“To note, this only applies to the works order for the surveys as the terms for the main works will vary from this, all as previously agreed with your Geoff Taylor.”
"Further to your e-mail last week please can you confirm our understanding of the areas and the assignment of colour. There are also other items that also require Mulalley's attention and agreement so that we can progress with the order elements. This is crucial if we are to make any headway with the manufacture of the products for Leybridge Maisonettes and Merridale Tower, all of which cannot be confirmed until we have agreed the order for these areas."
“45 The general principles are not in doubt. Whether there is a binding contract between the parties and, if so, upon what terms depends upon what they have agreed. It depends not upon their subjective state of mind, but upon a consideration of what was communicated between them by words or conduct, and whether that leads objectively to a conclusion that they intended to create legal relations and had agreed upon all the terms which they regarded or the law requires as essential for the formation of legally binding relations. Even if certain terms of economic or other significance to the parties have not been finalised, an objective appraisal of their words and conduct may lead to the conclusion that they did not intend agreement of such terms to be a precondition to a concluded and legally binding agreement.”
“22. However, there are two further factors which effectively override considerations as to whether or not there were one, two, three or four contracts between the parties which establish that the Adjudicator was acting within his proper jurisdiction: (a) The substantive decision-making process upon which the Adjudicator had to embark in relation to the disputed claim put before him necessarily involved a consideration of whether there was more than one contract. It was thus within his jurisdiction to decide in effect that there was one contract, albeit one that may have been varied by agreement. (b) It was thus a part of his jurisdiction to decide whether or not and if so to what extent the Basebuild Contract had been varied by the CPA and BMS Arrangements and indeed whether there were yet further variations ordered to the Basebuild Contract. There may be cases, and this is clearly one, where substance and jurisdiction overlap so that it is within the Adjudicator’s jurisdiction to decide as matters within his or her substantive jurisdiction whether there have been in effect variations to the contract pursuant to which he or she has properly been appointed Adjudicator. It cannot then in those circumstances be a valid challenge to his or her jurisdiction that upon analysis he or she may be wrong as a matter of fact or law in determining that such variations were made to the originating contract as opposed to a series of later legally unconnected contracts. (c) ... I have therefore formed the view that the Adjudicator did have jurisdiction to rule on all the matters which he did decide in his Decision. Whether he was right or wrong to find or make the assumption that there was effectively one contract which was varied and whether he was wrong as a matter of fact or law in any other part of his decision is immaterial. Any such errors do not mean that he does not have jurisdiction. Even if I was wrong about that conclusion, then my analysis that effectively the CPA and BMS Arrangements and the Supplementary Agreement were simply variations of the Basebuild Contract would apply.” (a) The substantive decision-making process upon which the Adjudicator had to embark in relation to the disputed claim put before him necessarily involved a consideration of whether there was more than one contract. It was thus within his jurisdiction to decide in effect that there was one contract, albeit one that may have been varied by agreement. (b) It was thus a part of his jurisdiction to decide whether or not and if so to what extent the Basebuild Contract had been varied by the CPA and BMS Arrangements and indeed whether there were yet further variations ordered to the Basebuild Contract. There may be cases, and this is clearly one, where substance and jurisdiction overlap so that it is within the Adjudicator’s jurisdiction to decide as matters within his or her substantive jurisdiction whether there have been in effect variations to the contract pursuant to which he or she has properly been appointed Adjudicator. It cannot then in those circumstances be a valid challenge to his or her jurisdiction that upon analysis he or she may be wrong as a matter of fact or law in determining that such variations were made to the originating contract as opposed to a series of later legally unconnected contracts. (c) ... I have therefore formed the view that the Adjudicator did have jurisdiction to rule on all the matters which he did decide in his Decision. Whether he was right or wrong to find or make the assumption that there was effectively one contract which was varied and whether he was wrong as a matter of fact or law in any other part of his decision is immaterial. Any such errors do not mean that he does not have jurisdiction. Even if I was wrong about that conclusion, then my analysis that effectively the CPA and BMS Arrangements and the Supplementary Agreement were simply variations of the Basebuild Contract would apply.”
“The fact that adjudication under the Scheme and adjudication under a JCT Prime Cost Contract would be similar procedures does not overcome the twin difficulties that Mr Morris was appointed under the Scheme, and that a sufficiently secure identification of the contractual terms was intrinsically necessary to the proper performance of his adjudication task.”
