‘No sums shall be withheld from any interim payment unless agreed by [Quartzelec] or unless relating to a claim by [Honeywell] for an actual loss already incurred by [Honeywell] as a direct result of a breach of this subcontract by [Quartzelec]. No set-off or abatement relating to such a claim shall be made from any payment unless a written statement of the amount of the claim to be abated or set-off, quantified in detail and with reasonable accuracy, has been received by [Quartzelec] no less than 7 days before the final date for payment.’
‘E. APPLICATIONS FOR PAYMENT 10. Quartzelec made an application for payment number 16 on15 March 2008 in the sum of£1,408,723 . On the23 April 2008 Honeywell valued application for payment number 15 [sic] (the final date for payment of which was1 June 2008 ) in the sum of£807,622.14 and Honeywell issued a notice of intention to withhold£601,100.86 . The amount withheld in respect of the scope change from loop circuitry to interleaved radial circuitry was£189,721.89 . 11. Quartzelec have made subsequent applications number 17, 18 and 19 requesting payment of the scope of works change that has been issued with supporting documentation by Quartzelec in its correspondence dated8 February 2008 . F. DISPUTE 12. Quartzelec are entitled to payment of the sum of£189,721.89 on the application for payment number 16. Quartzelec's application for payment number 15 included the sum of£189,721.89 in relation to the costs incurred from the change in scoop from loop circuitry to interleaved radial circuitry and a sum of£275,558.55 in relation to the prolongation costs arising from the execution of the subcontract and change in scope. Quartzelec are entitled to payment of the additional sum of£189,721.89 under the application number 16 under the contract. Honeywell disputes Quartzelec's entitlement to payment for the change in scope and have withheld the monies that have become properly due. Further, the notices of intention to withhold payment issued by Honeywell do not comply with the contract in that although they specify the amount of withholding they do not specify the grounds for withholding such amounts (by reference to Quartzelec's obligations under the contract) but merely outlined matters of which complaint is to be made. Honeywell is therefore unable to withhold any amount from Quartzelec. Quartzelec also disputes the grounds and the separate amounts attributable to such grounds as outlined in the notices of intention to withheld payment issued by Honeywell. … I. RELIEF SOUGHT 17. Quartzelec requests and will request that the Adjudicator decide that's a change in the scope of works has occurred and that Quartzelec are entitled to payment within seven days: a) the sum of£189,721.89 or such sum as the Adjudicator decides (in payment of the entitlement arising out of the scope change); b) the sum of£275,558.55 or such sum as the Adjudicator decides (in payment of the entitlement arising as of the prolongation costs caused by the scope change). c) …’
‘7.1. The relief sought by Quartzelec is the payment of money arising from payment application number 15. The amounts now claimed were first sought in that application. They have also been claimed in subsequent applications. There is of course an important difference between: 7.1.1. Fixing the correct amount for a change in scope; and 7.1.2. Deciding whether an additional amount must be paid in respect of that change in scope for a specific payment application. 7.2. The first question simply requires an assessment of the change in scope. The second question however can be affected by broader valuation issues which reduce the amount payable. For example, if omissions in scope were directed prior to the payment application but were not taken into account in calculating the payment notice, then those omissions can be raised to diminish any amount now said to be due on the application by virtue of the correct evaluation of an increase in scope. In short, to reach a conclusion about a further amount due under a payment application, any relevant items which might reduce the amount in the payment notice should also be taken into account. 7.3. The consideration of such items does not require a withholding notice. This is discussed further in Honeywell's comments on the Referral Notice, but in brief this is because the question is one of valuation rather than of set off, abatement or counterclaim. The adjudicator has been asked on certain terms to value the payment application, therefore points leading to a reduction in valuation are free to be raised. 7.4. There is one such point on which Honeywell relies. It is an omission in scope arising from the combination of the disabled refuge telephones with fire telephones for buildings 13A, 13B and 13D. This omission escaped Honeywell's attention until very recently when considering the final account. The omission was made between February and May 2007 for the three buildings and therefore well preceded payment application 15. Honeywell was therefore at liberty to reduce payment application 15 on the basis of this omission…. as an exercise in valuation therefore Honeywell requests the adjudicator to offset the omission in scope for combining telephones from any amount assessed for the increase in scope due to radial circuitry for building 13D.’
