“What, I think, nobody could have predicted at the time of Caledonian Modular was the proliferation of what I understand are (unhappily) called 'smash and grab' cases: those adjudication claims (usually, but not always, brought by contractors) based on the contention that the other party has failed to serve proper or timeous applications for payment or payment/pay less notices, thereby automatically entitling the claiming party to the sums claimed, no matter how controversial. The significant increase in these sorts of claims seems to me to arise principally from the ill-considered amendments to the 1996 Act, and the over-prescription of the payment terms included in the standard forms of contract, which have led to provisions of unnecessary complexity.”
“Q: The application last summer, we were told in a witnessstatement that she only became involved at SteeringCommittee level at around February 2015. You are saying that is wrong; is that right?A. Correct. She was in a number of Steering Committeessince August 2014.Q. For six months basically? A. Yes.”
“If their internal cost reports or project cost detailed reports show that they had no funds and that's why they couldn't produce any adequate plan for further testing and/or rectification, then we would suggest that is relevant. It gives the motivation, the explanation, why they are simply unable to produce any adequate plan to actually rectify their own defective work.”
“A further point raised by Mr. Matthew McGrady, MMT's financial director, in a witness statement dated15 July 2015 , was that in Adjudication No. 2 ICI relied on a witness statement of a Mr. Brugman….”
“MMT failed to produce when requested any adequate plan for further testing or rectification of the defective welding. MMT also failed to produce any evidence or proposals for ensuring that the welders were appropriately qualified. MMT refused PROJEN access to its fabrication shop.”
"Lowlights"? Do you see that heading at the bottom of that page? A. Mm. Q. "
“[Mr Consonni]’s opinion is also that due to the inadequate quality of the welding produced by MMT and to the exceptionally high repair rates…..it would have been reasonable for ICI to have lost confidence in MMT’s ability to carry out the rectification works to an acceptable standard.”
“I am quite astonished you bring this fact to me now”
“I did not leave instructions for something I didn't expect to happen”
“Q. So you haven't seen the spreadsheet with all 2,500 on it? A. I'm not saying that there is a spreadsheet. Q. Take it from me, Mr Millwood, if necessary I can get it out -- A. I don't know. Q. -- there is such a spreadsheet. It was provided in October 2016 when we asked for the proper documents from the other side, and your evidence is you haven't actually seen any analysis of the 2,500 which would either support or contradict your evidence that the 412 is properly representative or may be representative, is that fair? A. I've not seen any spreadsheet for more welds than the 412. Q. All right. My Lord, just for the court's reference -- MR JUSTICE FRASER: Give me the reference later, Mr Mort. THE WITNESS: My Lord, I'd like to see that, if that is disclosed information. 71. A. Yeah, I know where you're trying to go on this but I don't have that data. So I can only comment on the data that I have. 72. Q. Mr Millwood, I'm just asking you why didn't you ask Mr Leadbetter [from Clyde & Co] or one of his colleagues: what about one of these other radiographs, what sort of incidence of defect do they show? A. I can't comment on that. Q. You can. You can explain why you didn't ask Mr Leadbetter that question. It may be "I didn't think of it" it may be "I was so keen for ICI to win the litigation, I didn't want to do anything that will upset the statistics" -- A. No -- 73. A. I can answer the question. I did ask for the data for those other welds and it was not forthcoming. MR JUSTICE FRASER: So you have asked? A. Indeed I have. MR JUSTICE FRASER: Yes, all right. When did you ask? 74. MR MORT: So you said to your clients, solicitors instructing you "I've only seen some radiograph reports. There are many more. It would be appropriate to look at all of them if only to see consistency or for whatever other purpose" and Clyde said, "They're not available"? Is that how it went? 75. A. Whether they said they were not available or not I don't know, but they were not forthcoming. 76. Q. Right. Why don't you mention that in your report, to say, "Well, I asked for these, I was unable to obtain them"? 77. A. Okay. I thought I had mentioned that, I didn't use those words exactly. But in that paragraph 149 -- Q. Mr Millwood, in fairness to you -- A. -- I say that I've pointed out that -- Q. You're quite right. A. That's fairly honest and unbiased, I think……I think it is fairly obvious and unbiased that I have actually pointed out that there may be other welds but I've not seen them. So I'm saying is what I've done my examination on is the 412, but if you look at the 412, the defect rate comes out at about 38 per cent which is a rather large number.”
