“Delete clause 9.2 and replace with the following: 9.2.1. If a dispute or difference arises under this Contract which either Party wishes to refer to adjudication, the Scheme shall apply, subject to the following: 1 for the purposes of the Scheme, the Adjudicator shall be chosen by the referring party from the Employer’s Panel of Adjudicators current as at the date of this Contract (a copy of which is available for inspection at the Employer’s registered office address or on request). Where the chosen adjudicator does not indicate his willingness to act within 2 days of such Notice, then the referring party shall choose a second Adjudicator from the Panel and so on through the list. In the event that none of the Adjudicators on the Panel is able to act then the Adjudication Nominating Body shall be as provided for in the Contract Particulars; and 2 Paragraph 7(1) of the Scheme shall be amended by deleting ‘shall, not later than 7 days from’ and replacing with ‘shall, as soon as reasonably possible after’…. 3 New paragraph 27 shall be included in the Scheme as follows: 1 The Adjudicator shall have power to determine more than one dispute at the same time and, if requested to do so by a party, shall determine any matter raised by such party in the nature of set-off, abatement or counterclaim at the same time as it determines any other matter referred to him.”
“For the avoidance of doubt, the Employer shall be entitled to recover from the Contactor any overpayments made at any time. All interim payments made to the contractor are payments on account only of sums due under the Contract.”
“To the extent that for whatever reason the Employer considers that the Contractor has been overpaid during the course of the Works the amount specified in the final certificate may be adjusted to take into account such overpayment and for the avoidance of doubt the amount so specified can be a negative sum which negative amount shall be a debt due from the Contractor to the Employer.”
“In relation to interim payments, there is no entitlement on the part of Bellway to be paid sums by Surgo on an immediate (or “smash and grab”) basis solely as a result of the issuing of the Interim Certificate containing a negative valuation.”
“(2) The contract shall include provision in writing so as to (a) enable a party to give notice at any time of his intention to refer a dispute to adjudication; (b) provide a timetable with the object of securing the appointment of the adjudicator and referral of the dispute to him within 7 days of such notice”
“The language of section 108(1)(b) is not rigid. It requires that the contractual timescale should have the object of securing the referral of the dispute to the adjudicator within seven days of the adjudication notice. Thus, the statute is setting a minimum requirement for the contract. The contract must allow a referring party, if it chooses, to issue a referral notice within the prescribed seven−day timescale”
“If an Adjudicator is not agreed or appointed within 7 days of the notice the referral shall be made immediately on such agreement or appointment”
“… unlike the Scheme for Construction Contracts, Clause 41A expressly recognises that sometimes, because of the involvement of a nominating body and the delays that that can bring, the adjudicator may not be appointed until after the seven day period has expired. Under Clause 41A that does not invalidate the adjudication; it simply means that the referral notice must be served immediately on the appointment of the adjudicator.”
“The overarching principle… is that a notice of adjudication, with a purported nomination made under a contractual provision or legislative power which, on a correct analysis does not apply, is invalid.”
“More widely, Ecovision Systems is important because the judge concluded that the adjudicator has no power to determine what rules of adjudication might apply if there was a dispute about the rules, and the dispute made a material difference to the procedure of appointment, the procedure to be followed in the adjudication, or the status of the decision”
“The distinction between jurisdictional challenges to enforcement and challenges alleging substantive error suggests that the issue in this case should be approached in two stages. The first question is whether the Adjudicator had jurisdiction. The answer to that question is that he did, on any contractual route being proposed by either party. He had jurisdiction and was to be appointed under the Scheme, on any contractual route being proposed by either party. That distinguishes the present case from Pegram. Chalcroft’s only point on jurisdiction is that RMP has not properly identified the contract that gives rise to the Scheme route to jurisdiction. This objection is similar to but not precisely the same as the objections being raised in Purton. …”
“In principle it is possible for negative certificates to be issued, particularly in the case of certificates of valuation. However, the contract may prohibit such certificates in certain circumstances or permit them only in specified circumstances thereby, perhaps, by implication prohibiting them in other circumstances.”
“Sometimes sums are paid against interim certificates, and it subsequently appears that the works have been over-valued and too much has been paid. In this situation recovery of the overpayments can usually be made by deduction from subsequent certificates. The opportunity for deduction may not occur if the contract is prematurely terminated. Where a contract was terminated owing to the contractor's insolvency, the employer tried to recover an interim payment on the ground of total failure of consideration or on the ground of mistake of fact, the mistake being the incorrect belief that the works would be completed. It was held that there was not a total failure of consideration, because work had been done and materials supplied, and the contract was not to be regarded as 'entire'. It was also held that the payment had not been made under a mistake of fact: it had been made pursuant to the contract and there was no mistake as to the facts existing at the time of payment. Where a contract ends by repudiation, existing rights and obligations remain in existence. These include the right on the part of an employer to recover an overpayment made before the repudiation. An employer's repudiation does not relieve the parties of an analysis of the value of the works and does not freeze the contractor's entitlement to payment at the amount already received. Similarly, the employer remains entitled to recover any overpayments on the basis that the sum paid includes sums which were paid under temporarily binding adjudicator's decisions which on a final basis can be proved not to be due.”
“… It is, therefore, undoubtedly the case that there is something which, for today's purposes, can helpfully be referred to as, the “correction principle” established by the authorities. By “correction principle”
“If an adjudicator finds that the employer has overpaid at an interim stage, he can order re-payment of the excess as the dispositive remedy flowing from the adjudicator’s re-evaluation”, saying that: “I agree with that analysis. The parties have agreed (albeit under statutory compulsion) that the adjudicator should have jurisdiction to deal with disputes between them, including any dispute concerning the correct valuation of work under clause 4.7. Having determined the true value of the works at an interim stage, the adjudicator (whose powers are co-extensive with the powers of the court in matters such as this) must be able to give effect to the financial consequences of his decision.”