“Without prejudice to the claimant’s obligation arising undersection 111(1) of the Housing Grants, Construction and Regeneration Act 1996 as amended (“the Act”) to pay the “notified sum,” the claimant is entitled to dispute such valuation if and insofar as it conflicts with what the parties have agreed is to be paid at clauses 4.7 and 4.14 of the contract conditions, and to refer such dispute to adjudication or other proceedings.”
“In relation to each Interim Payment, the Contractor shall make an application to the Employer (an ‘Interim Application’) in accordance with the following provisions of this clause 4.8, stating the sum that the Contractor considers to be due to him and the basis on which that sum has been calculated.”
“Where Alternative B applies, for the period up to practical completion of the Works, Interim Applications shall be made as at the monthly dates specified in the Contract Particulars for Alternative B up to the date of practical completion or the specified date within one month thereafter… The due date in each case shall be the later of the specified date and the date of receipt by the Employer of the Interim Application.”
“Interim Applications may be made on or after completion of the relevant stage or the monthly date and shall be accompanied by such further information as may be specified in the Employer’s Requirements.”
“1. At least 2 days before the established dates for interim payments submit to the Employer’s Agent a detailed application for amounts due under the Contract together with all necessary supporting information. 2. Such application details are to be based on the elemental breakdown of the Contract Sum Analysis to the approval of the Quantity Surveyor including: Percentage completions in respect of each element of the Contract Sum Analysis … Supporting evidence of the above by means of progress reports … Full substantiation of all sums claimed in respect of changes including labour, plant and material expenditure, detailed calculations, measurements and invoices (where applicable) together with a copy of the instruction giving rise to the change ... No variations will be included in the valuation until a valid Change Order is issued. Comprehensive list of materials on site with proof of cost. 3. At the same time submit a statement from each of the specialist sub-contractors stating: The gross amount claimed for inclusion in the current valuation …”
“We refer to the … purported Pay Less Notice referencing instalment No.19 … Any queries we have in relation to the certificate/notice which has been issued will continue but will not hold up our invoice.”
“We refer to the above Contract and to the purported Pay Less Notice referencing instalment No.19 dated the12th August 2016 and to our invoice no. 54364 dated31st July 2016 , a copy of each of which we attach for ease of reference. The contractual final date for payment of the certified and invoiced sum of£78,224.26 is19th August 2016 , however, as at today’s date, payment still remains outstanding. We therefore wish to record the following and hereby provide notice accordingly: Under clause 4.9.5, we are entitled to be paid simple interest on the outstanding sum … Under clause 4.11, we give you notice that we intend to suspend all or part of the performance of our contractual obligations, on the ground that you have failed to make payment in accordance with the Contract, should the above sum not be paid within 7 days after the date of this notice. We note that we will also seek to recover our costs and expenses incurred in the exercise of this right. In the meantime, our rights remain reserved in their entirety, including our right to commence adjudication or court proceedings to recover the above and any other sums properly due under the Contract.”
“The doctrine of approbation and reprobation requires for its foundation inconsistency of conduct as, where a man, having accepted a benefit given him by a judgment, cannot allege the invalidity of the judgment which conferred the benefit.”
“If the Employer intends to pay less than the sum stated as due from him in the Payment Notice or Interim Application, as the case may be, he shall not later than 5 days before the final date for payment give the Contractor notice of that intention in accordance with clause 4.10.2 (a ‘Pay Less Notice’). Where a Pay Less Notice is given, the amount of the Interim Payment to be made by the Employer on or before the final date for payment shall be the sum stated as due in the Pay Less Notice.”
“Any notice, certificate or other communication (notice) to be given under Section 4 (Payment) may, in addition to any other permitted method of service, be delivered by hand or sent electronically to the e-mail address of the addressee, provided, if sent by email and not delivered by hand, a copy is sent on the same day to the addressee by pre-paid first class post. Any notice served in accordance with this clause 1.7.3A takes effect as being given and served: (a) if delivered by hand or sent by email by 4.00 pm on a Business Day, on that day; but otherwise (b) on the next Business Day.”
“In a case where this subsection applies, the decision of the adjudicator referred to in subsection (8) shall be construed as requiring payment of the additional amount not later than – (a) seven days from the date of the decision, or (b) the date which apart from the notice would have been the final date for payment, whichever is the later.” whichever is the later.”
“(a) Adjudication (whether pursuant to the 1996 Act or the consequential amendments to the standard forms of building and engineering contracts) is designed to be a quick and inexpensive method of arriving at a temporary result in a construction dispute. (b) In consequence, adjudicators' decisions are intended to be enforced summarily and the claimant (being the successful party in the adjudication) should not generally be kept out of its money. (c) In an application to stay the execution of summary judgment arising out of an adjudicator's decision, the court must exercise its discretion under Order 47 with considerations (a) and (b) firmly in mind (see AWG). (d) The probable inability of the claimant to repay the judgment sum (awarded by the adjudicator and enforced by way of summary judgment) at the end of the substantive trial, or arbitration hearing, may constitute special circumstances within the meaning of Order 47 rule 1(1)(a) rendering it appropriate to grant a stay (see Herschell). (e) If the claimant is in insolvent liquidation, or there is no dispute on the evidence that the claimant is insolvent, then a stay of execution will usually be granted (see Bouygues and Rainford House). (f) Even if the evidence of the claimant's present financial position suggested that it is probable that it would be unable to repay the judgment sum when it fell due, that would not usually justify the grant of a stay if: (i) the claimant's financial position is the same or similar to its financial position at the time that the relevant contract was made (see Herschell); or (ii) The claimant's financial position is due, either wholly, or in significant part, to the defendant's failure to pay those sums which were awarded by the adjudicator (see Absolute Rentals).”