“1. General • The conditions of contract are the core clauses and the clauses for main Option A, dispute resolution Option ... and secondary Options X7, X16, X 17 and Y (UK) 2 of the NEC2 Engineering and Construction Subcontract June 2005 (with amendments June 2006). All as amended by the numbered documents in Appendix 1 annexed hereto. … • The Adjudicator in this subcontract is Name: The President of the Royal Institute of Chartered Surveyors … • The Adjudicator nominating body is As Appendix 6 annexed hereto … 9. Options statements • If Option Z is used The additional conditions of subcontract are All as detailed in the numbered documents in Appendix 1 annexed hereto.” • The conditions of contract are the core clauses and the clauses for main Option A, dispute resolution Option ... and secondary Options X7, X16, X 17 and Y (UK) 2 of the NEC2 Engineering and Construction Subcontract June 2005 (with amendments June 2006). All as amended by the numbered documents in Appendix 1 annexed hereto. • The Adjudicator in this subcontract is Name: The President of the Royal Institute of Chartered Surveyors • The Adjudicator nominating body is As Appendix 6 annexed hereto • If Option Z is used The additional conditions of subcontract are All as detailed in the numbered documents in Appendix 1 annexed hereto.”
“10.1 The Contractor and the Subcontractor shall act as stated in this subcontract and in a spirit of mutual trust and co-operation. 11.1 In these conditions of subcontract, terms identified in the Subcontract data are in italics and defined terms have capital initials.”
“The additional conditions of subcontract stated in the Sub-Contract Data are part of this contract”
“All as detailed in the numbered documents in Appendix 1 annexed hereto” under Option Z in the Sub-Contract Data had the consequence that all the terms in the numbered documents in Appendix 1 were incorporated into and became part of the Sub-Contract. The numbered documents in Appendix 1 were stated as comprising, amongst others, “The Description of Works”
“DISPUTE RESOLUTION PROCEDURE Z16.1 Delete main option clauses W2.1, W2.2, W2.3 and W2.4. Z16.2 Insert the new main option clauses as follows: “W2.1 The proper law of this contract is English law. The courts of England have jurisdiction in relation to this contract, and a court or judge thereof has jurisdiction to open up review and revise any decision or opinion or certificate under the contract. W2.2 Where pursuant to this contract orPart II of the Housing Grants, Construction and Regeneration Act 1996 a dispute or difference is referred to adjudication, that adjudication is governed by and conducted in accordance with the Adjudication Rules of the Technology and Construction Solicitors Association, which are incorporated herein by reference. The decision of the adjudicator is binding on the parties until the dispute or difference is finally determined by a court or judge thereof. W2.3 Any reference in the contract to arbitration or to an arbitrator is deleted and substituted with a reference to the English courts or a judge thereof.” ” “W2.1 The proper law of this contract is English law. The courts of England have jurisdiction in relation to this contract, and a court or judge thereof has jurisdiction to open up review and revise any decision or opinion or certificate under the contract. W2.2 Where pursuant to this contract orPart II of the Housing Grants, Construction and Regeneration Act 1996 a dispute or difference is referred to adjudication, that adjudication is governed by and conducted in accordance with the Adjudication Rules of the Technology and Construction Solicitors Association, which are incorporated herein by reference. The decision of the adjudicator is binding on the parties until the dispute or difference is finally determined by a court or judge thereof. W2.3 Any reference in the contract to arbitration or to an arbitrator is deleted and substituted with a reference to the English courts or a judge thereof.” ”
“20A.1 The Subcontractor shall be deemed to have full knowledge of the provisions of the main contract (other than details of the rates and prices) and other contracts made by the Contractor in connection with the main contract Works and the Contractor shall, if so requested, make available a copy of the main contract and other contracts for inspection by the Subcontractor. 20A.2 Save where the provisions of the Subcontract otherwise provide the Subcontractor shall carry out, complete and maintain the subcontract works and shall observe, perform and comply with all the obligations and liabilities of the Contractor under the main contract and other contracts made by the Contractor in connection with the main contract works insofar as they relate to the subcontract works. Nothing herein shall be construed as creating any privity of contract between the Subcontractor and the Employer.”
“The Adjudicator referred to in the Sub-Contract shall be the President (or if he is unable to act, any Vice-President) of the Royal Institution of Chartered Surveyors.”
“Is this application made under the Scheme or Contract?”
“(a) the source of your client’s right to adjudicate and (b) pursuant to what adjudication procedure”
“In the absence of this information, we are unable to accept that any dispute has been properly notified or referred, unable to accept that you have jurisdiction and we do not see how you can in any event conduct an adjudication when, as far as we are aware, you have not been told what your powers to do so are said to be.”
“In this contract certain of those clauses have been replaced by Z clauses ...”
“In the circumstances, Vinci was free to approach an adjudicator nominating body of its choosing and it is a matter of record that Vinci subsequently approached the RICS and asked the Dispute Resolution Service to nominate an adjudicator.”
“Please explain which adjudication procedure your client considers applies: W2, the Scheme, TeCSA or something else”
“If and insofar as there is an adjudication validly on foot, and if and in so far as a valid direction has been given requiring a response within 7 days (which we deny) then we [RPC] agree that our client should have at least 14 days for response on the terms proposed.”
“what procedural rules are you applying?”
