“The Employer gives no warranty or representation as to the condition of the Site, any existing buildings or structures on the Site or any adjoining property or any services in or under the Site or as to the accuracy, reliability or sufficiency of any soils or survey data, asbestos reports, condition surveys or other data contained in any document made available to the Contractor by the Employer or as to any recommendations or conclusions made or reached in any such document.”
“The Contractor shall be deemed to have inspected and examined the Site and its surroundings and to have satisfied himself before the date of the Contract as to the nature of the ground, the sub-surface conditions and sub-soil (any information in connection therewith which may have been provided by or on behalf of the Employer being provided by way of information only without any warranty or representation as to its accuracy, reliability or completeness) the form and nature of the Site, existing buildings, services, utilities or structures on, in and under the Site, the extent, nature and difficulty of the work and materials necessary for the completion of the Works, the means of communication with and the restrictions of access to the Site, the accommodation he may require, and in general to have obtained for himself all necessary information as to risks, contingencies and all other circumstances influencing or affecting the Works or the occupation and intended use of the Site. The Contractor shall not be entitled to any extension of time or to any additional payment on the grounds of any misunderstanding or any such matter nor shall the Contractor be released from any of the risks accepted or obligations undertaken by him under this Contract on the ground that he did not or could not have foreseen any matter which might affect or have affected the carrying out and completion of the Works.”
“The Contractor has had the opportunity of inspecting the physical conditions and other conditions of the Site and structures upon it and acknowledges that it shall be solely responsible for ensuring that the ground, the Site and any existing structures to be retained under or upon or adjacent to the Site are (or will upon completion of the Works) be suitable for the development and intended occupation and use of the Site to which the Works relate and the Contractor shall be responsible for dealing with any other matters required to be dealt with in order to complete the Works. Nothing referred to in this clause 2.42.3 shall give rise to an increase in or addition to the Contract Sum, nor to an extension of time, nor give rise to any right on the part of the Contractor to determine its employment on the grounds of any misunderstanding or any such matter nor shall the Contractor be released from any of the risks accepted or obligations undertaken by him under the Contract on the ground that he did not or could not have foreseen any matter which might affect or have affected the execution of the Works.”
“Refer to separate tab for detailed schedule also issued to Cinns 3rd February 22”
“Received from Cinns 16-03-22 currently under review”
“TBC – Not reviewed as cannot accept the below”
“Existing Structures Risk sits with the Employer including insurance”; Sisk’s additional comments reads: “Employer to warrant that the structural condition of the existing fabric is suitable to facilitate the new works”; Sisk’s pricing confirmation is ticked “Unable to price”
“Not accepted. PCSA This is usually an abbreviation for Pre-Construction Services Agreement and,in this context,is plainly a reference to the period of time preceding the entry into the design and build contract in which Sisk was – at least in C&C’s opinion – in a position to investigate and satisfy itself as to such matters. period has been for Sisk to satisfy themselves on exactly these issues. We will categorically not accept a blanket exclusion on existing structures”
“Evidence of pre-contractual negotiations is not generally admissible to interpret the concluded written agreement. But evidence of pre-contractual negotiations is admissible to establish that a fact was known to both parties; … to determine which party put forward a particular term This is only admissible where the contra proferentem principle is in play: Lewison at 3.55. ; and to elucidate the general object of the contract. Evidence that parties negotiated on the basis of an agreed meaning is only admissible in support of a claim of estoppel or rectification.”
“… What is not permissible, as the decision of the House of Lords in the Chartbrook case confirms, is to seek to rely on evidence of what was said during the course of pre-contractual negotiations for the purpose of drawing inferences about what the contract should be understood to mean. It is also clear from the Chartbrook case that it is not only statements reflecting one party’s intentions or aspirations which are excluded for this purpose but also communications which are capable of showing that the parties reached a consensus on a particular point or used words in an agreed sense. The exclusion of such evidence was justified in the Chartbrook case, not on the ground that it will always or necessarily be irrelevant, but because of the costs and other practical disadvantages that would result from relaxing the rule and because the "safety devices" of rectification and estoppel will generally prevent the exclusionary rule from causing injustice.”
“A new clause 2.42.4 has been added - wording needs agreeing and including in the clarifications document”