“We write further to your application for payment email dated24 July 2024 . We provide our Pay less notice underparagraph 10 of Part II of the Scheme for Construction Contracts (England and Wales) Regulations 1998 (SI 1998/649) (as amended) andsection 111 of the Housing Grants, Construction and Regeneration Act 1996 (as amended). We consider that the gross amount due on the date this notice is served to be£2,769,275.56 (excluding retention and VAT) in accordance with our assessment of the works reference Esh Winning - Car Construction - Valuation 30 which has been enclosed for your information.”
“Payment notices: contractual requirements 110A.— (1) A construction contract shall, in relation to every payment provided for by the contract— (a) require the payer or a specified person to give a notice complying with subsection (2) to the payee not later than five days after the payment due date, or (b) require the payee to give a notice complying with subsection (3) to the payer or a specified person not later than five days after the payment due date. (2) A notice complies with this subsection if it specifies— (a) in a case where the notice is given by the payer— (i) the sum that the payer considers to be or to have been due at the payment due date in respect of the payment, and (ii) the basis on which that sum is calculated; (b) in a case where the notice is given by a specified person— (i) the sum that the payer or the specified person considers to be or to have been due at the payment due date in respect of the payment, and (ii) the basis on which that sum is calculated. (3) A notice complies with this subsection if it specifies— (a) the sum that the payee considers to be or to have been due at the payment due date in respect of the payment, and (b) the basis on which that sum is calculated. (4) For the purposes of this section, it is immaterial that the sum referred to in subsection (2)(a) or (b) or (3)(a) may be zero. (5) If or to the extent that a contract does not comply with subsection (1), the relevant provisions of the Scheme for Construction Contracts apply. (6) In this and the following sections, in relation to any payment provided for by a construction contract— “payee” means the person to whom the payment is due; “payer” means the person from whom the payment is due; “payment due date” means the date provided for by the contract as the date on which the payment is due; “specified person” means a person specified in or determined in accordance with the provisions of the contract. Payment notices: payee’s notice in default of payer’s notice 110B.—(1) This section applies in a case where, in relation to any payment provided for by a construction contract— (a) the contract requires the payer or a specified person to give the payee a notice complying with section 110A(2) not later than five days after the payment due date, but (b) notice is not given as so required. (2) Subject to subsection (4), the payee may give to the payer a notice complying with section 110A(3) at any time after the date on which the notice referred to in subsection (1)(a) was required by the contract to be given. (3) Where pursuant to subsection (2) the payee gives a notice complying with section 110A(3), the final date for payment of the sum specified in the notice shall for all purposes be regarded as postponed by the same number of days as the number of days after the date referred to in subsection (2) that the notice was given. (4) If— (a) the contract permits or requires the payee, before the date on which the notice referred to in subsection (1)(a) is required by the contract to be given, to notify the payer or a specified person of— (i) the sum that the payee considers will become due on the payment due date in respect of the payment, and (ii) the basis on which that sum is calculated, and (b) the payee gives such notification in accordance with the contract, that notification is to be regarded as a notice complying with section 110A(3) given pursuant to subsection (2) (and the payee may not give another such notice pursuant to that subsection). Requirement to pay notified sum 111.— (1) Subject as follows, where a payment is provided for by a construction contract, the payer must pay the notified sum (to the extent not already paid) on or before the final date for payment. (2) For the purposes of this section, the “notified sum” in relation to any payment provided for by a construction contract means— (a) in a case where a notice complying with section 110A(2) has been given pursuant to and in accordance with a requirement of the contract, the amount specified in that notice; (b) in a case where a notice complying with section 110A(3) has been given pursuant to and in accordance with a requirement of the contract, the amount specified in that notice; (c) in a case where a notice complying with section 110A(3) has been given pursuant to and in accordance with section 110B(2), the amount specified in that notice. (3) The payer or a specified person may in accordance with this section give to the payee a notice of the payer’s intention to pay less than the notified sum. (4) A notice under subsection (3) must specify— (a) the sum that the payer considers to be due on the date the notice is served, and (b) the basis on which that sum is calculated. It is immaterial for the purposes of this subsection that the sum referred to in paragraph (a) or (b) may be zero. (5) A notice under subsection (3)— (a) must be given not later than the prescribed period before the final date for payment, and (b) in a case referred to in subsection (2)(b) or (c), may not be given before the notice by reference to which the notified sum is determined. (6) Where a notice is given under subsection (3), subsection (1) applies only in respect of the sum specified pursuant to subsection (4)(a). (7) In subsection (5), “prescribed period” means— (a) such period as the parties may agree, or (b) in the absence of such agreement, the period provided by the Scheme for Construction Contracts. (8) .. (9) ..”
“36. This regime depends on the issue of a series of notices whereby the payer becomes liable to pay “the notified sum”
“…to require an employer at periodic intervals to pay “the notified sum” by the final date for payment, irrespective of whether or not that sum in fact represents a correct valuation of the work to date. If an employer fails to give relevant notice, irrespective of whether this is by mistake, administrative oversight or any other reason, then a sum for which the contractor has applied becomes immediately contractually payable, even if it is wrong in valuation terms.” 38. This can have severe, if not draconian, consequences for a party who fails to serve a pay less notice. However, that is the acknowledged effect of the statutory provisions, always assuming that the application for payment is made with sufficient clarity and provides reasonable notice that the payment period has been triggered in the first place (see Caledonian Modular Ltd v Mar City Developments Ltd[2015] BLR 694 , per Coulson J (as he then was) at [35]-[37]). 39. The conventional sequence of notices contemplated by the statutory regime is for (i) an application for payment to be made by the payee (section 110(B)(4) of the Act). This provides an opportunity for the payee to set out the amount it considers to be due to it at the relevant date, calculated in accordance with the valuation provisions; (ii) a payment notice by the payer (section 110(A)(1) of the Act), setting out the amount it considers due as at the relevant date, calculated in accordance with the valuation provisions and (iii) a pay less notice by the payer (section 111(3) of the Act), again setting out the amount it considers due but taking into account any deductions or cross claims available to it. Depending on which of these notices is actually served, section 111(2) of the Act identifies which should prevail as the notified sum. In this case, and in the absence of service by Advance of a payment certificate, there appears to be no dispute that the notified sum is the sum contained in Application 24. 40. The Amended Particulars of Claim set out the statutory provisions in some detail. As Sir Rupert Jackson made clear in the Court of Appeal in S&T (UK) Ltd v Grove Developments Ltd[2019] BLR 1 at [42], section 111 of the Act imposes direct obligations on contracting parties such that in the event of contractual terms providing something different, they are overridden. Where the contractual terms are compliant with the Act “they are a mere aide memoire – what matters are the statutory provisions. The Act requires the Employer to pay the “notified sum” by the final date for payment, unless it has specified a lesser sum in a timeous Payment Notice or a timeous Pay Less Notice.”
“The older cases talk about certificates, because that was the method by which the financial relationship between the employer and the contractor was regulated. Now, largely due to the 1996 Act, the standard forms of contract focus instead on notices and applications. But there is no essential difference: they are simply the means by which interim payments (and the final payment) are made.”