‘Capacity Fee payable for the Contract Year in question.’ (Under clause 1.1, a ‘Contract Year’ is ‘a period during the term of this Agreement commencing at 6 o'clock a.m. on 1st October of any calendar year and ending at the same hour on 1st October of the following calendar year.’) iv. CRR is the amount of gas reserved by TGTL. It is defined as: ‘an amount equal to the sum of the Capacity Reservation Rates (expressed in Cubic Metres per Day) applicable on each Day of the Contract Year in question, adjusted in accordance with Clause 7.5 as though references in such Clause 7.5 to factor “C” were references to factor “CRR”.’ (The reference to clause 7.5, which concerns force majeure and ‘failure to deliver’, is not relevant to the present dispute). The CRR was defined under clause 1.1 as 8,334,900 Cubic Metres per Day. That sum was later adjusted in respect of the 2017-18 Contract Year, in accordance with the procedure set out in clause 21, to 6,515,000 Cubic Metres per Day. v. CC is defined as: ‘an amount equal to the sum of the CATS Capacities (expressed in Cubic Metres per Day) applicable on each Day of the Contract Year in question.’
‘reasonable Operating Expenditures (expressed in Pounds) incurred by the CATS Parties in connection with the CATS Transportation Facilities in the Contract Year in question.’
‘reasonable Extraordinary Operating Expenditures (expressed in Pounds) incurred by the CATS Parties in connection with the CATS Transportation Facilities in the Contract Year in question.’ ‘Extraordinary Operating Expenditures’ are defined in clause 1.1 as ‘expenditures of a non-capital non-recurring nature with respect to the operation of the CATS Transportation Facilities’, not including (so far as is relevant) ‘any costs or expenditures that may arise in respect of matters occurring prior to the date when the Capacity Fee […] becomes effective.’ viii. CE is defined as ‘Capital Expenditures (expressed in Pounds) amortised over their useful life reasonably and necessarily incurred by the CATS Parties after 6 o’clock a.m. on1st October 2013 to operate the CATS Transportation Facilities.’ ‘Capital Expenditures’ are defined in clause 1.1. as ‘all costs and expenditures of a capital nature for the design, purchase, construction, installation, repair or replacement of property, materials, plant and equipment, provided that Capital Expenditures shall not include any Abandonment [“decommissioning, demolition or removal”] Costs attributable to such property, materials, plant and equipment.’
‘the Agreement, the Measurement Provisions, the Allocation Provisions and any agreements made pursuant hereto contains the entire agreement between the Parties with respect to the subject matter hereof and supersede any previous understandings, commitments, agreements or representations whatsoever relating thereto, whether oral or written. This agreement shall not be varied except by an instrument in writing, of even date herewith or subsequent hereto executed by the duly authorised representatives of the Parties.’
‘10 The court's task is to ascertain the objective meaning of the language which the parties have chosen to express their agreement. It has long been accepted that this is not a literalist exercise focused solely on a parsing of the wording of the particular clause but that the court must consider the contract as a whole and, depending on the nature, formality and quality of drafting of the contract, give more or less weight to elements of the wider context in reaching its view as to that objective meaning. In Prenn v Simmonds[1971] 1 WLR 1381 , 1383H—1385D and in Reardon Smith Line Ltd v Yngvar Hansen-Tangen[1976] 1 WLR 989 , 997, Lord Wilberforce affirmed the potential relevance to the task of interpreting the parties' contract of the factual background known to the parties at or before the date of the contract, excluding evidence of the prior negotiations. When in his celebrated judgment in Investors Compensation Scheme Ltd v West Bromwich Building Society[1998] 1 WLR 896 , 912—913Lord Hoffmann reformulated the principles of contractual interpretation, some saw his second principle, which allowed consideration of the whole relevant factual background available to the parties at the time of the contract, as signalling a break with the past. But Lord Bingham of Cornhill in an extra-judicial writing, A New Thing Under the Sun? The Interpretation of Contracts and the ICS decision'' (2008) 12 Edin LR 374, persuasively demonstrated that the idea of the court putting itself in the shoes of the contracting parties had a long pedigree. 