfied: the Claimant is a company and there is reason to believe that it will be unable to pay the Defendant’s costs if ordered to do so. “(5) An extension of time for the Defence until after the above applications are decided.”
“(a) there are special circumstances which render it inexpedient to enforce the judgment or order, or (b) the applicant is unable from any reason to pay the money.”
“52. Further or alternatively, even if the Court considers (contrary to the above) that A&V has demonstrated it is unable to pay the Enforcement Sum, JBH submits that the Court should refuse to exercise its discretion to do so. JBH relies, in particular, on the following factors: “52.1 Firstly, the “pay now, argue later” policy behind adjudication and clause 20.3 of the Sub-Contract (“The decision of the adjudicator shall be binding until the dispute is finally determined by legal proceedings or by agreement.” [D/8/47]) are analogous to a no-set off clause. Applying the principles set out in Andrew v Flywheel, it should be a very rare case in which the Court would grant a stay of execution of a judgment enforcing an adjudicator’s decision until legal proceedings on the same dispute are determined. “52.2 This principle applies even more strongly in this case given that it was A&V which commenced the Final Account Adjudication. A&V chose to pursue the dispute as to the final account in adjudication first…..” “52.1 Firstly, the “pay now, argue later” policy behind adjudication and clause 20.3 of the Sub-Contract (“The decision of the adjudicator shall be binding until the dispute is finally determined by legal proceedings or by agreement.” [D/8/47]) are analogous to a no-set off clause. Applying the principles set out in Andrew v Flywheel, it should be a very rare case in which the Court would grant a stay of execution of a judgment enforcing an adjudicator’s decision until legal proceedings on the same dispute are determined. “52.2 This principle applies even more strongly in this case given that it was A&V which commenced the Final Account Adjudication. A&V chose to pursue the dispute as to the final account in adjudication first…..”
“We are in receipt of your email/letter dated 05.05.2023. “Please note that I am on my annual leave until the 22nd of May 2023. Therefore, I am unable to respond or to get in contact with our accountant until the 22nd of May 2023. “However, and until then [22.05.2023] I can assure you that A&V Building Solution is not and has never been insolvent. “Also, I can assure you that the up to date information regarding A&V’s financial position and your client [J&B] breaches would be formally provided to the Court prior to the forthcoming application hearing dated 01.06.2023. “Until then, I would suggest that HK Legal and your client J&B Hopkins stop searching for my name on LinkedIn and all others social media profiles. I believe that our case/dispute it is commercial dispute between two companies and not a personal matter.”