“47.1. … Should any dispute arise between the Parties under or in relation to this Framework Agreement: 47.1.1 where such dispute or difference involves matters which arise under and/or relate to any Works and Services for Projects, such dispute or difference shall be resolved in accordance with the dispute resolution provisions of the relevant Call-off Contract forming part of the Memorandum of Agreement (including, where applicable, the mediation, adjudication and/or litigation provisions of such agreement).”
“Part 1 of theSchedule to the Scheme for Construction Contracts (England and Wales) Regulations 1998 as amended by theScheme for Construction Contracts (England and Wales) Regulations 1998 (Amendment) (England) Regulations 2011”
“3.1. The dispute concerns an error and/or ambiguity and/or inconsistency in the Framework Agreement Schedule Rates; more specifically the interpretation of the HMEP Method of Measurement rules contained in the Framework and the Call off Agreement for the use of Temporary Fencing”