“In making any decision in the adjudication whether it be the final Decision or a decision as to the procedure, I am entitled to the assistance of both parties. The Claimant has made relevant submissions relying upon its Referral, and now it is for you, if you so wish, to make submissions as to the procedural rules which you consider I should apply. Upon receiving your submissions I will then decide what rules I am applying.”
“… As we have stated before, we have no idea whether the referring party commenced the adjudication under W2, TeCSA, the Scheme or some other set of adjudication rules. It is incumbent on the referring party to be clear on this issue. It is not for us to second-guess the rules of the adjudication. …”
“If you do not presently know which rules apply, how do you know that we are not already contractually entitled (under W2) to 14 days for response?”
“In my judgment, on the facts of this case, that would not affect his [Mr Bingham’s] jurisdiction. Unlike the situation in Pegram Shopfitters Ltd v Tally Weijl (UK) Ltd[2003] EWCA Civ 1750 , there is no dispute here about the existence or otherwise of a binding contract. Moreover, on this basis [i.e. that the Scheme applied], there could be no dispute that the RICS had the jurisdiction to nominate Mr Bingham, so the point in Lead Technical Services Ltd v CMS Medical[2007] EWCA Civ 316 , where there were two competing nominating bodies, would not arise either.”
“… the adjudicator’s decision as to whether or not a particular set of contract conditions were incorporated or not would seem to me to be part of the dispute properly referred to him and would not ordinarily be a matter with which the court could interfere on enforcement.”
“The other party then has a period of 14 days within which to reply, subject to a right to extend that period by agreement. Once again, the adjudicator may set a timetable for further submissions provided that none are provided more than 14 days after the referral (unless agreed by all the parties)”
“… Unless a pure question of jurisdiction as to whether or not a contract existed at all arises, a court ought ordinarily not decide a disputed question in enforcement proceedings since that question has been left, by the terms of the statutory jurisdiction of the adjudicator, for decision by the adjudicator.”
“29. … In my judgment, the judge was wrong to conclude that it was not open to the defendants to advance their alternative contention [that there was no contract] in the enforcement proceedings. His decision was wrongly premised on the assumption that the defendants had accepted that there was a written construction contract, however the contractual dispute was resolved, and that the only dispute was as to its terms. The judge was also, I think, wrong to suppose that because (as he thought) there was a construction contract but the parties were not able clearly to identify its terms, the Scheme applied because the parties had not produced a construction contract which complied with s.108 of the 1996 Act. This was simply ducking the critical question. 30. The grounds of appeal essentially follow this line of reasoning. The defendants say that they have a real, not fanciful, prospect of establishing that Mr Morris acted without jurisdiction because he was appointed under the provisions of the Scheme when the Scheme did not apply; because on one view there was no written construction contract within s. 107 of the 1996 Act at all; because he had no jurisdiction to determine his own jurisdiction; and because he decided the substantive adjudication with reference to conditions which did not apply. This last ground is a point of substance, since, as I have indicated, resolution of the contractual dispute was critical to any decision on the claimants’ monetary claim. 31. The claimants contend that the judge properly took account of the defendant's contention in relation to the existence and identity of the construction contract and properly rejected it. Mr Hyam submits that it was a legitimate conclusion in the context of a summary judgment application that there was a written construction contract and that the identification of its precise terms was a matter of detail which did not impugn the existence of the contract, whatever its terms may have been. I rather rudely characterised this submission in argument as palm tree contractual analysis. I apologise for the rudeness but adhere to the sentiment. It was, in my judgment, necessary for the success of this summary judgment application to conclude that neither of the defendants’ contentions as to the contractual situation [JCT PC 98 or no contract at all] had any real prospect of success. … 32. The claimants further, by respondents’ notice, contend that the no contract submission is not reasonably arguable. Mr Hyam submits that, where the factual matrix demonstrates an intention on both sides to be bound by written contractual terms of a building contract, the subject matter of which is certain and evidenced by extensive communications between the parties; where the work is complete but there remains a residual dispute as to the terms under which the work was carried out, an adjudicator or judge is entitled to conclude that there is no realistic prospect of the defendants establishing that there was no contract in existence, and thus no jurisdiction of the adjudicator to adjudicate. I agree that a judge would be entitled so to conclude in appropriate circumstances, but I do not consider that these are such circumstances. It seems to me to be at least arguable either that there was a contract here, but upon JCT Prime Cost terms, or, perhaps more likely, that there was no concluded written construction contract. The judge’s recitation of the facts and the analytic contortions evidenced at [30] and [31] of his judgment, including his characterisation of the situation as a "construction contract whose terms cannot be readily ascertained", suggests to me a real possibility that there was no written construction contract. I emphasise that I do not so decide. Mr Hyam’s submission, however, overlooks the fact that the only circumstance in which the adjudicator would clearly have had jurisdiction was if the claimants’ contentions as to the contractual terms were correct. I regard this as the least likely of the three possibilities. The fact that adjudication under the Scheme and adjudication under a JCT Prime Cost Contract would be similar procedures does not overcome the twin difficulties that Mr Morris was appointed under the Scheme, and that a sufficiently secure identification of the contractual terms was intrinsically necessary to the proper performance of his adjudication task.”
“If that is so, the adjudicator had no jurisdiction. He was appointed by the wrong body. The judge was wrong to enforce the adjudication by way of summary judgment”