“However, the Defendant resists summary judgment being given on this enforcement action on the basis that by the time that the adjudication was commenced in January 2020 the Claimant was no longer entitled to be paid the sum stated in PA26, because any entitlement under PA26 had been superseded by subsequent interim payment cycles in which the Claimant made further applications for payment which were the subject of valid payment payless notices and which superseded and corrected the sum payable under the Sub-contract as at August 2019. At no point before the Adjudication commenced in January 2020 did the Claimant contend that PA26 represented its current payment entitlement, having gone along with subsequent payment cycles on a cumulative basis which were the subject of payment/payless notices that govern the Claimant’s payment entitlement pursuant to s.111 of the HGCRA as amended.”
“The current entitlement as at the date of these proceedings is against the Claimant’s application PA33 dated28 February 2020 in respect of which the Defendant served a payment notice/payless notice which constitutes the notified sum of the amount due under the Sub-contract.”
“In the circumstances, it is submitted that it would be manifestly unjust to permit the Claimant to enforce a decision in respect of PA26, when that sum had ceased to be due, following later payment cycles which the Claimant went along with, before the adjudication started, and no longer represents the current payment entitlement under the Sub-contract. To enforce the decision would be inconsistent with, andundermine, the ‘correction’ principle set out in the case law, namely, that interimpayments can be corrected in the next interim payment cycle. Here that correction occurred long before the adjudication was commenced and so the earlier payment entitlement ceased to exist and is replaced by the current sum due pursuant to s111. Alternatively, if the decision were enforced the Court should give effect to the current payment entitlement with the result that payment would be met with an immediate obligation to repay.”
“Finally, I must consider whether or not to grant a stay in the circumstances of this case. I am satisfied that Hillview is entitled to judgment but I am also satisfied that the purpose of the 1996 Act is to provide a statutory framework which would enable justice to be done between parties to a dispute. It was not intended to cause injustice. This can, in appropriate cases, be dealt with by the grant of a stay.”
“I am satisfied that the jurisdiction in adjudication enforcement cases to grant a stay under the CPR must be limited to cases where there is a risk of manifest injustice. I asked Ms Jefford …”
“… specifically whether or not it was being suggested that if the sum awarded in the adjudication was paid to Hillview, there was a risk that Hillview would be unable to, or would not, repay the sum awarded promptly in the summary judgment application of Botes if it were successful.”
“If there had been a serious risk in those circumstances that money paid over on a provisional basis would not be recovered promptly in the event that Botes succeeded in obtaining summary judgment at the hearing on23 June 2006 , I should have given sympathetic consideration to granting a stay for the short time until that date or making other orders to secure the sum which had been paid. That is not the position here.”
“At [43] of his judgment in Interserve Jackson J said the following, the principle with which I respectfully agree …”