“all activities rendered by CONTRACTOR to PTT in connection with the Project.”
“ARTICLE 12. LIABILITY AND RESPONSIBILITY 12.1 CONTRACTOR shall exercise all reasonable skill, care and diligence and efficiency in the performance of the Services under the Contract and carry out all his responsibilities in accordance with recognized international professional standards. [...] 12.3 CONTRACTOR shall be liable to PTT for any damage suffered by PTT as a consequence of CONTRACTOR’s breach of contract, including software defects or inability to perform ‘Fully Complies’ or ‘Partially Complies’ functionalities as illustrated in Section 24 of Part III Project and Services. The total liability of CONTRACTOR to PTT under the Contract shall be limited to the Contract Price received by CONTRACTOR with respect to the services or deliverables involved under this Contract. Except for the specific remedies expressly identified as such in this Contract, PTT’s exclusive remedy for any claim arising out of this Contract will be for CONTRACTOR, upon written notice, to use best endeavor to cure the breach at its expense, or failing that, to return the fees paid to CONTRACTOR for the Services or Deliverables related to the breach. This limitation of liability shall not apply to CONTRACTOR’s liability resulting from fraud, negligence, gross negligence or wilful misconduct of CONTRACTOR or any of its officers, employees or agents.”
“ARTICLE 13. INDEMNITY 13.1 Each party shall indemnify, protect, defend and hold harmless the other party, its affiliates and their respective directors, officers, agents and employees from and against all losses, damages, liabilities and claims, including legal expenses, arising out of or relating to the performance or obligation of CONTRACTOR under this Contract, provided that such losses, damages, liabilities and claims shall occur as a consequence of the errors, omissions, negligence or wilful misconduct of the indemnifying party, its personnel or agents on the CONTRACTOR’s part.”
“18.1 Payment shall be made by milestone as indicated in the below table. The CONTRACTOR shall submit invoice to PTT (1 original and 2 copies) along with sign off document of each milestone in section 23, DELIVERABLES of Part III Project and Services.”
“ARTICLE 28. MODIFICATION TO CONTRACT This Contract consists of the Contract document and the Exhibits thereto. Exhibit 1 Letter of Intent Number 4110000917 and Terms of Reference (TOR) For Commodity Trading & Risk Management (CTRM) System, Rev June 13, 2012 Exhibit 2 Technical Document (Clarification) Exhibit 3 Triple Point Software Product Perpetual License Agreement, Software Maintenance Services and Order Form 2012 (dated January 31, 2013) Exhibit 4 Performance Security The Contract constitutes the entire agreement between PTT and CONTRACTOR and shall not be altered, amended or modified except in writing which shall bear the authorized signatures of both parties. ARTICLE 29. ORDER OF PRECEDENCE In the event of a conflict in the provisions of this Contract, the following shall prevail in the order set forth below: 29.1 This Contract 29.2 Exhibit 1 and 2 29.3 Exhibit 3 CONTRACTOR shall immediately refer to PTT for clarification of any such inconsistency.”
“Warranties, Liabilities and Indemnification”
“Triple Point represents and warrants to Licensee that the Maintenance Services and Consulting Services, if applicable, will be provided with its best efforts and professional abilities. Triple Point represents and warrants to Licensee that Licensee’s use of the Licensed Software as contemplated by this Agreement does not infringe any US patent, trademark, trade secret, copyright or similar right of any third party. If the Licensed Software is held, or believed by Triple Point, to so infringe or misappropriate, Triple Point shall have the option, at its expense, to (x) modify the Licensed Software to be noninfringing or (y) obtain for Licensee a license to continue using the Licensed Software, and if (x) or (y) are commercially impractical, then Triple Point may terminate the Software License and refund the Software License Fee paid by Licensee, pro rated over a five year term from the Effective Date.” (b) Paragraph 7.2 provided: “If any third party claim of intellectual property infringement is brought against Licensee arising from Licensee’s use of the Licensed Software licensed under this Agreement in accordance with the terms hereof, Triple Point will indemnify, defend and hold harmless at its own expense, Licensee from and against any and all costs, damages, expenses, liability, suits, claims and proceedings (including reasonable attorneys’ and professional fees) incurred by Licensee as a result of any such suit or action. Licensee shall provide Triple Point with as soon as possible written notice of the suit or action for which indemnity is claimed giving Triple Point sole control of the defence thereof and any related settlement negotiations; and providing all assistance, information and authority reasonably required to defend or settle the suit or action.” (c) Paragraph 7.3 provided: “Triple Point represents and warrants that the Licensed Software will substantially conform to the documentation in all material respects and Triple Point’s sole obligation hereunder shall be to repair any defect in the Licensed Software or replace the Licensed Software that causes it to fail to so conform provided that written notice of such defect is received by Triple Point during the Maintenance Term. Except with respect to the warranty set forth in this section, the Licensed Software, Documentation, Maintenance and Consulting Services are provided ‘as is’ and without warranty of any kind, express or implied, including any implied warranties of merchantability or fitness for a particular purpose. Triple Point does not warrant that the Licensed Software will be free of defects, will operate uninterrupted or error free or will satisfy the operational requirements of Licensee.” (d) Paragraph 7.4 provided: “Without limiting the foregoing, Licensee agrees that the aggregate liability of Triple Point for damages from any cause of action whatsoever, regardless of the form of action, shall not exceed the fees paid to Triple Point under the CTRM Contract and except such damages caused by fraud, gross negligence and wilful misconduct.”
