“7.2 The Fee shall (subject to VDC’s rights of set-off and deduction) be payable in the instalments stated in Schedule 1 (the ‘specified dates’). The application date for payment of each instalment shall be the specified date in Schedule 1 and the Consultant shall submit an invoice on or before the relevant application date. The due date for payment of each instalment shall be the specified date in Schedule 1. The Consultant’s invoice shall state the amount the Consultant considers due to him as at the due date and the basis on which such amount has been calculated (the ‘Notified Sum’) and shall be accompanied by such documents, receipts and vouchers as may reasonably be required by VDC. The final date for payment shall be 30 days after the relevant due date save that if the Consultant invoice is issued late, the final date for payment shall be postponed by the same number of days by which the Consultant’s invoice is late. 7.3 If VDC intends to pay less than the Notified Sum, VDC shall not later than five days before the relevant final date for payment give notice to the Consultant of that intention (a ‘Pay Less Notice’) specifying the amount VDC considers to be due to the Consultant at the date the notice is given and the basis on which that amount has been calculated. Where such notice is given, VDC shall pay the Consultant not less than the amount stated as due in that notice on or before the final date for payment. If no Pay Less Notice is given in respect of any invoice, VDC shall pay the Notified Sum on or before the final date for payment.”
“6. The Fee shall be calculated on a time charge basis as follows, provided always that such charges are intended to be incurred as set out in the Calculation of Service Fee including Resource Schedule (Numbered Document 4) and any material deviations from such schedule shall be subject to clause 8.1 and only payable to the extent that additional fees are agreed under clause 8.1: 6.1 subject to paragraph 6 above, the number of hours worked by the Consultant shall be multiplied by the Hourly Rates, such hours to be worked during Business Hours.” 6.1 subject to paragraph 6 above, the number of hours worked by the Consultant shall be multiplied by the Hourly Rates, such hours to be worked during Business Hours.”
“The Fee shall be paid by instalments as follows: The Consultant shall submit its monthly invoices to VDC in accordance with the Schedule of Valuation Dates (Numbered Document 10). If Valuation Dates are not stated (or if the schedule of Valuation Dates has expired), the Consultant shall invoice the VDC at the end of each month for Services performed during that month.”
“(1) Subject as follows, where a payment is provided for by a construction contract, the payer must pay the notified sum (to the extent not already paid) on or before the final date for payment. … (3) The payer or a specified person may in accordance with this section give to the payee a notice of the payer's intention to pay less than the notified sum. … (5) A notice under subsection (3)— (a) must be given not later than the prescribed period before the final date for payment, and (b) in a case referred to in subsection (2)(b) or (c), may not be given before the notice by reference to which the notified sum is determined. (6) Where a notice is given under subsection (3), subsection (1) applies only in respect of the sum specified pursuant to subsection (4)(a). (7) In subsection (5), ‘prescribed period’ means— (a) such period as the parties may agree, or (b) in the absence of such agreement, the period provided by the Scheme for Construction Contracts.” (a) must be given not later than the prescribed period before the final date for payment, and (b) in a case referred to in subsection (2)(b) or (c), may not be given before the notice by reference to which the notified sum is determined. (a) such period as the parties may agree, or (b) in the absence of such agreement, the period provided by the Scheme for Construction Contracts.”
“(1) Where the parties to a construction contract fail to provide a final date for payment in relation to any sum which becomes due under a construction contract, the provisions of this paragraph shall apply. (2) The final date for the making of any payment of a kind mentioned in paragraphs 2, 5, 6 or 7, shall be 17 days from the date that payment becomes due.”
“The brief description of subcontractor works to be carried out Works are lump sum … RCL will issue activity schedule to KCL, application date end of month … commercial … valuations monthly as per attached payment schedule end of month. Payment terms thirty days from invoice as per attached payment schedule. S/C payment cert must be issued with invoice.”
“That, [counsel for the defendant] submitted and I accept, suggests that while a due date can be fixed by reference to, say, an invoice or a notice, the final date has to be pegged to the due date, and be a set period of time, and not an event or a mechanism. That also makes a degree of sense given that it will be important for the payer to be exactly certain how much time he or she has in which to serve a payless notice, the final date for payment being the date which is critical to that step.”
