“A. Buyer [TRW Lucas] wants to purchase from Supplier [Globe] Brushless electric motor and leadframe assembly produced in accordance with the specifications attached as Appendix A (“Products”) to be used in conjunction with EPS systems. B. Supplier wants to sell Products to Buyer.”
“Buyer will purchase from Supplier all of Buyer's requirements of the Products and Supplier will sell to Buyer all such quantities of Products as Buyer [may] order from time to time pursuant to this Agreement.”
“The Products include, but are not limited to, (i) motors and leadframe assembly for 38Nm Nissan B/Renault P1. (ii) motors and leadframe assembly for 58Nm Fiat C192, and (iii) motors and leadframe assembly for 58Nm Renault P2. The parties may add additional products by mutual agreement.”
“4.1 General: Buyer reserves the right to propose, at any time, changes in the Specifications or other requirements relating to the Products (''Engineering Changes"). Supplier has to mutually agree. Buyer will advise Supplier of all Engineering Changes by giving Supplier prior written notice. If Supplier proposes to make an Engineering Change, Supplier will advise Buyer of such proposal. Before making such proposed Engineering Change, Supplier must obtain prior written approval from Buyer. 4.2 Effects of Change: Following notice of an Engineering Change by Buyer or of a proposed Engineering Change by Supplier, Supplier will use all reasonable efforts in cooperation with Buyer to minimize the effects of such Change and will submit to Buyer as soon as reasonably practicable a written statement of the anticipated effects of such Change on production costs, delivery schedules, and matters related thereto. 4.3 Cost: Buyer will reimburse Supplier for all reasonable costs associated with each Engineering Change made by Buyer within ninety (90) days following its receipt of Supplier's invoice for such costs, which such invoice will not be issued prior to the implementation of such Change. Such costs will include reasonable costs related to surplus inventory and obsolete Products, tooling, and equipment. Buyer and Supplier will negotiate, in good faith, the allocation of costs associated with each Engineering Change proposed by Supplier.”
“The quantities will depend upon the requirements of Buyer's customers (currently Fiat, Nissan, Renault). At present, Buyer estimates that it will require the following …”
“The supplier has committed to produce the products at a European manufacturing location as soon as practicable - anticipated to be in 2002.”
“The parties acknowledge and agree that Supplier shall recover its costs of tooling and capital by amortizing such costs over the units to be sold over the first five (5) years of this Agreement (''Recovery Period"). During the Recovery Period, the volume of Buyer's purchases of each Product shall be reviewed the first month of each year following the initial year of the agreement. In the event that the aggregate volume of Buyer's purchases of each Product during the preceding years is less than that which is provided in Article 1.2 above and such variance is greater than fifteen percent (15%), then Supplier shall adjust its pricing so as to amortize the remainder of Supplier's tooling and capital costs over the forecasted units to be produced for the remainder of the Recovery Period. If, at the end of the Recovery Period, Supplier shall not have fully recovered its tooling and capital costs, then Supplier shall invoice Buyer for the remaining portion of such costs and Supplier shall pay on such invoice within ninety (90) days following its receipt of such invoice.”
“The Term of this Agreement will begin on the Effective Date and shall continue for the lifetime of each of the platforms at a rate of 100% of the platform requirement as estimated in Article 1.2.”
“6.3 Entire Agreement; Amendment: This Agreement, which includes the Appendices hereto, is the only agreement between the Parties relating to the subject matter hereof. It can only be amended by a written document which (i) specifically refers to the provision of this Agreement to be amended and (ii) is signed by both Parties.”
“motors and lead frame assemblies built to different specifications from the Globe Gen 1 specification, where [TRW Lucas] required those motors and leadframe assemblies for the platforms identified in the Agreement” where two conditions were satisfied. The first was that “those motors were comprised of motors and leadframe assemblies initially produced by [Globe] but with changes to their specifications or other requirements”
“Courts will never construe words in a vacuum. To a greater or lesser extent, depending on the subject matter, they will wish to be informed of what may variously be described as the context, the background, the factual matrix or the mischief. To seek to construe any instrument in ignorance or disregard of the circumstances which gave rise to it or the situation in which it is expected to take effect is in my view pedantic, sterile and productive of error. But that is not to say that an initial judgment of what an instrument was or should reasonably have been intended to achieve should be permitted to override the clear language of the instrument, since what an author says is usually the surest guide to what he means. To my mind construction is a composite exercise, neither uncompromisingly literal nor unswervingly purposive: the instrument must speak for itself, but it must do so in situ and not be transported to the laboratory for microscopic analysis.”
“When interpreting a written contract, the court is concerned to identify the intention of the parties by reference to "what a reasonable person having all the background knowledge which would have been available to the parties would have understood them to be using the language in the contract to mean", to quote Lord Hoffmann in Chartbrook Ltd v Persimmon Homes Ltd[2009] UKHL 38 ,[2009] 1 AC 1101 , para 14. And it does so by focussing on the meaning of the relevant words, in this case clause 3(2) of each of the 25 leases, in their documentary, factual and commercial context. That meaning has to be assessed in the light of (i) the natural and ordinary meaning of the clause, (ii) any other relevant provisions of the [contract], (iii) the overall purpose of the clause and the [contract], (iv) the facts and circumstances known or assumed by the parties at the time that the document was executed, and (v) commercial common sense, but (vi) disregarding subjective evidence of any party’s intentions. …”
“a court may … take into account that, by reason of the changing conditions affecting such a contract, a flexible approach may best match the reasonable expectations of the parties. But, as in the case of all contracts, loyalty to the contractual text viewed against its relevant contextual background is the first principle of construction.”
“Wright J was incontestably right in concluding (a) that no oral variation of the written terms could have any legal effect, and (b) that in any event Mr Lateef had no authority, either actual or ostensible, to bind the Bank. This being so, nothing in the arguments advanced below or now advanced can afford a defence.”