“22.1 The adjudicator must attempt to answer the question referred to him. The question may consist of a number of separate sub-issues. If the adjudicator has endeavoured generally to address those issues in order to answer the question then, whether right or wrong, his decision is enforceable […] 22.2 If the adjudicator fails to address the question referred to him because he has taken an erroneously restrictive view of his jurisdiction (and has, for example, failed even to consider the defence to the claim or some fundamental element of it), then that may make his decision unenforceable, either on grounds of jurisdiction or natural justice. […] 22.3 However, for that result to obtain, the adjudicator's failure must be deliberate. If there has simply been an inadvertent failure to consider one of a number of issues embraced by the single dispute that the adjudicator has to decide, then such a failure will not ordinarily render the decision unenforceable: see Bouygues and Amec v TWUL. […] 22.4 It goes without saying that any such failure must also be material. […] In other words, the error must be shown to have had a potentially significant effect on the overall result of the adjudication: see Keir Regional Ltd v City and General (Holborn) Ltd[2006] EWHC 848 (TCC) . 22.5 A factor which may be relevant to the court's consideration of this topic in any given case is whether or not the claiming party has brought about the adjudicator's error by a misguided attempt to seek a tactical advantage. […]”
“(a) It must first be established that the Adjudicator failed to apply the rules of natural justice; (b) Any breach of the rules must be more than peripheral; they must be material breaches; (c) Breaches of the rules will be material in cases where the adjudicator has failed to bring to the attention of the parties a point or issue which they ought to be given the opportunity to comment upon if it is one which is either decisive or of considerable potential importance to the outcome of the resolution of the dispute and is not peripheral or irrelevant. (d) Whether the issue is decisive or of considerable potential importance or is peripheral or irrelevant obviously involves a question of degree which must be assessed by any judge in a case such as this. (e) It is only if the adjudicator goes off on a frolic of his own, that is wishing to decide a case upon a factual or legal basis which has not been argued or put forward by either side, without giving the parties an opportunity to comment or, where relevant put in further evidence, that the type of breach of the rules of natural justice with which the case of Balfour Beatty Construction Company Ltd -v- The Camden Borough of Lambeth was concerned comes into play . It follows that, if either party has argued a particular point and the other party does not come back on the point, there is no breach of the rules of natural justice in relation thereto.”
‘…we were acting in accordance with what we had been told by a professional architect and Contract Administrator who as far as we could see was discharging his obligations in accordance with the Contract. As in [Woodar], even if we were mistaken in doing so, that mistake would not have constituted a repudiation because it would not have indicated an intention not to comply with the Contract; we reasonably believed in reliance on Mr Griffies’ expert judgment that we were acting wholly consistently with what the Contract required.’
“24. Paragraph 11.8 is denied. The Employer misconstrues the Woodar case as providing an effective ‘get out of jail free card’ in all circumstances where a party terminates a contract in bona fide belief in the legality of his actions, including where he has relied on the advice of a professional, in this case the CA, RSA. However, the essential part of the judgment has been overlooked in assessing whether a repudiatory breach was committed, namely the effect of the termination of the innocent party. By reference to Woodar the effect on Corebuild is to deny it the opportunity to complete the Works and be paid significant amounts of money whilst depriving it of its legitimate expectation of making a profit.”
“26. It follows that if the adjudicator finds that the termination was unlawful then the mere fact of the Employer relying on the advice of the CA will be of no relevance and a finding of repudiatory breach is the only reasonable conclusion.”
“51. The expected effect of a wrongful termination under the terms of the Contract or at common law is that it acts as a wrongful repudiation of the Contract, but the Respondents have submitted that, even if, as I found, they were mistaken as to their rights that alone should not be treated as a wrongful repudiation for reason they say that they relied on the Architect’s expert view that the Claimant was in default and that the Claimant’s explanation as to why it was not in default was manifestly defective. I do not accept that the Respondents relied on the Architect’s expert view because, as explained above, both of the Respondents were very much involved in the administration of the Contract, and in those circumstances it can be expected that the Architect did not send his default notice of22nd June 2018 in the absence of a suggestion from or at least without the approval of the Respondents, and consequently I find that the termination of the Claimant’s employment under the Contract was a wrongful repudiation of the Contract.”
“If the claimant is in insolvent liquidation, or there is no dispute on the evidence that the claimant is insolvent, then a stay of execution will usually be granted.”
“Even if the evidence of the claimant's present financial position suggested that it is probable that it would be unable to repay the judgment sum when it fell due, that would not usually justify the grant of a stay if: (i) the claimant's financial position is the same or similar to its financial position at the time that the relevant contract was made; or (ii) The claimant's financial position is due, either wholly, or in significant part, to the defendant's failure to pay those sums which were awarded by the adjudicator.”