“… whether a contract term which provides for a final date for payment other than by reference to a specified period between the due date and the final date for payment is compliant with section 110(1)(b).”
“122. Moreover, with respect I am satisfied that the decision in Rochford is correct for the reasons given by Cockerill J in her judgment. Counsel for Lidl did not in their written submissions articulate any basis for contending that the decision was wrong. They did refer me to the reasons given by Edwards-Stuart J in Volkerlaser for saying that it made sense for the contractor to be required to provide a VAT invoice and they did submit that requiring a contractor to submit an invoice is not obviously and inherently objectionable in the same way as are the provisions rendered unenforceable by the amendments to the Act, where the due date for payment depends upon occurrences under a separate contract. Whilst I accept all of these points, they do not in my view sufficiently engage with the key point articulated by Cockerill J in Rochford and repeated by counsel for 3CL in this case, which is that there is a very obvious and compelling difference between the wording used and the plain intent of section 110(1)(b) when compared with that of section 110(1)(a) and, that on a proper analysis, that is because the only discretion intended to be and actually given in the former case is for the parties to agree the length of the time period between the due date for payment and the final date for payment. If it was open to a paying party to include a provision which required the fulfilment of some further condition between the due date for payment and the final date for payment, that would have the effect of driving a coach and horses through the wording and the clear intention of this part of the Act, which is to allow the parties a wide discretion as regards when payments become due under a contract, constrained only by the requirement that it be an adequate mechanism and the specific anti-abuse provisions of section 110(1A) and (1D), but in contrast a much narrower and more circumscribed discretion as regards the final date for payment – only as to the length of the period between the due date and the final date. 123. I can see that the potential for abuse is not present to anything like the same extent where, as in this case and in the Volkerlaser case, the only additional requirement is for the contractor to serve a VAT invoice as well. However, if the way in which Parliament has decided to address this problem is to introduce a blanket prohibition on party autonomy as regards the ascertainment of the final date for payment save as to the length of the period, it is not for the courts to allow parties to agree terms which go beyond that narrow limit simply because they do not appear to have the same potential for abuse.”
“54. Accordingly, I regard it as settled law that, where payment provisions do not comply with s.109 or s.110 of the Act, Part II of the Scheme applies, but only to the extent that such implication is necessary to achieve what is required by the Act. … 66. It follows from the above that the right replacement option (paragraph 7 of Part II of the Scheme) does the least violence to the agreement between the parties. The adoption of the least damaging option also happened in Alstom v Jarvis. Furthermore, the importance of the parties’ original agreement, notwithstanding the provisions of the Act, was stressed by the Court of Appeal in Grove Developments v Balfour Beatty. It seems to me that, when dealing with Part II of the Scheme, these are matters which should be central to the court’s considerations. 67. That links to a wider point about the underlying purpose of the Act. As previously noted, in relation to payment provisions, the purpose of the Act was to provide for certain minimum, mandatory standards so as to achieve certainty and regular cash flow. Save in perhaps exceptional circumstances, it was not designed to delete a workable payment regime which the parties had agreed and replace it with an entirely different payment regime based on a radically changed set of parameters. It seems to me that could only happen where the regime which had been agreed was so deficient that wholesale replacement was the only viable option. That is plainly not this case.”
“4.4 To be clear, I believe that the Defendant’s understanding of how the Consultancy Agreement operates was correct and consistent with the Construction Act. However, if the Defendant is wrong about that, I understand from the Defendant’s solicitors, CMS, that the Defendant seeks to rely on an argument based on estoppel. I further understand from the Defendant’s solicitors that in circumstances where there is to be a substantial dispute of fact, and an issue of estoppel, then those proceedings are generally not considered suitable for Part 8. 4.5 The Defendant would like the opportunity to develop its case on estoppel, and I understand from the Defendant’s solicitors that that would involve pleadings, disclosure, witness evidence from both parties as to their understanding of the operation of the payment provisions, and an opportunity to cross examine those witnesses. 4.6 The Defendant has relied on the common understanding between the parties as to the operation of the payment provisions under the Consultancy Agreement throughout the life of the Project. It is on the basis of that common understanding that the Defendant has paid the Claimant during the Project and issued its Pay Less Notices.”
