“9.2 If a dispute or difference arises under this Contract which either Party wishes to refer to adjudication, the Scheme shall apply, subject to the following: .1 for the purposes of the Scheme the Adjudicator shall be the person (if any) and the nominating body shall be that stated in the Contract Particulars…”
“1. Main Works Stages Contract Sum£749,726.00 Less [various items] Less Client’s Prov Sum£20,000.00 £686,226.00 5. Variations/Instructions Add [various items] Kitchen as Martin Luck£37,752.00 [3 more items] Prolongation costs from7th Nov 2010 to21st Jan 2011 11 weeks @£1,500 per week£16,500.00 Total£802,032.13 Less 2.5% Retention£20,050.80 £781,981.33 Less Previously Certified£678,497.17 Nett Application£103,484.16 excl VAT”
“1. Main Works Stages Contract Sum£749,726.00 Less [various items ] Less Client’s Prov Sum£20,000.00 *Less Contingency 5%£35,701.00 £650,525.00 5. Variations/Instructions Add [as before] *Lettering to external gable£753.00 *Change ceiling from suspended grid to mf ceiling£4,470.00 *Prolongation costs from7th Nov 2010 to26th Nov 2010 3 weeks @£1,500 per week£4,500.00 *Interest for amounts not certified and incorrect retention£3,454.53 *Interest for unfixed materials on-site not valued or included in Arch Certificates£340.89 *Insurance of completed buildings from 6th Jan 11£1,450.00 * Prolongation costs from26th Nov 2010 to2nd March 2011 14 weeks @ say£1,200 per week£16,800.00 *Legal costs to conclude settlement of final accounts say£12,000.00 Total£776,108.15 *Less 1.5% Retention£11,641.62 £764,466.53 *Less Previously Certified£668,681.05 Nett Application£95,785.48 excl VAT”
“1. The Works were practically complete by6 January 2011 , or in the alternative28 January 2011 . The continued with-holding of the certificate of practical completion is a breach of contract for which damages are claimed. 2. No proper extension of time has been granted. Damages are claimed as a result. 3. No proper ascertainment, certification or payment of loss and expense has been received. Damages and interest are claimed as a result. 4. Our Client’s draft final accounts submitted on21 January 2011 has not been properly valued and certified in accordance with the Contract and interest and damages are claimed as a result. 5. Retention has been incorrectly deducted throughout, and is being with-held now beyond practical completion, in further breach of contract. Again, interest and damages are claimed as a result.”
“…proceeding to compile its case for a referral to an Adjudicator. As we have noted to you previously, this will necessarily involve the Council in unnecessary expenditure of approximately£35,000 on top of the debt due to our client, which is a further£107,427.10 plus VAT.”
“7. [Beam] submitted its draft final account for the Works on21 January 2011 in the sum of£802,032.13 , and the latest payment certificate issued by the Employer’s Agent dated2 February 2011 certified a gross£703,874.79 , less 5% retention, being£668,681.05 net paid to date. 8. [Beam] submitted its final account for the works on to March 2011 in the sum of£776,108.15 . 9. In breach of contract, [the Council] has deducted 5% retention through its gross valuations, certificates and payments for this project, despite the Contract stating at Clause 4.18.1 that retention was agreed to be 3%. Interest is due as a result of this underpayment throughout the project and is claimed. 10. By a letter dated11 March 2011 …[the Council] purported to terminate the Contract under Clause 8.4.2…However, [the Council] failed to serve any prior notice under Clause 8.4.1, and the purported termination is void and of nil effect… 12. On 23 March, [Beam] arrived on site to find that the locks had been changed by the [Council] on or around 22 March, without notice. To deny access in this matter is a fundamental breach of contract. In the alternative, this is a repudiatory breach which [Beam] has no alternative but to accept, therefore bringing the Contract to an end…. 15. Interest is claimed on all sums due amount paid, in accordance with the Clause 4.10.6 of the Contract… 19. And whereas the following dispute has arisen between the parties requiring the decision of an adjudicator: 19.1. What value is due to [Beam] from [the Council]? 19.2. What value is due to [Beam] from [the Council] under and in connection with the account dated21 January 2011 ? 19.3. What value is due to [Beam] under and in connection with the account dated to March 2011? 19.4. What is the time or times for payment? 19.5. What sum is due to [Beam] as interest? 19.6. Is [Beam] entitled to recover the costs of the action? 19.7. Is [Beam] entitled to such further or other sums from [the Council] as the Adjudicator decides?”
