"The Contract Administrator shall within 14 days after the date of practical completion certified under clause 2.4 hereof certify payment as an amount due to the Contractor of 97½%... of the total amount to be paid to the Contractor under this Contract so far as that amount is ascertainable at the date of practical completion including any amounts either ascertained or agreed under clauses 3.6 and 3.7 hereof less the total amounts due to the Contractor in certificates of progress payments previously issued. The penultimate certificate shall state to what the progress payment relates and the basis on which the amount of the certificate was calculated. The final date for payment by the Employer of the amount so certified shall be 14 days from the date of issue of that certificate. If the Employer fails properly to pay the amount, or any part thereof, due to the Contractor by the final date for its payment the provisions of clause 4.2.2 shall apply. The provisions of clause 4.4 shall apply to the certificate issued pursuant to this clause 4.3."
"Where the Employer does not give a written notice pursuant to 4.4.1 and/or to clause 4.4.2 the Employer shall pay the amount stated as due in the certificate."
"The Contractor shall supply within three months... from the date of practical completion all documentation reasonably required for the computation of the amount to be finally certified by... the Contract Administrator and... the Contract Administrator shall within 28 days of receipt of such documentation, provided that... the Contract Administrator has issued the certificate under clause 2.5 hereof, issue a final certificate certifying the amount remaining due to the Contractor or due to the Employer as the case may be and such sum shall, as from the fourteenth day after the date of issue of the final certificate be a debt payable as the case may be by the Employer to the Contractor or by the Contractor to the Employer."
"Our invoice SPA B897 was due to be paid by 9th July. "
"Further to our letter of 10th July, putting you on notice of our intention to determine the contract, we note you have failed to respond or make the payment due under the contract. We therefore continued the default. "
"If the Employer makes default in any one or more of the following respects: "1 he does not pay by the final date for payment the amount properly due to the Contractor in respect of any certificate or pay any VAT due on that amount pursuant to clause 5.2 and the Supplementary Memorandum Part B... "the Contractor may give notice to the Employer which specifies the default and requires it to be ended. If the default is not ended within 7 days of receipt of the notice the Contractor may by further notice to the Employer determine the employment of the Contractor under this Contract. Such determination shall take effect on the date of receipt of the further notice. A notice of determination under clause 7.3.1 shall not be given unreasonably or vexatiously."
"Upon determination of the employment of the Contractor under clause 7.3.1 or clause 7.3.2 the Contractor shall prepare an account setting out - the total value of work properly executed and of materials and goods properly brought on the site for the purpose of the Works, such value to be ascertained in accordance with this Contract as if the employment of the Contractor had not been determined together with any amounts due to the Contractor under the Conditions not included in such total value; and - the cost to the Contractor of removing or having removed from the site all temporary buildings, plant, tools and equipment; and - any direct loss and/or damage caused to the Contractor by the determination. After taking into account amounts previously paid or otherwise discharged to the Contractor under this Contract, the Employer shall pay to the Contractor the full amount properly due in respect of this account within 28 days of its submission by the Contractor."
"A party to a construction contract may not withhold payment after the final date for payment of a sum due under the contract unless he has given an effective notice of intention to withhold payment."
"If any dispute or difference as to the construction of this Agreement or any matter or thing of whatsoever nature arising thereunder or in connection therewith ... shall arise between the Employer or the Architect/the Contract Administrator on his behalf and the Contractor either during the progress or after the completion or abandonment of the Works or after the determination of the employment of the Contractor it shall be and is hereby referred to arbitration in accordance with clause 9. If under clause 9.1 the Employer and the Contractor have not agreed a person as the Arbitrator the appointer of the Arbitrator shall be the President or a Vice-President for the time being ... of the Royal Institution of Chartered Surveyors."
"Article 4 "4.1. If any dispute or difference arises under this Agreement either party may refer it to adjudication in accordance with the procedures set out in Part D of the Supplementary Memorandum to the Agreement for Minor Building Works. If, under clause D2 the Parties have not agreed a person as the Adjudicator the nominator of the Adjudicator shall be: ... ·Royal Institution of Chartered Surveyors. ... "4.2 Subject to Article 4.1 if any dispute or difference as to any matter or thing of whatsoever nature arising under this Agreement or in connection therewith, except in connection with the enforcement of any decision of an Adjudicator appointed to determine a dispute or difference arising thereunder, shall arise between the Parties either during the progress or after the completion or abandonment of the Works or after the determination of the employment of the Contractor ... it shall be referred to arbitration in accordance with the procedures set out in Part E of the Supplementary Memorandum. "
"(1) A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section. For this purpose "dispute" includes any difference. (2) The contract shall - ... (3) The contract shall provide that the decision of the adjudicator is binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement. The parties may agree to accept the decision of the adjudicator as finally determining the dispute. ... (5) If the contract does not comply with the requirements of subsections (1) to (4), the adjudication provisions of the Scheme for Construction Contracts apply."
"For England and Wales, the Scheme may apply the provisions of theArbitration Act 1996 with such adaptations and modifications as appear to the Minister making the scheme to be appropriate ..."
"(1) A party to an arbitration agreement against whom legal proceedings are brought (whether by way of claim or counterclaim) in respect of a matter which under the agreement is to be referred to arbitration may (upon notice to the other parties to the proceedings) apply to the court in which the proceedings have been brought to stay the proceedings so far as they concern that matter. ... (4) On an application under this section the court shall grant a stay unless satisfied that the arbitration agreement is null and void, inoperative, or incapable of being performed."