“MR MORT: [Referring to the 412 welds] They are the welds that had been rejected, aren't they? That's why you have a sample showing such a high proportion, they've been cut out because they've been rejected, and they're radiographed. That's precisely what has happened. A. No, I don't believe that. 80. A. Perhaps that an oversight, but I had pointed out that I am aware of at least a suggestion that other welds had been radiographed but nobody has come to me with any actual evidence saying they had been radiographed.”
“Whilst ICI may not have specified the technical requirements for the pipework fabrication as thoroughly as they should have, ICI was entitled to rely on MMT who were engaged as the experts in pipework fabrication and installation. It was therefore incumbent on MMT to be fully aware of the technical requirements and to manage the weld quality in a professional manner. In my opinion, MMT failed to do so.”
“Q: But it would be an explanation as to why far higher rates of weld defects were found on my project compared to these little numbers, that the method of NDT was changed. That would be an explanation, would it not? A. No, I don't think that would be an explanation. The figures in table 1, which is what we're referring to, are first of all these are projects which are not directly comparable but are there to give an idea of reject rates in pipe products made partly or entirely of stainless steel. But there are other factors, as I said, which might be causing the reject rates to be higher. So I would not conclude that the reject rate was high because the NDT regime changed. I think there are other measures that should have been put in place, knowing that the NDT regime was inadequate from the start, and this was known by the fabricator [ie MMT] to pick up any other cause of defects, for example problems with the application of the welding procedures. You know, this one example, of chemical analysis of the material which may affect penetration, which is then the cause of -- root cause of problems like this lack of penetration or lack of root penetration that have been reported. Q. If the client says to the contractor, "We don't want to pay for X-raying", if that is what they said, it is reasonable to assume, isn't it, that the employer is not concerned by certain categories of defect. Is that reasonable? A. I do not think that is reasonable to assume. I -- there are specific requirements in, for example, BS4677 which say that table 5, which had been discussed often in these days, applies, and any changes to those difference must be -- to those defect acceptance criteria shall be agreed between the parties or specified by the purchaser. In this case the purchaser, ICI, did not specify changes to the acceptance criteria.”
“A part of the Works which is not in accordance with the Works Information…”
“All drawings, plans, designs, diagrams, details and specifications of materials, goods and workmanship, technical data, models, CAD materials, bills of quantities reports, calculations and other related documents and recorded information, of any nature whatsoever, which have been or will be written prepared and/or produced by or on behalf of the Contractor in connection with the design and/or construction of Works.”
“… information, documents, records and the like, in the possession of, or available to the Contractor, and/or Related Persons, in each case relating to the Works and this Contract, including information, documents and records of: • the Contractor’s monitoring of its Provision of the Works against the Key Performance Indicators and its quality management systems…”
“The Contractor Provides the Works in a proper and workmanlike manner and in accordance with the Works Information and shall proceed regularly and diligently with the performance of its obligations and this contract…”
“The Contractor warrants and undertakes that the Works when completed, will satisfy any performance specification or other requirements included or referred to in this contract.”
“The Contractor shall not use or specify for use in the Works any Materials which contravene any British Standard Specification or Code of Practice or European Union equivalent relevant at the date of specification or use which are generally known to be deleterious to health and safety and/or to the durability of the Works in particular circumstances in which they are used. The Contractor shall impose a like obligation on all Sub-Contractors.”
“The Contractor grants to the Employer an irrevocable, royalty-free and non-exclusive licence to copy and use the Contractor’s Documents and to reproduce the designs and Works contained in them for all purposes relating to or connected with the Works, the Site or in the property comprising the works… If the employment of the Contractor under the Contract is terminated the Contractor hereby agrees that the licence in respect of the Contractor’s Documents granted pursuant to this Clause 22.1 shall continue in all respects, and shall not be affected by such termination and the Contractor shall when requested in writing to do so by the Employer, deliver up forthwith to the Employer two copies of the Contractor’s Documents.”