“20. [Beam] submitted its draft final account for the Works on21 January 2011 in the sum of£802,032.13 and the latest payment certificate issued by the Employer’s Agent dated2 February 2011 certified a gross£703,874.79 , less 5% retention, being£668,681.05 net paid to date. Copies of applications for payments and valuations and certificates for payment are enclosed… 21. [Beam] submitted its final account for the works on2 March 2011 in the sum of£776,108.15 . 22. In breach of contract, [the Council] has deducted 5% retention throughout its gross valuations, certificates and payments for the project, despite the Contract stating at Clause 4.18.1 that the retention was agreed to be 3%. Interest is due as a result of this underpayment throughout the project, and is claimed. 23. Interest is claimed on all sums due and underpaid, in accordance with the Clause 4.10.6 of the Contract.”
“30. Secondly, the contractual right of [the Council] to withhold retention is at an end, and all retention must be returned. 31. Thirdly, the time periods in the Contract for dealing with the final accounts are obviously not applicable.”
“(1) The Contract Completion date is07 November 2010 (2) Extension of Time: 3 weeks already awarded therefore26 November 2010 . Adjudicator: It is not clear as to how the Extension of Time has been awarded. Further, the Extension of Time challenge in Beam’s letter (Simon Lee22 February 2011 ) is not met head on. The Adjudicator doing the best he can takes the Extension of Time within 3 weeks of 06 January and identifies 3 x£1000 LAD applies. ISSUE: "Termination of the Main Contract". Witney issued a "Termination by Employer" notice under JCT [clause 8.4] on14 March 2011 . Adjudicator: Witney is too late. Such termination machinery only applies prior to Practical Completion. Adjudicator answers: Witney’s attempt to terminate fails. ISSUE: “Did Witney repudiate the contract?" Adjudicator answers: YES. Beam denied access22 March 2011 (to complete Works or carry out snagging). This is repudiatory breach, which is accepted… ISSUE: “Was Beam entitled to complete the outstanding Works, carry out remedial Work and snagging?" Adjudicator answers: YES”
“Did Witney repudiate the contract?" ISSUE: “Was Beam entitled to complete the outstanding Works, carry out remedial Work and snagging?" Adjudicator answers: YES”
“14. ISSUE: “What value is due to [Beam] in connection with the account21 January 2011 ?" Adjudicator: NONE. The document sent by Beam on21 January 2011 is headed "Draft Final Account"…This is not a Final Account ("Final Statement" per JCT [clause 4.12]) it is merely a draft. It merely foreshadows what is yet to come being the Final Statement. No liability arises on the mere draft.”
“19.1 What value is due to the [Beam] from [the Council]? Adjudicator Answers: Gross£735,000 19.2 What value is due to [Beam] from the Council] under and in connection with the account dated21 January 2011 ? Adjudicator Answers: None 19.3 What value is due to [Beam] from the Council] under and in connection with the account dated2 March 2011 ? Adjudicator Answers:£735,000 less previous payments. 19.4: What is the time or times for payment? Adjudicator Answers: The new date was 02 March. The Final Date for Payment is02 April 2011 . 19.5 What sum is due to [Beam] as interest? Adjudicator answers:£66,319 x 5.5% for 2 months =£640 19.6 Is [Beam] entitled to recover the costs of the action? Adjudicator answers: That Adjudicator allocates his fees to be paid by [the Council]. No other legal fees are allocated/allowed. 19.7 Is [Beam] entitled to any such further or other sums from [the Council]? Adjudicator answers: The Net Due Sum forthwith to Beam is£69,819.00 plus£640.00 (all excluding VAT) plus the Adjudicator’s fee, if already paid by Beam to the Adjudicator.”