‘7. Again Honeywell seek to extend the jurisdiction of the Adjudicator by introducing items that are not contained within the scope of the dispute that has been referred, furthermore and due to Honeywell's failure to provide an appropriate withholding notice in detailing the issue's of contention, Quartzelec aver to any prior discussion in respect of this item (sic). In re quoting our previous statement, it is clear that the Adjudicator's jurisdiction is confined to within the limits of the dispute referred in the Notice of Adjudication, and in reasserting the case law quoted by Honeywell [KNS v. Sindall] There is no agreement from Quartzelec to extend the Adjudicator's jurisdiction to include the matters raised in section 7 of Honeywell's Response. 7.1. Quartzelec do not consent to the adjudicator determining his own jurisdiction and reserves the right to raise these challenges in due course. 7.2. Quartzelec aver that the Adjudicator's decision is limited to those matters correctly referred to in the notice and as provided by those matters raised in section B of this document.’
‘Respondent’s case 28.1. It is contended that if there is an amount due to Quartzelec in the adjudication, then Honeywell is entitled to make an abatement for an omission in the scope of the subcontract works; on the basis that the omission was notified prior to the payment notice in connection with application for payment number 15 but not given effect at that time. In support of this contention I am directed to case law. Referring party’s case 28.2. Quartzelec avers that it has not been advised of any omission or its effect on any valuation. In the event, no withholding notice has been issued. Furthermore, my attention is drawn to case law with the object of demonstrating that the introduction of the proposed abatement is out with my jurisdiction. Decision 28.3. Whilst acknowledging the ingenuity of Honeywell's argument I fail to be persuaded by it. In my opinion and having read the relevant cases, the proposed abatement would have needed to have been in play prior to the Notice of Adjudication, rather like Quartzelec's claim for interest, for it to have been part of the dispute. While Honeywell is entitled to run any defences in contradiction of Quartzelec's various claims 62 William Verry v Furlong Homes[2005] EWHC 138 (TCC) 62, they must surely be of direct relevance to those claims. For example, the reason that 100% payment has not been made is because the work is not complete and/or defective hence the claimant is not entitled to the full rate. Having read paragraph 37 of PC Harrington v Multiplex I cannot appreciate how the parties’ agreement to something in that contract is a statement of law. While I recognise the distinction that Honeywell is making viz its claim is in diminution of any amount found to be due as opposed to a positive request for payment, this does not necessarily admits items unrelated to the matters in dispute. 28.4. In addition, I have consulted a reference book 63 Chapter 10, Construction Adjudication by HHJ Peter Coulson QC. 63 for further guidance. I cannot detect any direct example of the issue under consideration and therefore have no firm basis for contradicting my own conclusion in this regard. 28.5. Furthermore, I believe that if I were to value the variation combining the disabled refuge telephones with the fire telephones, then I am opening up a revaluation of application for payment number 15 in its entirety; and if this is the case, I wonder should this not include a valuation of Quartzelec's claims for additional fire cabling. While there is an element of ambiguity in this regard, for Honeywell says at paragraph 7.5 of the Rejoinder narrative ‘There is a dispute over the proper valuation of payment application 15 and that question requires the consideration of the decrease in scope submitted by Honeywell’, I do not believe the intention is for me to give this a wider meaning than the scope change. As Honeywell has successfully argued that the scope change is limited to the change to radial circuitry (and the effects thereof) I cannot accept the proposition for valuing Honeywell's unrelated claim. To take Honeywell's logic further: any item connected with the Sub-Contract is open for review in the guise of an abatement and can be used in diminution of an award. I do not believe the case law supports this contention. If it were otherwise, then every respondent to adjudication, irrespective of the contents of the payment notice, could avail itself of this type of defence rendering the basis for the referring party’s decision to embark on this form of dispute resolution misconceived.’
‘However, where a party has an opportunity to consider the position of the opposite party and to formulate arguments in relation to that position, what constitutes a ‘dispute’ between the parties is not only a ‘claim’ which has been rejected, if that is what the dispute is about, but the whole package of arguments advanced and facts relied upon by each side.’
‘In all cases where there is a decision on one dispute or difference, and the adjudicator acts materially, in excess of jurisdiction or in breach of the rules of natural justice, the decision will not be enforced by the court.’
‘(a) The first step must be to ascertain what dispute or disputes has or have been referred to adjudication. One needs to see whether in fact or in effect there is in substance only one dispute or two, and what any such dispute comprises.’