“Termination of the Contract does not affect Staptina’s ongoing obligation to correct Defects. A list of Defects as at the date of this letter is attached as Appendix 2 to this letter. You are fully aware of these Defects and have been requested to return to site on numerous occasions to carry out Defect correction. This includes, without limitation, requests made on;29 February 2016 ,08 March 2016 ,18 March 2016 ,25 March 2016 . If these Defects are not corrected within two (2) weeks of the Termination Date the Defects will be corrected by a third party. Pursuant to Clause 42.1 of the Contract you will be responsible for these third party costs.”
“On the30 March 2016 , your company served a termination certificate pursuant to ‘Reason 5’. As your company, did not terminate for reasons 1, 2, 3 or 4 then there is no entitlement to deduct costs for your company completing the works, see clause 92.2”
“It might assist if I explain that on Friday of last week I requested clarification of the matters that Staptina wishes to refer to adjudication (and reserved AECOM’s position in respect of jurisdiction pending receipt of such clarification). Staptina did not respond to that request and I repeated it today because, understandably, AECOM wishes to know the subject matter of the proposed adjudication before it agrees to a particular timeframe and considers the implications of a ‘stay’ for Christmas.”
“I have now considered the Referral Notice and note in particular paragraphs 6, 14 and 15 and the decision sought at paragraph A, in line with the first paragraph on the second page of the Notice of Adjudication. (I take the view that paragraph B is superfluous and in any event cannot alter the scope of the Notice of Adjudication). On that basis, I understand that the dispute that Staptina wishes to refer is indeed a question of contractual interpretation as Staptina suggests, namely whether, as a matter of principle, following a termination under clause 90.3 for reason 5 the Contractor is entitled to take account of Defects in calculating the amount due under clause 92. (I presume that the capitalisation of the term “Defects” in the Referral Notice is an indication that Staptina is adopting the contractual definition). If I have misunderstood Staptina’s intentions, I should be grateful if [BEA] would confirm the correct position. If not, then I am inclined to agree with him that this matter raises a question of principle that should be capable of disposal on or before22 December 2016 . On that basis, AECOM is happy to agree to your appointment on the basis suggested in your e mail at 12:53 on28 November 2016 .”
“The Referring Party seeks a decision that it is entitled to a declaration that following termination pursuant to Reason 5 of the Sub Contract the Respondent was/is not entitled to make any deductions against the Referring Party’s termination account for alleged Defects not rectified or at all, or such declaration as the Adjudicator deems proper”. 2. Paragraph 14 stated: “Following well-known principles of contractual interpretation, the Referring Party contends that the meaning of these provisions is clear: if the Respondent chooses to terminate under Reason 5 the Referring Party does not, indeed, cannot return to site and the Respondent is not entitled to make any deductions of any kind from the Referring Party.” 3. Paragraph 15 stated: “The Respondent had a choice of which termination Reason to use and it chose Reason 5; if the Respondent wanted to make any deductions from the Referring Party it could have chosen to terminate under Reasons 1 to 4 which, pursuant to clause 92.2. clearly would entitle it to make deductions”. 4. Paragraph A was the first declaration and stated that Staptina sought: “A declaration that following termination pursuant to Reason 5 of the Sub-Contract the Respondent was/is not entitled to make any deductions against the Referring Party’s termination account for alleged Defects not rectified or at all, or such declaration as the Adjudicator deems proper.” 5. Paragraph B stated that Staptina sought: “Such other relief as the Adjudicator deems proper”
“31. All that is referred pursuant to the current Notice is the underlying principle, namely whether or not termination for convenience pursuant to Reason 5 leads to a right in principle for AECOM to make the two relevant deductions from Staptina’s application. 32. However, I am empowered to decide how the sums to be deducted are to be assessed in the event that I find that deductions can be made, rather than simply stating that some form of deduction can be made in principle and no more.”
“58. Clauses 40 to 43 deal with Defects, and provide that the Subcontractor is to correct Defects before Completion. 59. After Completion, the Subcontractor has a time period up to the end of the defect correction period to correct a Defect. It is only if the Subcontractor has not corrected a notified Defect within its defect correction period that the Contractor is to assess the cost of having the Defect corrected by other people and the Subcontractor is obliged to pay this amount. 60. In order to address this issue, I need to consider who is at fault in this instance. Had the termination been for Reasons 2, 3 or 4, Staptina would have been at fault (on the assumption that the termination was valid). It would therefore have been Staptina which had prevented itself from taking advantage of the defects provisions of the subcontract and it would have been a fair and equitable result for Staptina’s account to be reduced by the deduction of a sum for the additional cost of completion of defects. 62. This means that it is AECOM which has prevented Staptina from having the opportunity to correct notified Defects either before Completion (if these would prevent the Contractor, Employer or others doing their work) or during the defect correction period 63. Accordingly, the act of prevention in this instance was AECOM’s rather than Staptina’s. The consequence is that: 63.1. AECOM has entirely lost the right to make any deduction for Defects; or 63.2. Alternatively, its right is confined to a claim for the sum it would have cost Staptina to carry out the relevant rectification works had the termination not taken place. This sum could be negligible if for instance Staptina would have been able to compel its own subcontractors to carry out rectification works. It could be in effect equal to the sum AECOM has or will pay third parties to rectify the relevant Defects. Or it could well be something between the two figures. 64. In my determination, it would be wrong to completely bar AECOM from making a deduction for Defects following determination for convenience, as this would be a windfall for Staptina as the subcontractor. 65. However, any such deduction must be confined to the sum it would have cost Staptina to remedy the relevant Defect either before Completion or during the defect correction period. 66. The relevant sum is a matter for evidence, as is the nature and extent of the actual Defects in the works (if any). Neither of these matters are before me in this adjudication which is solely concerned with issues of principle. 67. Accordingly, I find and declare that AECOM is also entitled in principle to deduct the cost of proven Defects from the sum due to Staptina at termination. This right is however confined to a deduction of the sum (if any) it would have cost Staptina to carry out the relevant rectification works had the termination not taken place.”