“The Contractor will operate a quality management system which complies with the relevant parts of BS EN ISO 9001 and 9002 and has third part[y] certification from an approved accreditation body or is operating in preparation for accreditation within six months of the Contract Date. Prior to the starting date the Contractor prepares a quality plan and submits it to the Project Manager for acceptance. The quality plan incorporates: • The Quality Statement; • Quality requirements stated in the Works Information …”
“Before Completion, the Contractor supplies to the Employer, without additional charge, such Contractor’s Documents and related information as may be specified in the Works Information or as the Employer may request, showing or describing the Works as constructed and concerning the maintenance and operation of the Works including any Plant. Notwithstanding any provision to the contrary in this contract, the Contractor is not entitled to any payment of any amount retained pursuant to Clause X16 that would (but for this provision) become due and payable until the provisions of this clause 27.8 have been complied with…”
“If a test of inspection shows that any work has a Defect, the Contractor corrects the Defect and the test or inspection is repeated” : Clause 43.1 obliges MMT to rectify defects in the Works. “The Contractor corrects the Defect whether or not the Supervisor notifies him of it.”
“The Project Manager assesses the amount due at each assessment date.”
“The amount due is • The Price for Works Done to Date • Plus other amounts to be paid to the Contractor • Less amounts to be paid by or retained from the Contractor Any tax which the law requires the Employer to pay to the Contractor is included in the amount due.”
“In assessing the amount due, the Project Manager considers any application for payment the Contractor has submitted on or before the assessment date. The Project Manager gives the Contractor details of how the amount due has been assessed.”
“The Project Manager corrects any wrongly assessed amount due in a later payment certificate.”
“The Contractor: • provides the right of access for the Employer, the Project Manager and other representatives of the Employer at all reasonable times to enter any of the Contractor’s premises or facilities to inspect or access the Contractor’s equipment (including computer hardware, software and databases) in order to monitor the Contractor’s compliance with its obligations under this contract; • provides the right of access for the Employer, the Project Manager and other representatives of the Employer at all reasonable times to: ◦ enter any Affiliates’ premises or facilities to inspect or access equipment (including computer hardware, software and databases); ◦ visit any Affiliates’ premises or site where Works or fabrication of equipment, components or materials for the Works is being carried out and/or which are being used as training facilities in connection with the Contractor’s Provision of the Works In order to monitor the Contractor’s compliance with its obligations under the contract; • uses reasonable endeavours to provide the right of access for the Employer, the Project Manager and other representatives of the Employer at all reasonable time to: ◦ enter any Subcontractor’s premises or facilities to inspect or access equipment (including computer hardware, software and databases) ◦ visit any Subcontractor’s premises or site where Works or fabrication of equipment, components or materials for the Works is being carried out and/or which are being used as training facilities in connection with the Contractor’s or a Subcontractor’s Provision of the Works.”
“The Contractor: ◦ enter any Affiliates’ premises or facilities to inspect or access equipment (including computer hardware, software and databases); ◦ visit any Affiliates’ premises or site where Works or fabrication of equipment, components or materials for the Works is being carried out and/or which are being used as training facilities in connection with the Contractor’s Provision of the Works ◦ enter any Subcontractor’s premises or facilities to inspect or access equipment (including computer hardware, software and databases) ◦ visit any Subcontractor’s premises or site where Works or fabrication of equipment, components or materials for the Works is being carried out and/or which are being used as training facilities in connection with the Contractor’s or a Subcontractor’s Provision of the Works.”
“The Contractor: • permits all Project Records and Financial Records to be examined and copied from time to time by any auditor (whether internal or external) of the Employer, by the Project Manager and by other representatives of the Employer: • co-operates fully and in a timely manner with any reasonable request from time to time of any auditor (whether internal or external) of the Employer (until Completion, being able to recover its reasonable costs of doing so as part of Defined Cost unless Clause 55.6 applies, and thereafter at the Contractor’s cost) to: ◦ provide any of the Project Records and/or the Financial Records or procure their provision; ◦ provide, or procure the provision of, any oral or written explanation relating to the same; ◦ provide relevant or requested personnel of the Contractor or procure the provision of relevant or requested personnel of Subcontractors for the purpose of attending interviews with any auditor and procure that Subcontractors grant such rights and/or undertake such obligations to any auditor (whether internal or external) of the Employer, to the Project Manager and to any other representatives of the Employer.”