“If the Claimant submitted its Application for Payment late (i.e., after the Interim Valuation Date), the parties treated the later submission date as the Interim Valuation Date for the purposes of the Payment Schedule, and the recalculated the subsequent dates in the Payment Schedule accordingly (i.e., the Due Date in Column C would be calculated as plus 7 days from the later Application for Payment date, and the Final Date for Payment in Column H would be 30 days from the revised Due Date).”
“As I explained above, I understood that both parties had a Common Understanding that the above wording from Clause 7.2 simply confirms that there was a discrepancy between (i) the Interim Valuation Date in Column B of the Payment Schedule, and (ii) the date the Application for payment is actually submitted, then it is the later date that shall be used to calculate the Final Date for Payment. The Defendant relied on the Common Understanding as to the operation of the payment provisions under the Consultancy Agreement and the Defendant issued its Pay less Notices on that basis.”
“5.2 During the Project, the Claimant usually submitted its Application for Payment late after the Interim Valuation Date (sometimes by weeks). In those circumstances, the parties treated that later Application for Payment as the Interim Valuation Date for the purposes of the Payment Schedule and adjusted the schedule accordingly. 5.3 For example, in respect of Application 5/Valuation 8: 5.3.1 The Interim Valuation Date in the Payment Schedule was listed as29 October 2025 . 5.3.2 The Claimant submitted its Application for Payment on20 November 2025 , 22 days later than the Interim Valuation Date. 5.3.3 The other steps in the Payment Schedule were therefore pushed back, The Due date became27 November 2025 (20 November 2025 plus 7 days) and the Final date for Payment was due by27 December 2025 . Payment was actually made early by the Defendant on22 December 2025 in advance of that date. 5.3.4 I note that the revised date for the Claimant to submit its post valuation invoice was4 December 2025 and the Claimant submitted its invoice on that date. This illustrates the Claimant’s understanding of how the payment provisions operated.” 5.3.1 The Interim Valuation Date in the Payment Schedule was listed as29 October 2025 . 5.3.2 The Claimant submitted its Application for Payment on20 November 2025 , 22 days later than the Interim Valuation Date. 5.3.3 The other steps in the Payment Schedule were therefore pushed back, The Due date became27 November 2025 (20 November 2025 plus 7 days) and the Final date for Payment was due by27 December 2025 . Payment was actually made early by the Defendant on22 December 2025 in advance of that date. 5.3.4 I note that the revised date for the Claimant to submit its post valuation invoice was4 December 2025 and the Claimant submitted its invoice on that date. This illustrates the Claimant’s understanding of how the payment provisions operated.”
“From the cases, one can conclude that the relevant law on estoppel by convention is: (a) An estoppel by convention can arise when parties to a contract act on an assumed state of facts or law. A concluded agreement is not required but a concluded agreement can be a ‘convention’. (b) The assumption must be shared by them or at least it must be an assumption made by one party and acquiesced in by the other. The assumption must be communicated between the parties in question. (c) At least the party claiming the benefit of the convention must have relied upon the common assumption, albeit it will almost invariably [be] the case that both parties will have relied upon it. There is nothing prescriptive in the use of ‘reliance’ in this context: acting upon or being influenced by would do equally well. (d) A key element of an effective estoppel by convention will be unconscionability or unjustness on the part of the person said to be estopped to assert the true legal or factual position. I am not convinced that ‘detrimental reliance’ represents an exhaustive or limiting requirement of estoppel by convention although it will almost invariably be the case that where there is detrimental reliance by the party claiming the benefit of the convention it will be unconscionable and unjust on the other party to seek to go behind the convention. In my view, it is enough that the party claiming benefit of the convention has been materially influenced by the convention; in that context, Goff J at the first instance in the Texas Bank case determined that this is what is needed and Lord Denning talks in these terms. (e) Whilst estoppel cannot