11 Lord Clarke of Stone-cum-Ebony JSC elegantly summarised the approach to construction in the Rainy Sky case[2011] 1 WLR 2900 , para 21f. In the Arnold case[2015] AC 1619 all of the judgments confirmed the approach in the Rainy Sky case: Lord Neuberger of Abbotsbury PSC, paras 13—14; Lord Hodge JSC, para 76and Lord Carnwath JSC, para 108. Interpretation is, as Lord Clarke JSC stated in the Rainy Sky case (para 21), a unitary exercise; where there are rival meanings, the court can give weight to the implications of rival constructions by reaching a view as to which construction is more consistent with business common sense. But, in striking a balance between the indications given by the language and the implications of the competing constructions the court must consider the quality of drafting of the clause (the Rainy Sky case, para 26, citing Mance LJ in Gan Insurance Co Ltd v Tai Ping Insurance Co Ltd (No 2) [2001] 2All ER (Comm) 299, paras 13, 16); and it must also be alive to the possibility that one side may have agreed to something which with hindsight did not serve his interest: the Arnold case, paras 20, 77. Similarly, the court must not lose sight of the possibility that a provision may be a negotiated compromise or that the negotiators were not able to agree more precise terms. 12 This unitary exercise involves an iterative process by which each suggested interpretation is checked against the provisions of the contract and its commercial consequences are investigated: the Arnold case, para 7, citing Re Sigma Finance Corpn[2010] 1 All ER 571 , para 12, per LordMance JSC. To my mind once one has read the language in dispute and the relevant parts of the contract that provide its context, it does not matter whether the more detailed analysis commences with the factual background and the implications of rival constructions or a close examination of the relevant language in the contract, so long as the court balances the indications given by each. 13 Textualism and contextualism are not conflicting paradigms in a battle for exclusive occupation of the field of contractual interpretation. Rather, the lawyer and the judge, when interpreting any contract, can use them as tools to ascertain the objective meaning of the language which the parties have chosen to express their agreement. The extent to which each tool will assist the court in its task will vary according to the circumstances of the particular agreement or agreements. Some agreements may be successfully interpreted principally by textual analysis, for example because of their sophistication and complexity and because they have been negotiated and prepared with the assistance of skilled professionals. The correct interpretation of other contracts may be achieved by a greater emphasis on the factual matrix, for example because of their informality, brevity or the absence of skilled professional assistance. But negotiators of complex formal contracts may often not achieve a logical and coherent text because of, for example, the conflicting aims of the parties, failures of communication, differing drafting practices, or deadlines which require the parties to compromise in order to reach agreement. There may often therefore be provisions in a detailed professionallydrawn contract which lack clarity and the lawyer or judge in interpreting such provisions may be particularly helped by considering the factual matrix and the purpose of similar provisions in contracts of the same type. The iterative process, of which Lord Mance JSC spoke in Sigma Finance Corpn[2010] 1 All ER 571 , para 12, assists the lawyer or judge to ascertain the objective meaning of disputed provisions.’
‘The [CTF] means the facilities listed below and such modifications thereto and/or replacements thereof (made in accordance with the standard of a Reasonable and Prudent Operator) from time to time: 1. The offshore riser platform jacket, decks and structural steel located in UKCS Block 22/9 adjacent to the North Everest production platform; 2. The topsides of the offshore riser platform described in paragraph 1 to the extent consisting of valving, metering and associated production equipment for the transportation of CATS Gas from the manifolds to the export riser, together with the safety and life support equipment, including hydrocarbon flare, located on such riser platform (the facilities described in paragraphs 1 and 2 hereinafter identified collectively as the “CATS Riser Platform”); … 5. The CATS 36” export riser, the 36” pipeline running from the CATS Riser Platform to the CATS Terminal together with the ancillary equipment installed for the purpose of transporting CATS Gas and CATS NGL from any points of entry to the CATS Terminal (including but not limited to equipment comprising or relating to all points of entry into the [CTF]); … Without limitation to the foregoing, the [CTF] will physically extend from the Entry Points to any Redelivery Points and the NGL Redelivery Point.’
‘However, we note clause 8(c) specifically adds the H2S Removal Facilities in the CATS Transportation Facilities, we assume that the costs of such facilities will not be passed through to TGTL in the Capacity Fee given the CATS Parties’ principal (sic) of “polluter” pays as not do so would lead to a double recovery.’
‘There will be no over recovery of costs associated with the H2S Removal Facilities as the costs used in the calculation of the estimated Capacity Fee have been prepared on a basis which ensures that this will not occur.’
‘We have ensured that there is no double dipping on costs recovered under the H2S Supplemental Agreement.’