“The Parties acknowledge and agree that damages shall not be an adequate remedy for breach of this Clause 55.”
“The issue of any payment certificate or the payment of any amount by the Employer to the Contractor does not constitute or imply or be evidence of the Project Manager’s, the Supervisor’s or the Employer’s approval or acceptance of any design, work, Plant and Materials forming part of the works or relieve the Contractor of any of his obligations under this contract.”
“The changes to the Prices are assessed as the effect of the compensation event upon • The actual Defined Cost of the work already done. • The forecast Defined Cost of the work not yet done and • The resulting Fee.”
“The rights of the Employer and the Contractor to changes to the Prices, the Completion Date and the Key Dates are their only rights in respect of a compensation event.”
“If the Project Manager has notified the Contractor of his decision that the Contractor did not give an early warning of a compensation event which an experienced Contractor could have given, the event is assessed as if the Contractor had given an early warning.”
“Assessment of the effect of a compensation event includes risk allowances for cost and time for matters which have a significant chance of occurring and are at the Contractor’s risk under this contract.”
“Assessments are based upon the assumptions that the Contractor reacts competently and promptly to the compensation event, that any Defined Cost and time due to the event are reasonably incurred and that the Accepted programme can be changed.”
“If the effect of a compensation event is to reduce the total Defined Cost and the event is A change to the Works Information or • A correction of an assumption stated by the Project Manager for assessing an earlier compensation event the prices are reduced.”
“Assessments for change Prices for compensation events are in the form of changes to the Activity Schedule.”
“If the Project Manager and the Contractor agree, rates and lump sums may be used to assess a compensation event.”
“Assuming Coppa are correct and based on invoice value from [MMT], we owe [MMT]£6.12m . The Capex budget allows for£3.2m for further [MMT] spend…..[AkzoNobel] can only pay [MMT] a maximum of£3.2m .”
“An employer can employ his own employee to act as Project Manager, providing he acts impartially and the check and balance to ensure he should act impartially is the fact his decisions, or non-decisions, can be challenged by adjudication.”
“This e mail is an official instruction to you that any revision of assessments on PMIs with Merit Merrell will need to be signed off by myself and Theo Brugman before they will be included in the certification each month. This goes for upwards and downwards revisions.”
“Further to your e mail below and the previous instruction from [Mr Boerboom] and [Mr Brugman] I believe that an amendment to the Contract is now required to give AkzoNobel full responsibility for the contractors. As you are aware Projen plc are named in the Contracts with [MMT and others] as the Project Manager. Under the NEC3 Contract the Project Manager carries a lot of responsibilities in terms of the administration of the Contract. As I am no longer empowered by the Employer to carry out these responsibilities it is, I believe, time to change the Project Manager to AkzoNobel”
“A visual inspection of the internal and external surface of the joint will be carried by the Quality Control Inspector to ensure the two components which have been welded are smooth, free from discolouration, straight and uniform. All welding and NDT requirements will be in accordance with the Client requirements. Unacceptable defects revealed by visual or non-destructive examination shall- either be repaired or deemed not to comply with the specification. All repairs shall be re-examined as if they were new welds.”
“All activities not meeting the requirements of the Quality Management Systems or agreements with clients are suspended pending appropriate action. All materials, products, services and sub-contractor performance not meeting the required specification are clearly identified and/or segregated pending a decision regarding their further processing. The occurrence is investigated in order to establish its cause.”
“Those methods [of testing] and the standard of welding that resulted were checked by AkzoNobel and ICI’s consultants, Projen and ABB, continuously from March 2013 with no detrimental comment. Indeed the weld inspectors were complimentary about the standard of welding as the e mail from Clive Chapman dated13 March 2013 at page PBC/70 and Akzo/Projen worked alongside MMT’s operatives in the fabrication workshop for over 16 months, continuously observing and checking the MMT welding throughout without even a single adverse comment about the fabrication workshop welding.”
