“1. Imperial Chemical Industries Limited is entitled to the documents listed in Schedule 1 of the Notice of Adjudication and as repeated at Appendix 1 of this Decision. 2. I make no order for delivery up by Merit Merrell Technology Limited to Imperial Chemical Industries Limited. 3. Merit Merrell Technology Limited shall be responsible for the Adjudicator’s fees in the sum of£17,690 + VAT. On Imperial Chemical Industries Limited paying in full the total Adjudicator’s fees then Merit Merrell Technology Limited shall reimburse to Imperial Chemical Industries Limited the total of the Adjudicator’s fees forthwith.”
“We note that the Contract Data Part One identifies the Adjudicator Nominating Body as The Chartered Institute of Arbitrators but Appendix 2 refers to the Nominating Body as The Royal Institution of Chartered Surveyors. Unless you advise otherwise by return we will be applying to the Chartered Institute of Arbitrators for the nomination of an Adjudicator.”
“This Engineering and Construction Contract conditions of contract are the core clauses, dispute resolution Option W2 and the clauses for Secondary Options X2, X4, X7, X13, X16, Y(UK)2, Y (UK)3, X18 and Z of the NEC3 Engineering and Construction contract June 2005 (with amendments June 2006 and September 2011) as amended by the Additional Conditions of Contract (Option Z).”
“Option W2 Dispute resolution procedure (used in the United Kingdom when the Housing Grants, construction andRegeneration Act 1996 applies). Dispute resolution W2 W2.1 (1) A dispute arising under or in connection with this contract is referred to and decided by the Adjudicator. A Party may refer a dispute to the Adjudicator at any time. (2) In this Option, time periods stated in days exclude Christmas Day, Good Friday and bank holidays. The Adjudicator W2.2 (1) The Parties appoint the Adjudicator under the NEC Adjudicators Contract current at the starting date. (2) The Adjudicator acts impartially and decides the dispute as an independent adjudicator and not as an arbitrator. (3) If the Adjudicator is not identified in the Contract Data or if the Adjudicator resigns or becomes unable to act • the Parties may choose an adjudicator jointly or • a Party may ask the Adjudicator nominating body to choose an adjudicator The Adjudicator nominating body chooses an adjudicator within four days of the request. The chosen adjudicator becomes the Adjudicator.”
“DISPUTE RESOLUTION OPTION Option W2 Dispute resolution procedure (used in the United Kingdom when theHousing Grants, Construction and Regeneration Act 1996 applies) Delete and replace with ‘The Contractor and the Employer acknowledge and agree that all Disputes shall be resolved in accordance with Appendix 2’.”
“Option W2 - Add new sentence ‘Notwithstanding any provisions to the contrary, this contract is deemed to be a “construction contract” within the meaning ofPart II of the Housing Grants, Construction and Regeneration Act 1996 as amended by theLocal Democracy, Economic Development and Construction Act 2009 ’.”
“DISPUTE RESOLUTION OPTION The Contractor and the Employer acknowledge and agree that all Disputes shall be resolved in accordance with Appendix 2.”
“DISPUTE RESOLUTION OPTION Option W2 Dispute resolution procedure (used in the United Kingdom when theHousing Grants, Construction and Regeneration Act 1996 applies) The Contractor and the Employer acknowledge and agree that all Disputes shall be resolved in accordance with Appendix 2.”
“DISPUTE RESOLUTION OPTION Option W2 Dispute resolution procedure (used in the United Kingdom when theHousing Grants, Construction and Regeneration Act 1996 applies) The Contractor and the Employer acknowledge and agree that all Disputes shall be resolved in accordance with Appendix 2. Notwithstanding any provisions to the contrary, this contract is deemed to be a ‘construction contract’ within the meaning ofPart II of the Housing Grants, Construction and Regeneration Act 1996 as amended by theLocal Democracy, Economic Development and Construction Act 2009 .”
“Accordingly the contract allows 14 days for the Response to be served”
“The inevitable conclusion appears to be that the parties’ right to adjudicate is not contractual but statutory, so that part I of the scheme applies (and not the NEC procedure and not the TeCSA procedure).”
“2. We do not believe that the adjudicator in this case has jurisdiction to decide his jurisdiction. We acknowledge that the TECSAR [sic] v3.2 rules envisage this. However it is (now) ICI’s stated case that the original NEC 3 clause W2 applies whereas it is MMT’s primary case that part I of the Scheme probably applies. So neither party supports the TECSAR [sic] regime, as things stand. 3 In any event the adjudication was initially conducted (by the adjudicator) on the basis of the NEC3 procedure, although the referring party purports to have commenced the adjudication under the appendix 2 procedure, notwithstanding its present position. As we have indicated before we do not believe that it is possible to change procedures mid-adjudication.”
“111. On that basis Jacobs has no real prospect of successfully defending these proceedings on the basis that the Adjudicator did not have jurisdiction because he was appointed under the England and Wales Scheme, as amended, rather than the Scotland Scheme. 112. If, however, the wrong Adjudicator had been appointed under the wrong Scheme and the wrong Scheme had been applied to the Adjudication then for the reasons set out by Mr. Justice Edwards-Stuart in Twintec, the Adjudicator would not have been properly appointed for the Adjudication conducted under the correct Scheme and this is a matter which would go to jurisdiction. However in this case where it seems that both parties proceeded on the basis that the England and Wales Scheme applied I would have had to consider whether this jurisdictional defence had been waived by Jacobs who expressly referred to the England and Wales Scheme in some documents.”
“… the documents were in a poor state and would not have been acceptable to ICI.”