‘(2) Ms Foulkes statement [in her email of22 August 2013 ], in its context, constituted a clear and unequivocal promise that the CATS Parties would not include costs associated with the H2S Removal Facilities in their calculation of the Capacity Fee. TGTL entered into the Amended Supplementary Agreement in reliance on this assurance. The CATS Parties are now estopped from claiming an entitlement to payment of those parts of the Capacity Fee that reflect the costs of operating and maintaining the H2S Removal Facilities. (3) Alternatively, in the email exchange between Mr Harper and Ms Foulkes, TGTL and the CATS Parties entered into a collateral agreement that the CATS Parties would not include costs of the H2S Removal Facilities in calculation of the Capacity Fee, or in any other way recover such costs from TGTL, notwithstanding that they formed part of the [CTF]. In consideration for that promise, TGTL entered into the Amended Supplementary Agreement.’
‘[22] “Capital” is generally accepted as being an expense for the purchase of an item that is expected to lead to long term benefits for a business and would thus [be] expected to be of use to a business for more than one year. … [24] “Capital nature” is not defined in the CRTA. … In the absence of the above, from an accounting experts’ point of view, it is appropriate to look for guidance at accounting standards current from time to time.’
‘36. Subsequent expenditure should be capitalised in three circumstances: (a) where the subsequent expenditure provides an enhancement of the economic benefits of the tangible fixed asset in excess of the previously assessed standard of performance. (b) where a component of the tangible fixed asset that has been treated separately for depreciation purposes and depreciated over its individual useful economic life, is replaced or restored. (c) where the subsequent expenditure relates to a major inspection or overhaul of a tangible asset that restores the economic benefits of the asset that have been consumed by the entity and have already been reflected in depreciation.’ (3) IAS 16 was revised on a number of occasions. The 1993 revision provided that the cost of an item of property, plant or equipment ‘should be recognised as an asset when (a) it is probable that future economic benefits associated with the item will flow to the enterprise; and (b) the cost of the asset to the enterprise can be measured reliably.’
‘(a) In the event that the CATS Parties have contracted the use of the CATS Transportation Facilities for Non-Capacity Gas, the CATS Operator shall promptly, subject to the provisions of Clause 24.4, give the ICI/Enron Party a notice containing the following information: (i) the field from which such Non-Capacity Gas shall be produced and the facilities through which such Non-Capacity Gas will be metered and delivered to the CATS Transportation Facilities; (ii) the proposed point of delivery of such Non-Capacity Gas into the CATS Transporation Facilities; (iii) the proposed point at which such Non-Capacity Gas is to be redelivered from the CATS Transporation Facilities; (iv) the date on which the transportation of such Non-Capacity Gas is proposed to commence; (v) the estimated date on which the transportation of such Non-Capacity Gas is proposed to terminate; (vi) the specification in a format to be agreed of such NonCapacity Gas at the point referred to in (ii) above together with a bona fide estimate of the composition of such NonCapacity Gas during the proposed period of transportation of such Non-Capacity Gas; (vii) the maximum rate of delivery of Non-Capacity Gas at such point during the proposed period of transportation; and (viii) the bona fide but non-binding estimate of the aggregate quantity and composition of Non-Capacity Gas (including Non-Capacity Gas under the contract the subject of the notice under this Clause 4.6(a)) to be delivered to the CATS Transportation Facilities for each Month of the current and each of the next 5 Contract Years and for each Quarter during the remaining term of this Agreement. (b) No less frequently than Quarterly, the CATS Operator shall, subject to the provisions of Clause 24.4, give the ICI/Enron Party a notice containing the following information: (i) any changes in the information previously provided pursuant to Clause 4.6(a); and (ii) the CATS Capacity for the ensuing Contract Year. (c) The foregoing information is provided for operational and planning purposes only and, so long as the information has been provided in good faith, the CATS Parties and the CATS Operator shall not be liable for the accuracy of any such information, nor shall any such information vary the respective rights and obligations of the Parties under this Agreement.’
‘In lieu of the Transportation Fee, a capacity fee (hereinafter referred to as the “Capacity Fee”) will be payable by the ICI/Enron Party to the CATS Parties for capacity in the CATS Transportation Facilities for each Contract Year during the period effective from 6 o’clock a.m. on1st October 2013 until 6 o’clock a.m. on1st October 2018 , which Capacity Fee shall be calculated in the following manner: CF = [CRR/CC] (OE + EOE + CE) 1.15’
‘I consider that the following principles can be derived from [Mannai Investment v Eagle Star Life Assurance[1997] AC 749 , 767E (per Lord Steyn)] and Architectural Installation Services v James Gibbons Windows (1989) 16 ConLR 68 (per HHJ Bowsher QC)]. First, that unilateral notices are to be construed in the same way as contractual documents and therefore it is necessary to construe them objectively against the background or “the relevant objective contextual scene” known to both parties. Secondly, the relevant meaning of the unilateral notices is the meaning that a reasonable recipient would have understood by the notices. The reasonable recipient “would have had in the forefront of his mind the terms” of the relevant underlying contract. Thirdly, that the purpose of the notice is relevant to its construction and validity. Prima facie, if a notice unambiguously conveys the purpose, a court will ignore immaterial errors which would not have misled a reasonable recipient. Fourthly, the notice must be sufficiently clear and unambiguous to leave a reasonable recipient in no reasonable doubt as to how and when the notice is intended to operate.’