“20. It is to be noted that the HGCRA refers to a "dispute" and not to "disputes". Thus, at any one time, a referring party must refer a single dispute, albeit that the Scheme allows the disputing parties to agree, thereafter, to extend the reference to cover "more than one dispute under the same contract" and "related disputes under different contracts". During the course of a construction contract, many claims, heads of claim, issues, contentions and causes of action will arise. Many of these will be, collectively or individually, disputed. When a dispute arises, it may cover one, several or many of one, some or all of these matters. At any particular moment in time, it will be a question of fact what is in dispute. Thus, the "dispute" which may be referred to adjudication is all or part of whatever is in dispute at the moment that the referring party first intimates an adjudication reference. In other words, the "dispute" is whatever claims, heads of claim, issues, contentions or causes of action that are in then in dispute which the referring party has chosen to crystallise into an adjudication reference. A vital and necessary question to be answered, when a jurisdictional challenge is mounted, is what was actually referred? That involves a careful characterisation of the dispute referred to be made. This exercise will not necessarily be determined solely by the wording of the notice of adjudication since this document, like any commercial document having contractual force, must be construed against the underlying factual background from which it springs and which will be known to both parties… 22. Neither of these contentions of Fastrack is sustainable. The statutory language is clear. A "dispute", and nothing but a "dispute", may be referred. If two or more disputes are to be referred, each must be the subject of a separate reference. It would then be for the relevant adjudicator nominating body to decide whether it was appropriate to appoint the same adjudicator or different adjudicators to deal with each reference. Equally, what must be referred is a "dispute" rather than "most of a dispute" or "substantially the same dispute". 23. In some cases, a referring party might decide to cut out of the reference some of the pre-existing matters in dispute and to confine the referred dispute to something less than the totality of the matters then in dispute. So long as that exercise does not transform the pre-existing dispute into a different dispute, such a pruning exercise is clearly permissible. However, a party cannot unilaterally tag onto the existing range of matters in dispute a further list of matters not yet in dispute and then seek to argue that the resulting "dispute" is substantially the same as the pre-existing dispute. 24. Even this prohibition will not always apply since the Scheme gives the adjudicator two powers: to take the initiative in ascertaining the facts and the law necessary to determine the dispute; and to resign if the dispute varies significantly from the dispute referred to him in the referral notice and, for that reason, the adjudicator is not competent to deal with the varied dispute. These powers show that it is possible that a dispute that has validly been referred to adjudication can in some circumstances, as the details unfold during the adjudication, become enlarged and change its nature and extent. If this happens, it is conceivable that at least some of the matters or issues referred to adjudication by the referring party which were not previously encompassed within a pre-existing dispute could legitimately become incorporated within the dispute that has been referred during the process of its enlargement whilst the adjudication proceeds. 25. These considerations do not lead to the conclusion that Morrison's submissions are correct, namely that only the precise sums previously claimed may be referred to adjudication; that no additional or lesser sum may be claimed; and that if a different sum is claimed, the consequence is that the whole reference, in its entirety, is without any jurisdiction. A claim can often be made without its quantification having been finalised or even attempted. The subsequent dispute can then be in the form: "what sum is due?" as opposed to "is £x due?" 26. Thus, whether or not the reference is wholly or partly lacking in jurisdiction will depend on the nature and extent of the dispute that has purportedly been referred to adjudication by the referring party. A particular dispute may be correctly characterised as being in this form: "what sum is due for a particular interim payment?" or "what sum is due for a particular item of work?" or "what sum is due at the Final Account stage?" without any particular or finalised sum being included as part of that claim. Alternatively, the dispute may be correctly characterised as being one concerning the question of whether or not a particular specified sum is due. In the first type of dispute, it would not necessarily follow, if a larger sum had been included in the notice of adjudication than the sum previously claimed in the relevant application, that no dispute had yet arisen. There would be three alternative possibilities in such a situation: that the whole sum referred could be adjudicated upon (the dispute being a general one as to what sum is due and the sums contained in the notification of the dispute and the notice of adjudication being no more than particulars of the overall dispute); that the sum referred should be split by the adjudicator and only the sum previously claimed adjudicated upon (the dispute being as to whether that particular sum was due); or that no part of the sum referred could be adjudicated upon (since the nature and extent of the subject-matter of the reference had transformed it into something different from the pre-existing claim).”
“7…When the matter came before me as a paper application for permission to appeal, I expressed the view that the judge's reasoning, to which I have just referred, was correct. I said that if Interim Claim 9 had included a claim for extended preliminaries and any other time related sums, there would have been a clear link between the figure claimed for Valuation 9 and the claimant's claim in relation to extensions of time and the validity of the certificate of non-completion. I also expressed the view that the judge's decision on the question of waiver was correct. 8. Before us this morning, Mr Newman does not seek to revive the waiver or estoppel issue that was raised before the judge. Moreover, as I understand it, he does not seek to challenge the reasoning of the judge to which I have referred. He accepts that in this case there was no claim for extended preliminaries in the ordinary sense. His main point is that the claim for 45 weeks, for the hire of kitchen portakabin, was a time-related item sufficient to provide a bridge between the claim in respect of Interim Valuation 9, and the time issues raised by the claim for extension of time and the issue in relation to the validity of the certificate of delay. 9. The portakabin issue was not the subject of any argument, either before the adjudicator or before the judge. It seems to me that the portakabin matter has no materiality to the issues which the Contractor seeks to raise before this court. It is not in dispute, as I understand it, that the portakabin was not for the Contractor's use and was no part of its preliminaries. The portakabin was hired by the Contractor for the use of the employer in relation to kitchen work, which would not be finished until after the completion of the appellant's works. It seems not to be in dispute that there was an agreement between the parties that the employer would reimburse the Contractor fully for the cost of the hire of the kitchen and portakabin and that they did so without dispute. There was simply no dispute between the parties about this item. 10. In my judgment, it is wholly artificial to say that because Interim Valuation 9 included as one of its many items this portakabin item, that that afforded the necessary link between the valuation dispute raised by the claim under Valuation 9 and the time related disputes to which I have already referred.”