“In no event shall either party be liable for lost profits or indirect, incidental, consequential, special or punitive damages of any nature whatsoever.” (f) Paragraph 10.9 of the PLA provides that that Agreement and the CTRM Contract should constitute the entire agreement and understanding between the parties. The proviso in paragraph 10.9 stated: “Provided, however, that Triple Point agrees that this Agreement shall not supersede and shall be an Annex to the CTRM Contract. In addition, Triple Point agrees that if there is any conflict between the CTRM Contract and this Agreement, the CTRM Contract shall prevail and be enforceable.”
“If the contractor fail to complete the works by the date named in clause 23 … and the architect shall certify in writing that the works could reasonably have been completed by the said date, … the contractor shall pay or allow to the employer the sum of£250 sterling per week for the first four weeks, and£500 per week for all subsequent weeks as liquidated and ascertained damages for every week beyond the said date or extended time, as the case may be, during which the works shall remain unfinished …”
“In my opinion it does not apply, and I think it does not apply for two reasons: first of all, that it is altogether inapt to the provisions made by clause 26, which contain a complete code of themselves; and secondly, because upon its construction I read it as meaning that if the contractors have actually completed the works, but have been late in completing the works, then, and in that case only, the clause applies. Under the circumstances in which this appeal comes before us the contractors have not completed the works; on the contrary, they have been ousted from the works by the employers under their powers given them by clause 26. I am therefore of the same opinion as the learned Judges in the Court of Session, who were unanimous in holding that clause 24 has no application to the present case …”
“110. The textbooks generally treat category (ii) as the orthodox analysis, but that approach is not free from difficulty. If a construction contract is abandoned or terminated, the employer is in new territory for which the liquidated damages clause may not have made provision. Although accrued rights must be protected, it may sometimes be artificial and inconsistent with the parties’ agreement to categorise the employer’s losses as £x per week up to a specified date and then general damages thereafter. It may be more logical and more consonant with the parties’ bargain to assess the employer’s total losses flowing from the abandonment or termination, applying the ordinary rules for assessing damages for breach of contract. In my view, the question whether the liquidated damages clause (a) ceases to apply or (b) continues to apply up to termination/abandonment, or even conceivably beyond that date, must depend upon the wording of the clause itself. There is no invariable rule that liquidated damages must be used as a formula for compensating the employer for part of its loss.”
“112. Let me now turn to article 5.3 in the present case. This clause, like clause 24 in the Glanzstoff case, seems to be focused specifically on delay between the contractual completion date and the date when Triple Point actually achieves completion. The phrase in article 5.3 ‘up to the date PTT accepts such work’ means ‘up to the date when PTT accepts completed work from Triple Point’. In my view article 5.3 in this case, like clause 24 in the Glanzstoff case, has no application in a situation where the contractor never hands over completed work to the employer.”
“Although accrued rights must be protected, ...”
“… it may sometimes be artificial and inconsistent with the parties’ agreement to categorise the employer’s losses as £x per week up to a specified date and then general damages thereafter. It may be more logical and more consonant with the parties’ bargain to assess the employer’s total losses flowing from the abandonment or termination, applying the ordinary rules for assessing damages for breach of contract.”