be used as a sword as opposed to a shield, analysis is required to ascertain whether it is being used as a sword. In this context, the position of the party claiming the benefit of the estoppel as claimant or indeed as defendant is not determinative or does not even raise some sort of presumption one way or the other. While a party cannot in terms found a cause of action on an estoppel, it may, as a result of being able to rely on an estoppel, succeed on a cause of action on which, without being able to rely on the estoppel, it would necessarily have failed. (f) The estoppel by convention can come to an end and will not apply to future dealings once the common assumption is revealed to be erroneous.” (a) An estoppel by convention can arise when parties to a contract act on an assumed state of facts or law. A concluded agreement is not required but a concluded agreement can be a ‘convention’. (b) The assumption must be shared by them or at least it must be an assumption made by one party and acquiesced in by the other. The assumption must be communicated between the parties in question. (c) At least the party claiming the benefit of the convention must have relied upon the common assumption, albeit it will almost invariably [be] the case that both parties will have relied upon it. There is nothing prescriptive in the use of ‘reliance’ in this context: acting upon or being influenced by would do equally well. (d) A key element of an effective estoppel by convention will be unconscionability or unjustness on the part of the person said to be estopped to assert the true legal or factual position. I am not convinced that ‘detrimental reliance’ represents an exhaustive or limiting requirement of estoppel by convention although it will almost invariably be the case that where there is detrimental reliance by the party claiming the benefit of the convention it will be unconscionable and unjust on the other party to seek to go behind the convention. In my view, it is enough that the party claiming benefit of the convention has been materially influenced by the convention; in that context, Goff J at the first instance in the Texas Bank case determined that this is what is needed and Lord Denning talks in these terms. (e) Whilst estoppel cannot be used as a sword as opposed to a shield, analysis is required to ascertain whether it is being used as a sword. In this context, the position of the party claiming the benefit of the estoppel as claimant or indeed as defendant is not determinative or does not even raise some sort of presumption one way or the other. While a party cannot in terms found a cause of action on an estoppel, it may, as a result of being able to rely on an estoppel, succeed on a cause of action on which, without being able to rely on the estoppel, it would necessarily have failed. (f) The estoppel by convention can come to an end and will not apply to future dealings once the common assumption is revealed to be erroneous.”
“72. I do not accept Mr Hargreaves QC’s submission that this issue would be unsuitable for Part 8 determination. In general, Part 8 proceedings are unsuitable for the trial of an issue of estoppel: ING Bank … per Stanley Burnton LJ at paragraph 77. That is because such issues require careful and precise formulation, and identification of the matters in dispute. In most cases, that is best done through pleadings using the Part 7 procedure. Further, many cases of estoppel involve substantial disputes of fact. However, where the court is concerned with enforcement of the payment and adjudication provisions in the Act, designed to promote cashflow during construction projects through swift interim resolution procedures, it is not sufficient for a party to rely on a vague, unparticularised issue to derail such enforcement. 73. MW has not identified any relevant issue of fact that is in dispute. The history and basis of earlier interim payments is a matter of documentary record, as are the abortive adjudication reference in respect of interim application 31 and the reason for withdrawal. The exchanges between the parties in regard to interim application 32 are likewise a matter of documentary record. It is not suggested by MW that there were oral meetings or agreements that are pertinent to the issue and require oral evidence to be given. The court has before it the relevant material to determine the question.”
“[T]here is no principle that the mere raising of an estoppel by convention argument makes the case unsuitable for Part 8 determination. The question is whether there needs to be a resolution of contested factual evidence.”