“We need your help in the Fresco Project. Could you please inform us about what welding specification (s) that was used in the Guangzhou and Gwailor projects? Preferably use your connections and try finding the specification documents and send them to me.”
“Our advice would be: i. pay MMT, try to minimize ie fixed price for remainder of work and seek compensation from Projen. ii. threaten to see them in Court or offer to pay and additional£8m (our original view of£4m is no longer in scope).”
“With one hand you are issuing us with informal and non-contractual instructions and with the other hand you are criticising us for responding to such instructions. That cannot carry on….. Please advise us today or Monday (9th) if anyone else is to have authority to issue us with instructions and if so who and in what format.”
“I still didn’t get a response to this e mail? I’m not sure why this point would not be clarified? I’d appreciate a response as your site team continue to instruct us by e mail without PMIs or Projen involvement.”
“It is ridiculous for you to assert that we have not repaired defects (which in any event are not admitted) when it is plainly you who instructed us to suspend such works ….. [the instruction to stop welding, with immediate effect] necessarily prevented us from carrying out any remedial works to the welds, regardless of whose responsibility those alleged defects were. We are of course obligated to comply with such instructions.”
“In my view Mr. Dunning's submission [for the Yard] fails properly to recognise the true nature of the contract. The primary purpose of Article 10 in the present case is to provide an agreed measure of compensation for breaches of contract by way of delay in delivery and deficiencies in capacity and performance which, although important, do not go to the root of the contract. For these the parties have agreed the payment of liquidated damages which are to be deducted from the final instalment of the price and to that extent their agreement displaces the general law, at least as regards the measure of damages recoverable for a breach of that kind. However, they have also agreed that there comes a point at which the delay or deficiency is so serious that it should entitle Gearbulk to terminate the contract. In my view they must be taken to have agreed that at that point the breach is to be treated as going to the root of the contract. In those circumstances the right to terminate the contract cannot sensibly be understood as anything other than embodying the parties' agreement that Gearbulk has the right to treat the contract as repudiated, with (subject to Mr. Dunning's alternative argument) the usual consequences. The same holds true in relation to the Yard's right to terminate the contract under Article 5.7. Although the parties may have agreed to exclude, in whole or in part, Gearbulk's right to recover damages for a repudiatory breach on the part of the Yard, I am unable to accept that they intended to create by their contract a situation which differed in its effect from that which would arise on the acceptance of a repudiation under the general law. Article 5.9 and Article 10 simply identify the circumstances in which one or other of the parties is entitled to treat the contract as discharged by the other's breach. In paragraph 88 of his judgment in Stocznia Gdanska S.A. v Latvian Shipping Co[2002] EWCA Civ 889 [2002] 2 Lloyd’s Ref 436 Rix L.J. expressed the view that where contractual and common law rights overlap it would be too harsh to regard the use of a contractual mechanism of termination as ousting the common law mechanism, at any rate against a background of an express reservation of rights. In this case I would go further. In my view it is wrong to treat the right to terminate in accordance with the terms of the contract as different in substance from the right to treat the contract as discharged by reason of repudiation at common law. In those cases where the contract gives a right of termination they are in effect one and the same.”
“Whenever one party to a contract is given the right to terminate it in the event of a breach by the other it is necessary to examine carefully what the parties were intending to achieve and in particular what importance they intended to attach to the underlying obligation and the nature of the breach. The answer will turn on the language of the clause in question understood in the context of the contract as a whole and its commercial background. Sometimes, as in Lockland Builders v Rickwood, the parties will have intended to give a remedy of a limited nature for breaches of a certain kind; in other cases the terms of the contract may reflect an intention to treat the breach as going to the root of the contract with the usual consequences, however important or unimportant it might otherwise appear to be. Inevitably, therefore, there can be no hard and fast rule.”
“Either Party may terminate if the Parties have been released under the law from further performance of the whole of this contract (R17) but this Clause 91.5 shall not entitle either Party to terminate this contract for repudiation (or accept the other Party’s repudiation or elect to treat this contract as rescinded by reason of repudiation).”