“22. If the Contractor fails to complete the Works by the Date for Completion …, then the Contractor shall pay or allow to the Employer a sum calculated at the rate stated in the said appendix as Liquidated and Ascertained Damages for the period during which the Works shall so remain or have remained incomplete, and the Employer may deduct such sum from any monies due or to become due to the Contractor under this Contract.”
“123. The final question is whether liquidated damages for delay fall outside the article 12.3 cap as the judge has held. On this issue Mr Howells supports the judge’s reasoning and Mr Stafford attacks it. 124. Mr Stafford submits that sentence 3 is a separate provision from sentence 2. He bases this argument on the reference to ‘the services or deliverables related to the breach’ at the end of sentence 3. He submits that sentence 3 is making provision for specific breaches of contract, each of which will have a lower damages cap than the total liability cap imposed by sentence 2. Therefore, says Mr Stafford, the exception in sentence 3 for ‘specific remedies expressly identified as such in this contract’ has no application to the general cap imposed by sentence 2. 125. Mr Howells rejects that analysis. He points out that under article 18 the contract price was payable by reference to milestones, not by reference to services or deliverables. He submits that sentences 2 and 3 must be read together. Sentence 3 amplifies sentence 2 and provides further details. Therefore, the exception in sentence 3 applies also to the cap imposed by sentence 2. 126. Both counsel accept that there are difficulties with the second and third sentences of article 12.3, whichever interpretation is correct. I have come to the conclusion that the appellant’s construction is preferable. Sentence 3 is dealing with specific remedies for individual breaches. Each breach is subject to its own individual mini-cap. I agree that precise calculation of an individual mini-cap will not be easy because of the way in which the contract price is structured, but it will be possible to make a reasonable assessment. For obvious reasons, sentence 3 cannot apply to delays. Unlike defects, delays cannot usually be ‘cured’ by the contractor. Furthermore, delays cannot be valued in the same way as defects. So there is a formula elsewhere, namely in clause 5.3, for valuing delays. Accordingly sentence 3 of article 12.3 contains a specific exclusion for delay breaches. Sentence 2 is talking about something different from sentence 3, namely the cap on the contactor’s total liability for all breaches. 127. In my view, the way in which the contract works is this: (i) Article 5.3 provides a formula for quantifying damages for delay. (ii) Sentence 3 of article 12.3 deals with breaches of contract not involving delay. Hence sentence 3 necessarily includes the words ‘Except for the specific remedies expressly identified as such in this contract’. It is common ground that this phrase refers to liquidated damages under article 5.3. Sentence 3 of article 12.3 imposes a cap on the recoverable damages for each individual breach of contract. (iii) Sentence 2 of article 12.3 imposes an overall cap on the contractor’s total liability. That cap on total liability means what it says. It encompasses damages for defects, damages for delay and damages for any other breaches …”
“What we have to determine is a matter of pure construction.”
“upon its construction I read it as meaning that if the contractors have actually completed the works, but have been late in completing the works, then, and in that case only, the clause applies.” (Emphasis added)
“If a construction contract is abandoned or terminated, the employer is in new territory for which the liquidated damages clause may not have made provision. Although accrued rights must be protected, it may sometimes be artificial and inconsistent with the parties’ agreement to categorise the employer’s losses as £x per week up to a specified date and then general damages thereafter. It may be more logical and more consonant with the parties’ bargain to assess the employer’s total losses flowing from the abandonment or termination, applying the ordinary rules for assessing damages for breach of contract.”
“It was suggested that the purchasers had it in their power to reduce this stipulation to a mere nullity, because they had only to be bold enough to throw up the contract and say that they would not fulfil it in order to relieve themselves of it. … The purpose which the parties had in view would be defeated, if the penalty could not be exacted immediately but was to be payable only if and when the purchasers thought fit to complete their contract.”
“Any such term would reward the defendant for his own default. Take the example of a contractor who has wholly failed to comply with the contract, is in considerable delay, and is facing a notice of termination. The defendant’s case would mean that such a contractor was only liable to pay liquidated damages for delay before the decision was taken to terminate, thereby penalising the employer for trying to get the works completed by another contractor, and rewarding the contractor for sitting on his hands and failing to carry out the works in accordance with the programme.”
