“(i) The date for completion of the Contract, (ii) Scope and validity of Architect’s Instructions issued to date, (iii) The issue and non-withdrawal of the Notice of Non-Completion, and (iv) The sum of Valuation Number Nine …”
“(i) That the Adjudicator make a finding of fact over the original date for Completion of the Contract and determine the revised date in the light of the agreed Extension of Time for completion granted by Mr Robin Hancock FRICS on7 February 2006 , … (iii) That the Adjudicator either order withdrawal of the Certificate of Non-Completion or declare [that] the same [was] invalid and improperly issued, (iv) That the Adjudicator [determine] the true sum properly payable to [the Contractor] under Valuation Number Nine and order such sum to be payable forthwith together with interest …”
“Steel kitchen portakabin@£28.80 per week,£1296 , 45 weeks [and an item of delivery]”
“The adjudicator may, with the consent of all the parties to those disputes, adjudicate at the same time on more than one dispute under the same contract.”
“I am in no doubt that on this aspect of the application Miss Lee’s submission is correct. Any successful challenge to the issue of the certificate of noncompletion in the adjudication would have been, and indeed was, of no monetary consequence to the sum awarded under valuation 9. That is to be contrasted with valuation 10 where, based upon the assumed extension of time, the contractor claimed extra preliminaries.”
“… If the sums claimed under valuation 9 were liable to alter by reference to either the original completion date or the extension, then I can see the force of the argument that the extension issue and the completion date issue was all part and parcel of the financial claim, the single dispute as to what sum is due to be paid under valuation 9. However, on the facts here, that was not the case, and so in truth there were two independent disputes which Mr Hinchcliffe [the adjudicator] entertained.”