“If any dispute or difference of any kind whatsoever shall arise between the Employer and the Contractor in connection with or arising out of the Contract or the carrying out of the Works including any dispute as to any decision opinion instruction direction certificate or valuation of the Engineer (whether during the progress of the Works or after their completion and whether before or after the determination abandonment or breach of the Contract) it shall be referred to and settled by the Engineer who shall state his decision in writing and give notice of the same to the Employer and the Contractor. … Such decisions shall be final and binding upon the Contractor and the Employer unless either of them shall require that the matter be referred to arbitration as hereinafter provided. If the Engineer shall fail to give such decision for a period of 3 calendar months after being requested to do so or if either the Employer or the Contractor be dissatisfied with any such decision of the Engineer then and in any such case either the Employer or the Contractor may within 3 calendar months after receiving notice of such decision or within 3 calendar months after the expiration of the said period of 3 months (as the case may be) require that the matter shall be referred to the arbitration of a person to be agreed upon between the parties or … a person to be appointed … by the President for the time being of the Institution of Civil Engineers. … Any such arbitration shall be deemed to be a submission to arbitration within the meaning of theArbitration Act 1950 or theArbitration (Scotland) Act 1894 as the case may be or any statutory re-enactment or amendment thereof for the time being in force. Any such reference to arbitration may be conducted in accordance with the Institution of Civil Engineers’ Arbitration Procedure (1983) or any amendment or modification thereof being in force at the time of the appointment of the arbitrator and in cases where the President of the Institution of Civil Engineers is requested to appoint the arbitrator he may direct that the arbitration is conducted in accordance with the aforementioned Procedure or any amendment or modification thereof. Such arbitrator shall have full power to open up review and revise any decision opinion instruction direction certificate or valuation of the Engineer and neither party shall be limited in the proceedings before such arbitrator to the evidence or arguments put before the Engineer for the purpose of obtaining his decision above referred to. The award of the arbitrator shall be final and binding on the parties.”
“Additionally the minutes did not record Amec’s views that the bearings had been installed correctly or that FIP Industrials had provided bearing calculations for the cracked roller bearing (the Contract required the Contractor’s design to be adopted by the Engineer) and that these had been checked by Pell Frischmann and forwarded to Atkins on5th September 2002 .”
“Notwithstanding that detailed work, the Highways Agency’s stance is firmly that there is a defect to be addressed here by one or more of the parties involved and the Highways Agency will be looking for the cost of correcting that defect (or defects) to be met by others. In the light of the latest developments on the additional piers, I would appreciate a formal response from your company, including any proposals to address the problems identified once you have received the factual report referred to earlier.”
“It is considered from the limited information presently available that the Contractor has provided and installed roller bearings which are not in accordance with the Contract. It is the opinion of the Engineer that the defects have resulted from the use of materials or workmanship not in accordance with the Contract and that this constitutes a breach of contract. Reference is made to Clause 8 of the Conditions of Contract, Contractors’ General Obligations and to Clause 61(2), Unfulfilled Obligations.”
“1. The word “dispute” which occurs in many arbitration clauses and also in section 108 of the Housing Grants Act should be given its normal meaning. It does not have some special or unusual meaning conferred upon it by lawyers. 2. Despite the simple meaning of the word “dispute”, there has been much litigation over the years as to whether or not disputes existed in particular situations. This litigation has not generated any hard-edged legal rules as to what is or is not a dispute. However, the accumulating judicial decisions have produced helpful guidance. 3. The mere fact that one party (whom I shall call “the claimant”) notifies the other party (whom I shall call “the respondent”) of a claim does not automatically and immediately give rise to a dispute. It is clear, both as a matter of language and from judicial decisions, that a dispute does not arise unless and until it emerges that the claim is not admitted. 4. The circumstances from which it may emerge that a claim is not admitted are Protean. For example, there may be an express rejection of the claim. There may be discussions between the parties from which objectively it is to be inferred that the claim is not admitted. The respondent may prevaricate, thus giving rise to the inference that he does not admit the claim. The respondent may simply remain silent for a period of time, thus giving rise to the same inference. 5. The period of time for which a respondent may remain silent before a dispute is to be inferred depends heavily upon the facts of the case and the contractual structure. Where the gist of the claim is well known and it is obviously controversial, a very short period of silence may suffice to give rise to this inference. Where the claim is notified to some agent of the respondent who has a legal duty to consider the claim independently and then give a considered response, a longer period of time may be required before it can be inferred that mere silence gives rise to a dispute. 6. If the claimant imposes upon the respondent a deadline for responding to the claim, that deadline does not have the automatic effect of curtailing what would otherwise be a reasonable time for responding. On the other hand, a stated deadline and the reasons for its imposition may be relevant factors when the court comes to consider what is a reasonable time for responding. 7. If the claim as presented by the claimant is so nebulous and ill-defined that the respondent cannot sensibly respond to it, neither silence by the respondent nor even an express non-admission is likely to give rise to a dispute for the purposes of arbitration or adjudication.”
“63. For my part I would accept those propositions as broadly correct. I entirely accept that all depends on the circumstances of the particular case. I would, in particular, endorse the general approach that while the mere making of a claim does not amount to a dispute, a dispute will be held to exist once it can reasonably be inferred that a claim is not admitted. I note that Jackson J does not endorse the suggestion in some of the cases, either that a dispute may not arise until negotiation or discussion have been concluded, or that a dispute should not be likely inferred. In my opinion he was right not to do so. 64. It appears to me that negotiation and discussion are likely to be more consistent with the existence of a dispute, albeit an as yet unresolved dispute, than with an absence of a dispute. It also appears to me that the court is likely to be willing readily to infer that a claim is not admitted and that a dispute exists so that it can be referred to arbitration or adjudication. I make these observations in the hope that they may be of some assistance and not because I detect any disagreement between them and the propositions advanced by Jackson J.”
