“Evidence of pre-contractual negotiations is not generally admissible to interpret the concluded written agreement. But evidence of pre-contractual negotiations is admissible to establish that a fact was known to both parties; … to determine which party put forward a particular term This is only admissible where the contra proferentum principle is in play: Lewison at 3.55. ; and to elucidate the general object of the contract. Evidence that parties negotiated on the basis of an agreed meaning is only admissible in support of a claim of estoppel or rectification.”
“Where the contract is a standard form of contract to which the parties have added special conditions, then unless the contract otherwise provides greater weight must be given to the special conditions, and in case of conflict between the general conditions and the special conditions, the latter will prevail. However, in interpreting a standard form there is less room for the influence of the special background applicable to any particular transaction.” “Where a contract contains general provisions and specific provisions, the specific provisions will be given greater weight than the general provisions where the facts to which the contract is to be applied fall within the scope of the specific provisions.”
“The Contractor has examined the Employer's Requirements and is satisfied: (a) that they have been prepared in compliance with the Statutory Requirements; (b) that the Contractor’s Proposals meet the Employer’s Requirements and that there is no discrepancy within and/or between these two documents; and (c) where the Employer’s Requirements contain elements of design, such design has been carried out with proper skill, care and diligence.”
“1. The Contractor has had an opportunity to inspect the physical conditions (including the sub-surface conditions) and all other conditions of or affecting the site and shall be deemed to have fully acquainted himself with the same and to have obtained all necessary information as to risks, contingencies and all other circumstances which may influence or affect the execution of the Works. 2. Any information prepared by or on behalf of the Employer (including any survey, report or document) relating in whole or in part to the physical conditions (including sub-surface conditions) and other conditions of or affecting the site is provided for information only. The Employer and the Employer’s Persons make no representation or warranty as to accuracy or completeness of any such information or for any representation or statement contained therein whether made by the Employer or the Employer’s Persons for misrepresentation or misstatement whether made negligently or otherwise in respect of such information. 3. No failure on the part of the Contractor to discover or foresee any physical conditions and/or other conditions affecting the site and/or any risks, contingencies or other circumstances whatsoever referred to in Clause 2.40.1 (whether the same ought reasonably to have been discovered or foreseen or not) shall entitle the Contractor to an adjustment of the Contract Sum or an adjustment of the Date for Completion of the Works or any Section thereof.”
“Employer’s Requirements. Pursuant to the Conditions of Contract, the Employer requires the following to be designed, constructed, and installed by the Contractor. All works are to comply with the relevant British Standards and Codes of Practice. Stair Pressurisation. The work to be executed shall comprise the design, supply, erection, adjusting, connection, testing and setting to work and commissioning of the Stair Pressurisation Installation all as described in the respective sections of this document to form a complete installation. The ‘complete installation’ shall mean not only the major items of plant, equipment and/or apparatus detailed but shall include all the incidental sundry components necessary for the complete execution of the work and for the proper operation of the stair pressurisation system installation all as per FHPP drawings and specifications. Builder’s Work in Connection with Services. The scope of builder’s work includes, but is not limited to the following and is subject to approval by Building Control. Any necessary work associated with the stair pressurisation installation and the asbestos removal works. Holes for new cabling, containment systems and ductwork to allow pass through at riser floors and walls. Fire stopping for sealing of new cabling, containment systems and ductwork to allow pass through at riser floors and walls. Protection to the risers, services, floors and walls. Alteration to the existing risers and plantroom. Asbestos Removal Works. The scope of asbestos removal works includes, but is not limited to, the phased removal and disposal of all asbestos containing material identified in a safe and compliant way. These works shall include an environmental clean within the existing service risers following successful completion of the above. All works are subject to provision of ‘clean air’ certification on completion. All tickets, documents demonstrating safe disposal of all material to be provided. All works to be executed by a registered specialist contractor.”
“1 – The Works. 1.1. An outline description of the works is included in the preliminaries document and shall be deemed to form part of the Schedule of Employer's Requirements. 1.2. The contractor shall note that the Employer’s Requirements shall not be relied upon as fully indicative of the extent works. The contractor is to use their experience to identify any additional elements of work that would be required in undertake the project works. This shall include all temporary works, phasing and additional detailing required. 2 – Drawings & Specifications 2.1. The successful contractor will be required to take on the Design and develop it through to completion.”
“1. Report: Included in the tender documents. Any such report is for information only. 2. New Item: It is the Contractor’s responsibility to undertake his own investigations or verify existing information as necessary.”