“In a number of the authorities which I have cited above the point has been made that each must turn on its own facts. Whilst I respectfully agree with that, it does seem to me that there are a number of clear principles which should always govern the exercise of the court’s discretion when it is considering a stay of execution in adjudication enforcement proceedings. These principles can be set out as follows: a) Adjudication (whether pursuant to the 1996 Act or the consequential amendments to the standard forms of building and engineering contracts) is designed to be a quick and inexpensive method of arriving at a temporary result in a construction dispute. b) In consequence, adjudicators’ decisions are intended to be enforced summarily and the claimant (being the successful party in the adjudication) should not generally be kept out of its money. c) In an application to stay the execution of a summary judgment arising out of an Adjudicator’s decision, the Court must exercise its discretion under Order 47 with considerations a) and b) firmly in mind (see AWG). d) The probable inability of the claimant to repay the judgment sum (awarded by the adjudicator and enforced by way of summary judgment) at the end of the substantive trial, or arbitration hearing, may constitute special circumstances within the meaning of Order 47 rule 1(1)(a) rendering it appropriate to grant a stay (see Herschell). e) If the claimant is in insolvent liquidation, or there is no dispute on the evidence that the claimant is insolvent, then a stay of execution will usually be granted (see Bouygues and Rainford House). f) Even if the evidence of the claimant’s financial position suggested that it is probable that it would be unable to repay the judgment sum when it fell due, that would not usually justify the grant of a stay if: (i) the claimant’s financial position is the same or similar to its financial position at the time that the relevant contract was made (see Herschell); or (ii) The claimant’s financial position is due, either wholly, or in significant part, to the defendant’s failure to pay those sums which were awarded by the adjudicator (see Absolute Rentals).” a) Adjudication (whether pursuant to the 1996 Act or the consequential amendments to the standard forms of building and engineering contracts) is designed to be a quick and inexpensive method of arriving at a temporary result in a construction dispute. b) In consequence, adjudicators’ decisions are intended to be enforced summarily and the claimant (being the successful party in the adjudication) should not generally be kept out of its money. c) In an application to stay the execution of a summary judgment arising out of an Adjudicator’s decision, the Court must exercise its discretion under Order 47 with considerations a) and b) firmly in mind (see AWG). d) The probable inability of the claimant to repay the judgment sum (awarded by the adjudicator and enforced by way of summary judgment) at the end of the substantive trial, or arbitration hearing, may constitute special circumstances within the meaning of Order 47 rule 1(1)(a) rendering it appropriate to grant a stay (see Herschell). e) If the claimant is in insolvent liquidation, or there is no dispute on the evidence that the claimant is insolvent, then a stay of execution will usually be granted (see Bouygues and Rainford House). f) Even if the evidence of the claimant’s financial position suggested that it is probable that it would be unable to repay the judgment sum when it fell due, that would not usually justify the grant of a stay if: (i) the claimant’s financial position is the same or similar to its financial position at the time that the relevant contract was made (see Herschell); or (ii) The claimant’s financial position is due, either wholly, or in significant part, to the defendant’s failure to pay those sums which were awarded by the adjudicator (see Absolute Rentals).”
“At the time of approving the financial statements, the director has a reasonable expectation that the company has adequate resources to continue in operational existence for the foreseeable future. The company is dependent upon the continued support from the ultimate controlling party, Deerns Groep B.V., who have provided written confirmation that they will act in a prudential manner about the decision if and when to claim back any portion of funding provided in order that this action would not preclude other creditors of Deerns UK Ltd to be paid in full.”
“2.4 The Defendant’s approach has therefore put the Claimant under extreme financial pressure in circumstances where the LHR11 Project has been the Claimant’s main revenue. Put simply, the Claimant has been starved of cash flow since December 2025. 2.5 The Claimant has and continues to receive numerous demands for payment from various subcontractors engaged by the Claimant on the LHR11 Project and is under increasing pressure from them. However, the Claimant has not received payment from the Defendant in order to pay any monies which are due down the chain. One subcontractor has now issued a money claim in the Civil National Business Centre against the Claimant. 2.6 Due to heavy reliance on the income that comes from such a large project, the Claimant is also struggling to meet the ongoing operational running costs of the business. 2.7 A hearing in May 2026 and a declaration in the terms sought by the Claimant, including payment of the sum of£910,501.71 plus VAT and interest, will allow the Claimant to pay its Creditors in full (to the extent that monies are properly due) and likely avoid an insolvency process at this time. It is imperative that the Claimant’s financial position is stabilised as soon as possible and thus a hearing beyond May 2026 will create additional risk for both the Claimant in terms of an insolvency process and its Creditors in terms of not being paid in full for its services. There is an increasing risk of insolvency as time passes beyond the end of May with a steep trajectory of risk rising during June 2026, which can become critical at any moment.”