“(1) No copy of the Highways Agency’s request for a clause 66 decision was sent to Amec. (2) No copy of Amec’s letter dated 10th December was sent to the Engineer for his information. (3) Amec were not given an opportunity to make submissions to the Engineer before the Engineer made his decision. (4) The Engineer had substantially drafted his decision before receiving the formal request for a decision under clause 66. (5) The Engineer was told that his decision was needed urgently. He was influenced by the urgency. He produced the final version of his decision with undue speed. (6) Because the Highways Agency was making a parallel claim against the Engineer, the Engineer was faced with so stark a conflict of interest that he could not properly discharge his duties.”
“… was not regarded by the parties as a person who had necessarily to listen to both sides, or to notify the contractor and give him an opportunity to be heard. I think he was entitled to form an opinion on the basis of his own knowledge of the progress of the works and his general knowledge and experience as an Engineer. If he required further information … then surely the parties must have contemplated that he would make his own enquiries, and if he chose to make them from the contractor that he would not necessarily be bound to give the employer an opportunity to check the information he gathered before finally forming an opinion.”
“By entering into the contract the respondents agreed that the appellant’s surveyor should discharge both these duties and therefore they cannot claim that the appellant’s surveyor must be in the position of an independent arbitrator, who has no other duty which involves acting in the interests of one of the parties.”
“In Hatrick the term “fairness” was avoided in the judgments, Richmond J saying that he resisted it partly because of its vagueness and partly because it might be regarded as equivalent to natural justice. Since then, however, in Sutcliffe v Thackrah[1974] AC 727 (1977), 4 BLR 16 the House of Lords have used that very term to describe the duty of an architect when acting not as an arbitrator or quasi-arbitrator but in the role of valuer or certifier. Lord Reid (with whom Lord Hodson agreed), Lord Morris and Lord Salmon all spoke of a duty to act in a fair and unbiased manner or fairly and impartially, although Viscount Dilhorne appears to have regarded an honest exercise of professional skill and judgment as enough. The tenor of the opinions of the majority of their Lordships accords with the substance of the Hatrick judgments, if not with their actual wording. In our opinion it should be held in the light of these authorities that in certifying or acting under Clause 13 here the Engineer, though not bound to act judicially in the ordinary sense, was bound to act fairly and impartially. Duties expressed in terms of fairness are being recognised in other fields of law also, such as immigration. Fairness is a broad and even elastic concept, but it is not altogether the worse for that. In relation to persons bound to act judicially fairness requires compliance with the rules of natural justice. In other cases this is not necessarily so.”
“It seems to me that under a building contract the architect has to discharge a large number of functions, both great and small, which call for the exercise of his skilled professional judgment. He must throughout retain his independence in exercising that judgment; but provided he does this, I do not think that, unless the contract so provides, he need go further and observe the rules of natural justice, giving due notice of all complaints and affording both parties a hearing. His position as an expert and the wide range of matters that he has to decide point against any such requirement: and an attempt to divide the trivial from the important, with natural justice applying only to the latter, would be of almost insuperable difficulty. It is the position of independence and skill that affords the parties the proper safeguards, and not the imposition of rules requiring something in the nature of a hearing. For the rules of natural justice to apply, there must, in the phrase of Mr. Harman, be something in the nature of a judicial situation; and this is not the case.”
“The building owner and the contractor make their contract on the understanding that in all such matters [decisions reflected in the amounts contained in certificates issued by the architect] the architect will act in a fair and unbiased manner and it must therefore be implicit in the owner’s contract with the architect that he shall not only exercise due care and skill but also reach such decisions fairly, holding the balance between his client and the contractor.”
“They were employed and paid by the appellant. The duties involved that the architect would act fairly: he was to act fairly in ensuring that the provisions of the building contract were carried out. He was to exercise his care and skill in so ensuring. But his function differed from that of one who has to decide disputes between a building owner and a contractor.”
“The certifier is not expected to conduct a judicial inquiry. He is there to decide matters by the exercise of his skill and knowledge…Of course, if he hears from one party representations which are of such a nature as to be calculated to influence him in arriving at his determination, then he must afford the other party the opportunity of answering what is alleged against him.”
“The next question is, what does this attribute involve, when tested by objective conduct? Audi alteram partem, said Mr Sanders. If by this submission Mr Sanders meant that it was obligatory upon the engineer to hear either party before giving his certificate, I would agree with Richmond J. that this submission must be rejected. But I understood Mr Sanders to make the more limited submission…I agree that if he heard material representations from one, that attribute of impartiality and independence which I have accepted as essential to his functions must have been lost if he did not give to the other an opportunity to be heard likewise.”
“In our opinion it should be held in the light of these authorities that in certifying or acting under Clause 13 here the engineer, though not bound to act judicially in the ordinary sense, was bound to act fairly and impartially. Duties expressed in terms of fairness are being recognised in other fields of law also, such as immigration. Fairness is a broad and elastic concept, but it is not altogether the worse for that. In relation to persons bound to act judicially fairness requires compliance with the rules of natural justice. In other cases this is not necessarily so. But we do not think it can be confined to procedure. Its use in the authorities in combination with “impartiality” suggests that it is not meant to be a narrow concept.”