“1. Description: The works shall include but not be limited to: Strip out and removal of the existing redundant stair pressurisation equipment and redundant plant room ductwork for staircases A and B thorough testing and analysis has been carried out by the contractor. Strip out will include but may not be limited to the pressurisation fans and associated ductwork. … Removal under controlled conditions of all works related to asbestos containing materials and all asbestos containing materials. Builders Work in Connection with Services including all temporary and permanent works …”
“1. Duty: Check proposed methods of work for effects on adjacent structures inside and outside the site boundary. 2. Supports: During execution of the Works: 2.1. Provide and maintain all incidental shoring, strutting, needling and other supports as may be necessary to preserve stability of existing structures on the site or adjoining that may be endangered or affected by the Works; 2.2 Do not remove until new work is strong enough to support existing structure; 2.3 Prevent overstressing of completed work when removing supports.”
“The scope of works shall generally include the complete supply and installation, connection, testing and commissioning and setting to works of the new mechanical systems as detailed in this specification and on the tender layout drawings”
“The works shall include but not be limited to:- Strip out, and removal of the existing stair pressurisation equipment and redundant plant room ductwork for both staircases A and B that cannot be re-used after thorough testing and analysis has been carried out by the contractor. Strip out will include but may not be limited to the pressurisation fans associated ductwork. The contractor shall allow for the diversion or removal of any other unrelated services that interfere with the stripping out of required systems. The installation of new fans within the plant room in which the existing fans have been removed. The fans shall connect to the existing ductwork only if the contractor can prove the ductwork is in a suitable state to re-use. If the ductwork is not in a suitable condition, replacement of the ductwork shall be within the contractors works… CFD analysis shall be carried out by the contractor to prove the design will operate as intended. (CFD is short for Computational Fluid Dynamics.)”
“The contractor shall allow for the strip out works as per the strip out drawings, however these drawings are indicative only and cannot be considered a complete scope of works”
“After the Design process has been completed by the contractor and due to the fact there are no air release paths within the modified class C design the proposals will need to be assessed though a CFD study to establish whether the system will achieve a satisfactory standard of safety for means of escape and firefighting operations. CFD analysis shall be in line with the fire report in Appendix A”
“Section 0001: Stair Core A”
“Quote from specialist Supplier (Copy of Quote attached)”
“In order to manage the risk from asbestos in non-domestic premises, the dutyholder must ensure that a suitable and sufficient assessment is carried out as to whether asbestos is or is liable to be present in the premises”
“If after the Date of Possession… but before practical completion of the Works the carrying out of the whole or substantially the whole of the uncompleted Works is suspended for a continuous period of [2 months] by reason of any impediment, prevention or default, whether by act or omission, by the Employer or any Employer’s Person, then, unless it is caused by the negligence or default of the Contractor or any Contractor’s Person, the Contractor may give to the Employer a notice specifying the event or events (a ‘specified’ suspension event or events).”
“If a specified default or a specified suspension event continues for 14 days from the receipt of notice under clause … 8·9·2, the Contractor may on, or within 21 days from, the expiry of that 14 day period by a further notice to the Employer terminate the Contractor’s employment under this Contract.”
“An act of prevention may be (a) a breach of an express or implied contractual obligation; and also (b) the exercise of an entitlement (such as the giving of an instruction). It will not be the happening of an event for which the parties have otherwise agreed the allocation of risk within the contract. The concept of ‘prevention’ is, therefore, itself rooted in consideration of the parties’ express or implied obligations…”
“We confirm that [B&F] has been unable to continue to carry out and complete the Contract works since8 December 2021 in view of the following issues: 1. Schroder has failed to procure a refurbishment and demolition survey (RDS) and in view of the extent of asbestos discovered, particularly by reference to the asbestos register for the site, our team is unable to safely access the site. We note that Schroder have refused our requests for a RDS to be carried out or for instructions to arrange for the same (see for example, progress report no.10). 2. We are also unable to access floors 11, 15, 16, 17 and 18 within Riser B because structural reinforcement bars have been cut away in these areas and no structural supports have been installed. We have advised you that reinforcement works are required and requested an instruction (see for example, our correspondence to the Employer's Agent dated3 December 2022 ). However, no such instruction has been provided. We confirm that the above issues constitute impediments, acts of prevention and/or default by the Employer which have resulted in the whole (or substantially the whole) of the uncompleted Works having been suspended for a continuous period since8 December 2021 . These issues are therefore "specified" suspension events as defined by clause 8.9.2 of the Contract. Accordingly, this letter constitutes a notice pursuant to clause 8.9.2. Should a "specified” suspension event continue for 14 days from receipt of this notice, we reserve the right to terminate our employment under the Contract in accordance with clause 8.9.3.”