“W2.1 (1) A dispute arising under or in connection with this contract is referred to and decided by the Adjudicator. A party may refer a dispute to the Adjudicator at any time. … W2.2 (1) The Parties appoint the Adjudicator under the NEC Adjudicator’s Contract current at the starting date. (2) The Adjudicator acts impartially and decides the dispute as an independent adjudicator and not as an arbitrator. W2.3 … (4) The Adjudicator may • review and revise any action or inaction of the Project Manager or Supervisor related to the dispute and alter a quotation which has been treated as having been accepted, • take the initiative in ascertaining the facts and the law related to the dispute … (8) The Adjudicator decides the dispute and notifies the Parties and the Project Manager of his decision and his reasons within twenty-eight days of the dispute being referred to him. This period may be extended by up to fourteen days with the consent of the referring Party or by any other period agreed by the Parties. The Adjudicator may in his decision allocate his fees and expenses between the Parties. (11) The Adjudicator’s decision is binding on the Parties unless and until revised by the tribunal and is enforceable as a matter of contractual obligation between the Parties and not as an arbitral award. The Adjudicator’s decision is final and binding if neither Party has notified the other within the times required by this contract that he is dissatisfied with a matter decided by the Adjudicator and intends to refer the matter to the tribunal. … W2.4 (1) A Party does not refer any dispute under or in connection with this contract to the tribunal unless it has first been decided by the Adjudicator in accordance with this contract. (2) If, after the Adjudicator notifies his decision a Party is dissatisfied, that party may notify the other Party of the matter which he disputes and state that he intends to refer it to the tribunal. The dispute may not be referred to the tribunal unless this notification is given within four weeks of the notification of the Adjudicator's decision. (3) The tribunal settles the dispute referred to it. The tribunal has the powers to reconsider any decision of the Adjudicator and to review and revise any action or inaction of the Project Manager or the Supervisor related to the dispute. A Party is not limited in tribunal proceedings to the information or evidence put to the Adjudicator. (4) If the tribunal is arbitration, the arbitration procedure, the place where the arbitration is to be held and the method of choosing the arbitrator are those stated in the Contract Data…” (2) The Adjudicator acts impartially and decides the dispute as an independent adjudicator and not as an arbitrator. (4) The Adjudicator may • review and revise any action or inaction of the Project Manager or Supervisor related to the dispute and alter a quotation which has been treated as having been accepted, • take the initiative in ascertaining the facts and the law related to the dispute … (8) The Adjudicator decides the dispute and notifies the Parties and the Project Manager of his decision and his reasons within twenty-eight days of the dispute being referred to him. This period may be extended by up to fourteen days with the consent of the referring Party or by any other period agreed by the Parties. The Adjudicator may in his decision allocate his fees and expenses between the Parties. (11) The Adjudicator’s decision is binding on the Parties unless and until revised by the tribunal and is enforceable as a matter of contractual obligation between the Parties and not as an arbitral award. The Adjudicator’s decision is final and binding if neither Party has notified the other within the times required by this contract that he is dissatisfied with a matter decided by the Adjudicator and intends to refer the matter to the tribunal. (2) If, after the Adjudicator notifies his decision a Party is dissatisfied, that party may notify the other Party of the matter which he disputes and state that he intends to refer it to the tribunal. The dispute may not be referred to the tribunal unless this notification is given within four weeks of the notification of the Adjudicator's decision. (3) The tribunal settles the dispute referred to it. The tribunal has the powers to reconsider any decision of the Adjudicator and to review and revise any action or inaction of the Project Manager or the Supervisor related to the dispute. A Party is not limited in tribunal proceedings to the information or evidence put to the Adjudicator. (4) If the tribunal is arbitration, the arbitration procedure, the place where the arbitration is to be held and the method of choosing the arbitrator are those stated in the Contract Data…”