‘[33] … The expression “futility principle” is perhaps misleading. In the present context it reflects an approach to construction which recognises that in certain circumstances (depending on the terms of the contract) a condition precedent may, as a matter of construction and in the light of subsequent events, no longer apply or may cease to have effect. [34] At para 49, the judge considered that the real argument was one of construction: “Whether a contractual obligation has arisen in any given case in principle depends on what the particular contract says, interpreted in accordance with the ordinary rules of contract interpretation. There is, in my opinion, no principle of law or even interpretive presumption which enables a contractual precondition to the accrual of a right or obligation to be disapplied just because complying with it is considered by the court to serve no useful purpose.” [35] Subject to the qualification expressed in para 33 above, we agree.’
‘[33] The starting-point of my analysis of this issue is the general appreciation by courts for over half a century that, while classifying a term as a condition precedent or as a condition may provide certainty, it can also have the effect of depriving a party to a contract of a right because of a trivial breach which has little or no prejudicial effect on the other and causes that other little or no loss. It was for that reason that, in the context of international sale and carriage contracts, the courts became more reluctant to classify terms as conditions precedent and conditions. […] The reluctance of the courts is particularly illustrated by what may be the high-water mark of this approach inSchuler (L) AG vWickman Machine Tool Sales Ltd[1974] AC 235 , in which even the use of the term ‘condition’ in a contract did not suffice. [34] In the context of insurance contracts, this appreciation is reflected by some reluctance to classify notification of loss provisions as conditions precedent: see, for example, Colman J inAlfred McAlpine plc v BAI (Run Off) Ltd [1998] CLC 1145at 1151–3. In such contracts it has been stated that what has to be found is a ‘conditional link’ between the assured's obligation to give notice and the underwriters' obligation to pay the claim: seeFriends Provident Life and Pensions Ltd v SiriusInternational Insurance Corp[2005] EWCA Civ 601 ,reportedat [2005] 1 CLC 794 at [31] per Mance LJ (as he then was). [35] The words ‘condition precedent’ are often expressly used in notification of claims clauses. But it is clear that other words can have the same effect, so long as the clause is apt to make that effect the ‘clear intention of the parties’: seeGeorge HuntCranes v Scottish Border and General Insurance[2001] EWCACiv 1964 , reportedat [2003] 1 CLC 1 at [11] per Potter LJ andEagle Star Insurance v Cresswell[2004] EWCA Civ 602 ,reportedat [2004] 1 CLC 926 at [20] per Longmore LJ. The general approach was usefully summarised in the context of a claims notification clause in a sale and purchase agreement by Teare J inAspen Insurance UK Ltd v Pectel Ltd [2008] EWHC2804 (Comm)at [62], reported at [2009] 2 All ER (Comm) 873 at 888.’
‘Because TGTL entered the TAA, it agreed that the information provided to it under clause 4.6 of the CRTA was to be provided under the TAA, pursuant to the TAA update schedules.’
‘The provisions of Schedules I [Details of Shipper at each CATS Field Meter…], VII [Capacities for Shipper and Stock Accounts] and IX [Input points, Gas Redelivery points, etc.] shall be changed to reflect any relevant changes in the parties to or details of any relevant Transportation Agreement and in accordance with any relevant provisions of or notification given under this Agreement. The provisions of Schedule IV shall be changed to reflect significant modifications, additions or extensions to the CATS Transportation Facilities. None of the Parties shall be entitled to object to any of the changes referred to in this Clause 10.8. The CATS Operator shall notify the other Parties of all amendments to Schedule I, IV, VII and IX but shall not be required to do so any more frequently than on a quarterly basis […].’
‘TGTL itself commenced an audit of the Capacity fee for 2013-14. Having opened up the Capacity Fee, TGTL cannot now resile from the consequences of the audit because it results in an unfavourable result. The restatements were in response to the audit that TGTL wanted.’
‘Any party shall have the right to dispute, in good faith, any amount specified in an invoice referred to in this Agreement.’