“30. That was a case in which there could be no doubt that the adjudicator was properly appointed under the first contract and there could be no argument that, in that capacity, he had jurisdiction to decide whether later "contracts" were simply variations of the first contract or stood on their own entirely separately as contracts in their own right. I am not convinced that this case is authority for any proposition other than that there may be cases in which adjudicators properly appointed have jurisdiction to resolve jurisdictional issues if and to the extent coincidentally those issues are part of the substantive dispute referred to adjudication.”
“29. One must bear in mind that variations, that is additional, altered, substituted or omitted works, are very common and almost invariably feature in payment disputes between construction contract parties. Many of the adjudication decisions which come to be considered by the TCC involve rulings on whether particular work has been varied and if so what price is to be put on it. Generally, an adjudicator properly appointed under the original contract between the parties to the adjudication will have jurisdiction to determine whether or not particular work was or was to be treated as a variation under or pursuant to that original contract. Of course, it is open to either party to argue that, although the particular work was extra to the scope of works covered by the original contract, it was not a variation envisaged or permitted by that contract. That argument will or may in effect give rise both to a substantive defence under the original contract (“there is no entitlement to payment because there is no variation") as well as a jurisdictional challenge (“the adjudicator has no jurisdiction to decide because the extra work can not have been ordered under the original contract which gives the adjudicator jurisdiction in the first place"). This is where there will often be an overlap between jurisdiction and substance. 30. The Court of Appeal in Thomas-Fredric’s (Construction) Ltd v Keith Wilson[2004] BLR 23 confirmed broadly the uncontroversial view that an adjudicator does not have jurisdiction to decide his or her own jurisdiction unless the parties have effectively agreed or permitted him or her to do so. Simon Brown LJ (as he then was) said as follows: “32. Let me now return briefly to the editors' commentary in the Building Law Reports. I readily recognise the concern lest this salutary new statutory power to promote early payment in construction contract cases be emasculated by jurisdictional challenges. The solution, however, seems to me not in finding defendants too readily to have, in the full sense, submitted to the adjudicator's jurisdiction, which if properly advised they plainly would not do. Rather, as Dyson J observed in paragraph 8 of his judgment in the Project Consultancy Group case, it is for courts (and adjudicators) to be "vigilant to examine the arguments critically." It is only if the defendant had advanced a properly arguable jurisdictional objection with a realistic prospect of succeeding upon it that he could hope to resist the summary enforcement of an adjudicator's award against him. 33. The position can I think be summarised in the following two propositions. (1) If a defendant to a Part 24(2) application has submitted to the adjudicator's jurisdiction in the full sense of having agreed not only that the adjudicator should rule on the issue of jurisdiction but also that he would then be bound by that ruling, then he is liable to enforcement in the short term, even if the adjudicator was plainly wrong on the issue. (2) Even if the defendant has not submitted to the adjudicator's jurisdiction in that sense, then he is still liable to a Part 24(2) summary judgment upon the award if the adjudicator's ruling on the jurisdictional issue was plainly right. 34. Applying those propositions in the instant case, I would hold that this appellant did not submit to the adjudicator's jurisdiction in the full sense and that the adjudicator's ruling was, on any view, not plainly right. Indeed, as already indicated, it seems to me that the adjudicator's ruling was, if anything, plainly wrong. I would accordingly allow the appeal, set aside the order made below and substitute for it an order dismissing the respondent's application for summary judgment.”
“Where there is a requirement in the Main Contract or the Order for the provision of warranties, guarantees and/or test certificates the Sub-Contractor shall provide those warranties, guarantees or test certificates in a form acceptable to the Main Contractor within seven days of request to do so by the Main Contractor, and in any event prior to practical completion of the works. For the avoidance of any doubt the value of said warranties, guarantees and /or test certificates shall be deemed to be not less than 10% of the Order Value should the Sub-Contractor fail to adequately provide the same”
“… substantiation for the contra charges has not been provided. The defaults of Viridis that are relied upon are not shown by way of cause and effect or that it was indeed Viridis’ actions that have caused the charges that are being made by Mulalley. Additionally the quantum is shown as summaries of the costs without any substantiation of those sums ...”
“Whilst I note these charges I accept that as far as this adjudication is concerned Mulalley have not shown on the balance of probabilities that such sums are payable by Viridis as contra-charges.”