“MMT contract still not terminated. Adjudication started; we have no legal grounds still to declare breach”
“1. The Price for Works Done to Date 2. Plus other amounts to be paid to the Contractor 3. Less amounts to be paid by or retained from the Contractor”
“The issue of any payment certificate or the payment of any amount by the Employer to the Contractor does not constitute or imply or be evidence of the Project Manager’s, the Supervisor’s or the Employer’s approval or acceptance of any design, work, Plant and Materials forming part of the works or relieve the Contractor of any of his obligations under this contract.”
“Since the only issue referred to the adjudicator in Adjudication No 2 was the value of ISG's works at the date of Application No 13, and since I have concluded that this question was decided in Adjudication No 1, that conclusion disposes of the dispute referred in Adjudication No 2. Accordingly, ISG is entitled to a declaration to that effect.”
“[44] However, if I am wrong about the issue referred to the adjudicator in Adjudication No 2 as being the value of ISG's works on the valuation date for Application No 13, there is another route to the same result. On this application for summary judgment the court is being asked, in effect, to decide the rights of the parties in relation to the dispute raised by Adjudication No 2. In my judgment, the court is entitled to do just that (because, as I have already mentioned, there is no arbitration clause). [45] For the reasons that I have already given under this form of contract the employer has no right to demand a valuation of the contractor's work on any date other than the valuation dates for interim applications specified in the contract. Accordingly, if and in so far as in Adjudication No 2 Mr. Juniper was purporting to determine the valuation of the works at a date other than a valuation date (ie.13 May 2014 instead of11 May 2014 ), and then to make a financial award on the basis of it, he was in my judgment wrong to do so.”
“[18] I held that if an employer fails to serve the relevant notices under this form of contract it must be deemed to have agreed the valuation stated in the relevant interim application, right or wrong. Accordingly, the adjudicator must be taken to have decided the question of the value of the work carried out by the contractor for the purposes of the interim application in question. [19] However, I made it clear that this agreement as to the amount stated in a particular interim application (and hence as to the value of the work on the relevant valuation date) could not constitute any agreement as to the value of the work at some other date (see paragraph 31). [20] This means that the employer cannot bring a second adjudication to determine the value of the work at the valuation date of the interim application in question. But it does not mean any more. There is nothing to prevent the employer challenging the value of the work on the next application, even if he is contending for a figure that is lower than the (unchallenged) amount stated in the previous application.”
“If it is necessary, out of respect for well-established principles in the law of contract and restitution, to base our decision on the proposition that there was a total failure of consideration in regard to the£4,673 [ie the balance], so be it. For myself, I would have held that simple common sense was every bit as sure a foundation.”
“Given the accepted constraints of the requirement to show a total rather than partial failure of consideration, apportionment is a necessary tool to enable the court to find that the payee has no right to retain the sum claimed for work which, in breach of contract, he has not done. In my view for work done one could equally substitute goods delivered and/or services provided.”
“(5) There was no valid payment notice or notice of intention to pay less against application number 22, and in the circumstances MMT’s application became the notified sum for the purposes of section 111 of the [Housing Grants Construction and Regeneration] 1996 Act as amended. ICI thereby became obliged to pay the said sum of£7,559,514.76 , ie corresponding with the valuation of the account in the sum of£20,930,363.05 . (6) The matters referred to in the last sub-paragraph have been the subject of both adjudication proceedings and court proceedings (claim number HT-2015-000161) determined in MMT’s favour. In the circumstances MMT is not seeking to put these matters into issue in these proceedings: they have already been determined in a finally binding adjudicator’s decision and in court proceedings, in MMT’s favour.”
“[70] So far as the declaration is concerned, the question of ICI's entitlement to the documents is not one that has been explored before me on the merits. It would therefore be inappropriate for the court to make any declaration of entitlement, but what it can and should do is to declare that the adjudicator's decision is valid and binding. That means that the adjudicator's declaration of entitlement will stand unless and until it is overruled by a decision of the court made on the merits.”
“If the employment of the Contractor under the Contract is terminated the Contractor hereby agrees that the licence in respect of the Contractor’s Documents granted pursuant to this Clause 22.1 shall continue in all respects, and shall not be affected by such termination…..”