“Adjudicator’s decisions will be enforced by the courts, regardless of errors of fact or law. This has been stated many times. Carillion v Devonport Royal Dockyard[2005] EWCA Civ 1358 is the most often quoted appellate authority, including as it does an exhortation (sometimes ignored) that dissatisfied parties should take steps finally to resolve the substantive dispute, rather than waste time and money opposing enforcement. Adjudication is a merely temporary resolution of any dispute.”
“However, over the years both in the law and practice relating to adjudication and arbitration, confusion has often arisen as to what a dispute is. The answer to this is that, to borrow from Mr Justice Jackson (as he then was) in Amec Civil Engineering Ltd v Secretary of State for Transport[2004] EWHC 2339 (TCC) , the circumstances in and by which a dispute may arise are "Protean". It is almost impossible to give a definition which will work in every case as to what a dispute is. It will usually involve a claim or assertion which is expressly or by implication challenged or not accepted. It may be broad or narrow. It may be a one or a multiple issue dispute.”
“If these Defects are not corrected within two (2) weeks of the Termination Date the Defects will be corrected by a third party. Pursuant to Clause 42.1 of the Contract you will be responsible for these third party costs.”
“If the Contractor terminates for Reason 1, 2, 3 or 4, the amount due on termination also includes a deduction of the forecast additional cost to the Contractor of completing the subcontract works.” (italics present in original). 2. Clause 92.3 states: “If the Subcontractor terminates for Reason 1, 6 or 7 or if the Contractor terminates for Reason 5, the amount due on termination also includes 5% of any excess of a forecast of the amount due at Completion had there been no termination over the amount due on termination assessed as for normal payments”
“…clauses 92.2 (fault) and 92.3 (no fault). Under clause 92.2, having terminated for Subcontractor default, in addition to assessing the amount due in the way described above, the Contractor ‘….also includes a deduction of the forecast additional costs to the Contractor of completing the subcontract work.’ (emphasis added)”
“The single sentence in paragraph 21 [of the Response] referred to above was written in support of AECOM’s case as to why it was entitled, in principle, to make deductions in respect of defects. Thus: a) at paragraph 17 of the Response, AECOM submitted as follows: “17. In short, Staptina claims that following a termination for Reason 5 it is entitled to be paid for work not done, either properly or at all. It does so in spite of its failure to correct notified Defects. For the following reasons, Staptina is wrong to do so” b) One of the “following reasons” referred to in paragraph 17 was set out at paragraph 21, as follows: “21. Moreover, clause 42.1 provides that “If the Subcontractor has not corrected a notified Defect within its defect correction period, the Contractor assesses the cost of having the Defect corrected by other people and the Subcontractor pays this amount.”
“17. In short, Staptina claims that following a termination for Reason 5 it is entitled to be paid for work not done, either properly or at all. It does so in spite of its failure to correct notified Defects. For the following reasons, Staptina is wrong to do so” b) One of the “following reasons” referred to in paragraph 17 was set out at paragraph 21, as follows: “21. Moreover, clause 42.1 provides that “If the Subcontractor has not corrected a notified Defect within its defect correction period, the Contractor assesses the cost of having the Defect corrected by other people and the Subcontractor pays this amount.”
“57(a) It must first be established that the Adjudicator failed to apply the rules of natural justice. (b) Any breach of the rules must be more than peripheral; they must be material breaches. (c) Breaches of the rules will be material in cases where the adjudicator has failed to bring to the attention of the parties a point or issue which they ought to be given the opportunity to comment upon if it is one which is either decisive or of considerable potential importance to the outcome of the resolution of the dispute and is not peripheral or irrelevant. (d) Whether the issue is decisive or of considerable potential importance or is peripheral or irrelevant obviously involves a question of degree which must be assessed by any judge in a case such as this. (e) It is only if the adjudicator goes off on a frolic of his own, that is wishing to decide a case upon a factual or legal basis which has not been argued or put forward by either side, without giving the parties an opportunity to comment or, where relevant put in further evidence, that the type of breach of the rules of natural justice with which the case of Balfour Beatty Construction Company Ltd -v- The Camden Borough of Lambeth was concerned comes into play . It follows that, if either party has argued a particular point and the other party does not come back on the point, there is no breach of the rules of natural justice in relation thereto.”