“6. Pursuant to clause W2.4(2), we hereby give notice that the Responding Party is dissatisfied with the Decision in its entirety, save for the Adjudicator’s determinations as follows: 6.1 Paragraph 494 of the Decision: “I find that Fee should not be added to the calculation of Contractor’s Share under Clause 93.4” 6.2 Paragraph 490 of the Decision: “For the purposes of this Adjudication only NWL accepts DIJV’s calculation of the costs of completing the whole of the works in the sum of£6,311,277.82 .” 6.3 Paragraph 495 of the Decision: “I find the calculation of Amount A3 under Clause 93.2 excludes the Contractor’s Share” 6.4 Paragraph 500 of the Decision; “I find that the calculation of Amount A3 under Clause 93.2 does include delay damages.” 6.5 The sum awarded for ‘Amount A3’ as detailed in cells E14 in the ‘Amount A3’ worksheet and in cell G23 in the ‘PLN’ worksheet within Appendix 2 to the Decision. “£1,883,032.30 ” 6.6 The sum awarded for ‘Notified Defects’ as detailed in cell G9 in the ‘PLN’ worksheet within Appendix 2 to the Decision. “£102,205 ” 6.7 Sums in respect of ‘Amount A3’ and ‘Notified Defects’ form part of the Adjudicator’s determination of the sum due to the Referring Party (see paragraph 502 of the Decision). For the avoidance of doubt, the overall sum of£22,458,540.04 , as determined by the Adjudicator to be due, is not accepted by the Responding Party and is necessarily included in this Notice of Dissatisfaction, save for the elements relating to ‘Amount A3’ and ‘Notified Defects’.…” “I find that Fee should not be added to the calculation of Contractor’s Share under Clause 93.4” “For the purposes of this Adjudication only NWL accepts DIJV’s calculation of the costs of completing the whole of the works in the sum of£6,311,277.82 .” “I find the calculation of Amount A3 under Clause 93.2 excludes the Contractor’s Share” “I find that the calculation of Amount A3 under Clause 93.2 does include delay damages.” “£1,883,032.30 ” “£102,205 ”
“Accordingly, the Responding Party intends to refer the matters addressed by the Decision (excluding those matters set out at paragraph 6 above) to the tribunal (as defined by the Contract) for the final determination of the Dispute.”
“The Responding Party does not admit the validity and/or effectiveness of the Decision. This Notice of Disaffection is given entirely without prejudice to that position.”
“Further and in any event, all the Responding Party’s rights, howsoever arising, are fully reserved.”
“As you are aware, the Contract provides for the resolution of disputes “arising under or in connection with the contract” in arbitration, in accordance with the dispute resolution provisions of clause W2. In breach of that agreement to refer disputes to arbitration, NWL has commenced the Claim in the High Court. In such circumstances, DIJV is entitled to a mandatory stay of proceedings undersection 9 of the Arbitration Act 1996 (the “Act”) (once it has acknowledged service of proceedings). Further, and pursuant to the terms ofsection 9 of the Act , it would be inappropriate for us to comment on the merits or otherwise of the Claim, save to note that there is a ‘dispute.’”
“a dispute arising under or in connection with this contract”
“[91] In my view, the purpose of the 1996 Act would be substantially defeated if a responding party could, as a matter of course, reserve its position on jurisdiction in general terms at the start of an adjudication, thereby avoiding any ruling by the adjudicator or the taking of any remedial steps by the referring party; participate fully in the nuts and bolts of the adjudication, either without raising any detailed jurisdiction points, or raising only specific points which were subsequently rejected by the adjudicator (and the court); and then, having lost the adjudication, was allowed to comb through the documents in the hope that a new jurisdiction point might turn up at the summary judgment stage, in order to defeat the enforcement of the adjudicator's decision at the eleventh hour. … [92] In my view, informed by that starting-point, the applicable principles on waiver and general reservations in the adjudication context are as follows: i) If the responding party wishes to challenge the jurisdiction of the adjudicator then it must do so “appropriately and clearly”
“… If it had been intended to qualify the word "decision" in some way, then this could have been done. Why not give the word its plain and ordinary meaning? I confess that I can think of no good reason for not so doing, and none was suggested to me in argument. If his decision on the issue referred to him is wrong, whether because he erred on the facts or the law, or because in reaching his decision he made a procedural error which invalidates the decision, it is still a decision on the issue. Different considerations may well apply if he purports to decide a dispute which was not referred to him at all.”