"Mr Waller [counsel for the defendant] submitted that if Mr Hamblen's [counsel for the plaintiff] argument as to the meaning of a dispute is correct then an arbitrator would have no jurisdiction to make an award, either interim or final, in respect of which a defendant had no arguable defence. For example, an arbitrator would have no jurisdiction to make an award in respect of a claim for freight. Furthermore, as an additional absurdity, if an entire claim was submitted to arbitration, the arbitrator would have no power to make an award on those parts of the claim in respect of which there was no arguable defence or no real or genuine dispute, but to make an award in respect of which there was a genuine dispute but in respect of which the defendant's argument failed. This argument seems to me to be compelling, and Mr Hamblen had no real answer to it save to say that it would be unlikely to arise in practice. I have serious doubts about that proposition when applied to a defendant who is anxious to delay payment for as long as possible."
"The fallacy in the plaintiffs' argument can be seen at once if one considers what would have been the position if the plaintiffs had in fact purported to appoint Mr Barclay as their arbitrator within the time limit of nine months. They could clearly have done so, and indeed any commercial lawyer or businessman would say that is what they should have done under the clause to enforce their claim. Arbitrators are appointed every day by claimants, who believe, rightly or wrongly, that their claim is indisputable. However, on the plaintiffs' own argument, Mr Barclay would have had no jurisdiction, since there was then, as they now say, no 'dispute' to which the arbitration clause could have applied. In my view this argument is obviously unsustainable."
"... the assumption is made that arbitrations are necessarily slow processes, but whatever the position in the past, I cannot accept that as a general or universal truth today. As Mr Justice Robert Goff (as he then was) pointed out in The Kostas Melas, [1981] 1 Lloyd's Rep. 18, arbitrators have ways and means (in particular by making interim awards) of proceeding as quickly as the Courts - indeed in that particular case quicker than any Court could have acted. If a claimant can persuade the arbitral tribunal that in truth there is no defence to his claim (ex hypothesi not on the face of it a difficult task if the claim is truly indisputable) then there is no good reason why that tribunal cannot resolve the dispute in his favour without any delay at all."
"There was no dispute that the architect had issued an Interim Certificate. It therefore seems to me that the defenders became entitled to payment of the sum brought out in the Interim Certificate within 14 days of it being issued. In my opinion that is an entitlement to payment of a sum due under the contract. In order to reach the figure in the Interim Certificate one has made use of the contractual mechanism. ... The interim certificate is not conclusive evidence that the works in respect of which the pursuers seek payment were in accordance with the contract (see Clause 30.10). That however does not preclude the sum brought out in an Interim Certificate being a sum due under the contract. The structure and intent of the Act, as I understand it, and accepted by [the solicitor for the defendant], is to pay now and litigate later."
"... it seems to me that ... if letters are written by the plaintiff making some request or some demand and the defendant does not reply, then there is a dispute. It is not necessary, for a dispute to arise, that the defendant should write back and say 'I don't agree'. If, on analysis, what the plaintiff is asking or demanding involves a matter on which agreement has not been reached and which falls fairly and squarely within the terms of the arbitration agreement, then the applicant is entitled to insist on arbitration instead of litigation."
"A 'dispute' can only arise once the subject-matter of the claim, issue or other matter has been brought to the attention of the opposing party and that party has had an opportunity of considering and admitting, modifying or rejecting the claim or assertion."
"From this review of the authorities I derive the following seven propositions: "1. The word 'dispute' which occurs in many arbitration clauses and also in section 108 of the Housing Grants Act should be given its normal meaning. It does not have some special or unusual meaning conferred upon it by lawyers. "2. Despite the simple meaning of the word 'dispute', there has been much litigation over the years as to whether or not disputes existed in particular situations. This litigation has not generated any hard-edged legal rules as to what is or is not a dispute. However, the accumulating judicial decisions have produced helpful guidance. "3. The mere fact that one party (whom I shall call 'the claimant') notifies the other party (whom I shall call 'the respondent') of a claim does not automatically and immediately give rise to a dispute. It is clear, both as a matter of language and from judicial decisions, that a dispute does not arise unless and until it emerges that the claim is not admitted. "4. The circumstances from which it may emerge that a claim is not admitted are Protean. For example, there may be an express rejection of the claim. There may be discussions between the parties from which objectively it is to be inferred that the claim is not admitted. The respondent may prevaricate, thus giving rise to the inference that he does not admit the claim. The respondent may simply remain silent for a period of time, thus giving rise to the same inference. "5. The period of time for which a respondent may remain silent before a dispute is to be inferred depends heavily upon the facts of the case and the contractual structure. Where the gist of the claim is well known and it is obviously controversial, a very short period of silence may suffice to give rise to this inference. Where the claim is notified to some agent of the respondent who has a legal duty to consider the claim independently and then give a considered response, a longer period of time may be required before it can be inferred that mere silence gives rise to a dispute. "6. If the claimant imposes upon the respondent a deadline for responding to the claim, that deadline does not have the automatic effect of curtailing what would otherwise be a reasonable time for responding. On the other hand, a stated deadline and the reasons for its imposition may be relevant factors when the court comes to consider what is a reasonable time for responding. "7. If the claim as presented by the claimant is so nebulous and ill-defined that the respondent cannot sensibly respond to it, neither silence by the respondent nor even an express non-admission is likely to give rise to a dispute for the purposes of arbitration or adjudication."