“2. In Adjudication No 1 the adjudicator, a Mr. Robert Juniper, decided that ISG was entitled to£1,097,696.29 being the sum claimed in ISG’s Application No 13 plus interest, because the Defendant (“Seevic”) had not served either a payment notice or a pay less notice in accordance with the provisions of the contract. 3. The Notice of Adjudication in Adjudication No 2 was served four days before Mr. Juniper made his decision in Adjudication No 1. It is clear that Seevic, aware that it had not served the relevant notices in time, was seeking to frustrate or reduce the impact of the likely decision in Adjudication No 1 in the hope that it could obtain a decision in Adjudication No 2 that the value of ISG’s works up to the date of the application was less than the amount claimed by ISG. 4. In that it succeeded. By his decision dated10 October 2014 (as corrected under the slip rule on13 October 2014 ) the adjudicator decided in Adjudication No 2 that the value of ISG’s works as at the date of Application No 13 was£315,450.47 . In fact, the adjudicator accepted ISG’s valuation of its measured works but did not accept the sum claimed by ISG for loss and expense, which was a little over£1 million . He concluded that the true value of the loss and expense claim was a little over£300,000 so that ISG had been overpaid. He therefore directed, on the assumption that Seevic had already paid ISG against Adjudication No 1 that ISG should repay the difference, which was£768,525.36 . 5. Seevic did not comply with the decision in Adjudication No 1, although it now accepts that it must do so, subject to the decision in Adjudication No 2. On15 October 2014 Seevic issued a cheque for the sum of£315,450.47 in favour of ISG.”
“In particular, he may- (a) open up, revise and review any decision taken or any certificate given by any person referred to in the contract unless the contract states that the decision or certificate is final and conclusive, (b) decide that any of the parties to the dispute is liable to make a payment under the contract ... when that payment is due and the final date for payment, (c) [this deals with interest].”
“The interim certificates, as is conventional, are on a ‘global’ basis. By this I mean that each interim certificate takes account of the total work done to date and the total payments to date. It follows that if there is an error (e.g. a double charging) in an interim certificate, it can and should be corrected in the next. That is not so for the final certificate.”
“So it is not the actual work done which either defines the sum or when it is due. The sum is the amount in the certificate. The due date is 14 days from certificate date. This certificate may be wrong - the architect may (though this is unlikely because he will be working from the builder’s bill) have missed out work done (which would operate against the contractor) or he may have included items not in fact done or items already paid for (which would operate against the client). In the absence of a withholding notice, section 111(1) operates to prevent the client withholding the sum due. The contractor is entitled to the money right away. The fundamental thing to understand is that section 111(1) is a provision about cash-flow. It is not a provision which seeks to make any certificate, interim or final, conclusive.”
“(b) It provides a fair solution, preserving the builder’s cash flow but not preventing the client who has not issued a withholding notice from raising the disputed items in adjudication or even legal proceedings. ... (d) It does not preclude the client who has paid from subsequently showing he has overpaid. If he has overpaid on an interim certificate the matter can be put right in subsequent certificates. Otherwise he can raise the matter by way of adjudication or if necessary arbitration or legal proceedings.”
“By virtue of clause 4.14 GTB’s Gross Valuation does not include and should not have included amounts which were not ascertained under clause 4.20 and was or should have been£12,656,645.49 less£2,764,427.73 , i.e.£9,892,217.76 (at the maximum).”
“It seems to me clear, pursuant to that authority, that it is not now possible for either party to open up the question of what the proper value of works actually was at the time of application 60 and, as a result, I do not possess the jurisdiction to continue with the matter referred.”
“Finally, I must consider whether or not to grant a stay in the circumstances of this case. I am satisfied that Hillview is entitled to judgment but I am also satisfied that the purpose of the 1996 Act is to provide a statutory framework which would enable justice to be done between parties to a dispute. It was not intended to cause injustice. This can, in appropriate cases, be dealt with by the grant of a stay. I am satisfied that the jurisdiction in adjudication enforcement cases to grant a stay under the CPR must be limited to cases where there is a risk of manifest injustice.”