“… Parliament has not abolished arbitration and litigation construction disputes. It has merely introduced an intervening provisional stage in the dispute resolution process. Crucially, it has made it clear that decisions of adjudicators are binding and are to be complied with until the dispute is finally resolved.” ii) In Bouygues (UK) Ltd v Dahl-Jensen (UK) Ltd[2000] EWCA Civ 507 Buxton LJ confirmed that the court’s approach to enforcement should be: “If the adjudicator has answered the right question in the wrong way, the decision will be binding. If the adjudicator has answered the wrong question, the decision will be a nullity.” iii) In Carillion v Devonport Royal Dockyard[2005] EWCA 1358 Chadwick LJ stated at [85]: “The objective which underlies the Act and the statutory scheme requires the courts to respect and enforce the adjudicator’s decision unless it is plain that the question which he has decided was not the question referred to him or the manner in which he has gone about his task is obviously unfair. It should be only in rare circumstances that the courts will interfere with the decision of an adjudicator.”
“The provisions of this Part are founded on the following principles, and shall be construed accordingly— (a) the object of arbitration is to obtain the fair resolution of disputes by an impartial tribunal without unnecessary delay or expense; (b) the parties should be free to agree how their disputes are resolved, subject only to such safeguards as are necessary in the public interest; (c) in matters governed by this Part the court should not intervene except as provided by this Part.”
“(1) A party to an arbitration agreement against whom legal proceedings are brought (whether by way of claim or counterclaim) in respect of a matter which under the agreement is to be referred to arbitration may (upon notice to the other parties to the proceedings) apply to the court in which the proceedings have been brought to stay the proceedings so far as they concern that matter. (2) An application may be made notwithstanding that the matter is to be referred to arbitration only after the exhaustion of other dispute resolution procedures. (3) An application may not be made by a person before taking the appropriate procedural step (if any) to acknowledge the legal proceedings against him or after he has taken any step in those proceedings to answer the substantive claim. (4) On an application under this section the court shall grant a stay unless satisfied that the arbitration agreement is null and void, inoperative, or incapable of being performed…”
“It thus follows from The Halki that it is no answer to an application for a stay under section 9 of the Arbitration Act that the defendant has no arguable defence to the claimant's claim. If there would otherwise be a "dispute" within section 9(1) it is no answer to an application for a stay to say that it is not a real dispute because the defendant has no defence to the claim. That was the very point decided in The Halki.”
“a dispute arising under or in connection with this contract”
“I do not consider that the mere fact that the decision may later be revised is a good reason for saying that summary judgment is inappropriate. The grant of summary judgment does not pre-empt any later decision that an arbitrator may make. It merely reflects the fact that there is no defence to a claim to enforce the decision of the adjudicator at the time of judgment.”
“…section 42 apart, the usual remedy for failure to pay in accordance with an adjudicator’s decision will be to issue proceedings claiming the sum due, following by an application for summary judgment.”
“Further, it is not as if any decision of the adjudicator could only be enforced, in a case such as this, through the medium of arbitration. It could be enforced immediately through the court, as was indicated by Dyson J in Macob Civil Engineering Ltd v Morrison Construction Ltd[1999] 1 BLR 93 at 100, especially second column (see also sections 42 and 66 of theArbitration Act 1996 ).”
“[28] This is an ingenious argument, but I cannot accept it. In my view, if the defendant wished to challenge the validity of the decision, it had an election. One course open to it was (as it did) to treat it as a decision within the meaning of clause 27, and refer the dispute to arbitration. The other was to contend that it was not a decision at all within the meaning of clause 27, and to seek to defend the enforcement proceedings on the basis that the purported decision was not binding or enforceable because it was a nullity… [29] But what the defendant could not do was to assert that the decision was a decision for the purposes of being the subject of a reference to arbitration, but was not a decision for the purposes of being binding and enforceable pending any revision by the arbitrator. In so holding, I am doing no more than applying the doctrine of approbation and reprobation, or election. A person cannot blow hot and cold: see Lissenden v CAV Bosch Ltd[1940] AC 412 , and Halsbury's Laws 4th Edition Volume 16, paragraphs 957 and 958. Once the defendant elected to treat the decision as one capable of being referred to arbitration, he was bound also to treat it as a decision which was binding and enforceable unless revised by the arbitrator. [30] I should add that in my view there is nothing in Halki which prevents the court from deciding that the defendant is precluded by its election from seeking a stay under section 9. ”