“If CONTRACTOR fails to deliver work within the time specified and the delay has not been introduced by PTT, CONTRACTOR shall be liable to pay the penalty at the rate of 0.1% (zero point one percent) of undelivered work per day of delay from the due date for delivery up to the date PTT accepts such work …” (Emphasis added)
“1. CONTRACTOR shall be liable to PTT for any damage suffered by PTT as a consequence of CONTRACTOR’s breach of contract, including software defects or inability to perform ‘Fully Complies’ or ‘Partially Complies’ functionalities as illustrated in Section 24 of Part III Project and Services. 2. The total liability of CONTRACTOR to PTT under the Contract shall be limited to the Contract Price received by CONTRACTOR with respect to the services or deliverables involved under this Contract. 3. Except for the specific remedies expressly identified as such in this Contract, PTT’s exclusive remedy for any claim arising out of this Contract will be for CONTRACTOR, upon receipt of written notice, to use best endeavor to cure the breach at its expense, or failing that, to return the fees paid to CONTRACTOR for the Services or Deliverables related to the breach. 4. This limitation of liability shall not apply to CONTRACTOR’s liability resulting from fraud, negligence, gross negligence or wilful misconduct of CONTRACTOR or any of its officers, employees or agents.”
“It is, of course, open to parties to a contract for sale of goods or for work and labour or for both to exclude by express agreement a remedy for its breach which would otherwise arise by operation of law … But in construing such a contract one starts with the presumption that neither party intends to abandon any remedies for its breach arising by operation of law, and clear express words must be used in order to rebut this presumption.”
“The court is unlikely to be satisfied that a party to a contract has abandoned valuable rights arising by operation of law unless the terms of the contract make it sufficiently clear that that was intended. The more valuable the right, the clearer the language will need to be.”
“Applying the modern approach, the force of what was the contra proferentem rule is embraced by recognising that a party is unlikely to have agreed to give up a valuable right that it would otherwise have had without clear words. And as MooreBick LJ put it in the Stocznia case, at para 23, ‘The more valuable the right, the clearer the language will need to be’. So, for example, clear words will generally be needed before a court will conclude that the agreement excludes a party’s liability for its own negligence.”
“It is well-established that the presumption against surplusage is of little value in the interpretation of commercial contracts.”
“all activities rendered by CONTRACTOR [ie Triple Point] to PTT in connection with the Project”
“12.1 CONTRACTOR shall exercise all reasonable skill, care and diligence and efficiency in the performance of the Services under the Contract and carry out all his responsibilities in accordance with recognized international professional standards. The CONTRACTOR, his employees and sub- contractors, while in Thailand and/or other countries where the Services are being carried out, shall respect the law and customs of the respective countries. The CONTRACTOR shall replace employees and sub-contractors who commit serious violation of the laws of such countries with others of equal competence satisfactory to PTT at the expense of the CONTRACTOR. 12.2 CONTRACTOR’s personnel, representatives, successors and permitted assignees shall not have the benefit, whether directly or indirectly, of any royalty on or of any gratuity of commission in respect of any patented or protected articles or process used on or for the purpose of the Contract unless it is mutually agreed in writing that CONTRACTOR shall have such benefit. 12.3 CONTRACTOR shall be liable to PTT for any damage suffered by PTT as a consequence of CONTRACTOR’s breach of contract, including software defects or inability to perform ‘Fully Complies’ or ‘Partially Complies’ functionalities as illustrated in section 24 of Part III Project and Services. The total liability of CONTRACTOR to PTT under the Contract shall be limited to the Contract Price received by CONTRACTOR with respect to the services or deliverables involved under this Contract. Except for the specific remedies expressly identified as such in this Contract, PTT’s exclusive remedy for any claim arising out of this Contract will be for CONTRACTOR, upon receipt of written notice, to use best endeavor to cure the breach at its expense, or failing that, to return the fees paid to CONTRACTOR for the Services or Deliverables related to the breach. This limitation of liability shall not apply to CONTRACTOR’s liability resulting from fraud, negligence, gross negligence or wilful misconduct of CONTRACTOR or any of its officers, employees or agents.”
“… Licensee agrees that the aggregate liability of Triple Point for damages from any cause of action whatsoever, regardless of the form of action, shall not exceed the fees paid to Triple Point under the CTRM Contract and except such damages caused by fraud, gross negligence and wilful misconduct.”
“… Triple Point agrees that this agreement shall not supersede and shall be an annex to the CTRM Contract. In addition, Triple Point agrees that if there is any conflict between the CTRM Contract and this agreement, the CTRM Contract shall prevail and be enforceable.”