“The amount claimed by your client represents 100% of the demolition having been completed and quite simply it can be evidenced even today that this is not the case. The financial claim against Phase 1B is incorrect as a substantial portion of the building is clearly still standing. The Phase 2B building has had the structure above slab demolished but the majority of the works, being the ground floor slabs and foundations, still require to be excavated and crushed, as again can be evidenced even today.”
“3. THE DISPUTE i) The Dispute concerns Payment comprising (a) Valuation of Works and Hire Invoicing and/or damages in lieu (b) Purported Termination and Employment of Others – damages for breach by Topevent. (c) Default Payment In addition Wycombe seeks payment of Interest, Statutory Compensation and Costs.”
“I see that Topevent is still seeking a meeting on site. I don’t yet see any reason to revisit my initial conclusion that this would be either necessary or cost effective. Topevent’s reasoning appears to be to evidence the simplicity of the site and outstanding work to be completed by others. Whilst I can see the nature of any outstanding works may be of some relevance to the claim, I am far from persuaded that it will be of significant help to me to decide the proper value of the works for which Wycombe claims payment.”
“It seems pretty clear that Topevent’s Schedule does indeed seek to reconstitute Topevent’s defence, effectively by way of a claim for the costs of completion. It does not fully reflect the case previously made, nor does it provide any further supporting information for the new value(s) for which it now contends in its Schedule. In the circumstances I therefore have some sympathy for Wycombe’s 18-page Reply to the Scott Schedule plus supporting documents – as opposed to the agreed table requested. Nevertheless if I try to do justice to the parties’ submissions I think I shall require another couple of days for my Decision. I am content that I have sufficient information to reach a Decision and do not ask for anything further in the circumstances, but I do ask the parties to indulge me in an extension of time for my decision to Wednesday 22 April. I apologise for the short notice but should be grateful for your confirmation of your agreement to this as soon as possible.”
“Recital 12. I invited the Parties to indicate whether or not they considered either a site visit or meeting to be required. Topevent requested a meeting on site but I was not persuaded that this was either necessary or cost effective, as explained to the Parties in my letter of16 March 2015 and my email of10 April 2015 . I therefore make this Decision on the basis of the documents only.” ii) As to the cessation of work on site: “114. Both Parties allege unlawful termination of the Contract by the other. WDL [Wycombe] claiming£4,000 in damages for lost profit and Topevent alleging that WDL’s failure to return to site will cost it in the region of£180,000 . I find on the evidence before me that the Parties probably ended the Contract by mutual consent; Topevent, because of the escalating costs, and WDL because it was not being paid. In any event I find neither claim made good on the facts before me.” iii) As to the valuation of Wycombe’s work: “9. The dispute principally concerns the terms of the Contract and the proper valuation of the Works. Neither party has produced any independent expert evidence in relation to the valuation of the Works or otherwise. 10. Topevent has not apparently had specialist advice in relation to these proceedings or the presentation of its case. Much of Topevent’s Response is comprised of bare allegations without supporting evidence. WDL’s case is, in contrast, well supported with documentary and witness evidence and also appears to be reasonably complete … 98. During the following period of August and September 2014 Mr Barber, of Benchmark, got involved with discussions with Mrs Hawes [of Wycombe] as did, towards the end, Mr Duce [of Topevent]. Both Messrs Barber and Duce failed to comprehend the change in contract price from the original February 2013 quotation to the subsequent agreed prices and associated valuations. Nevertheless I find it clear from the above analysis that the jump in price was very largely justified and agreed in accordance with WDL’s subsequent quotations as and when the necessary information became available regarding the existing asbestos on site… 117. WDL’s outstanding invoices amount to£100,203.18 . Whilst it is clear from the correspondence, and its Response, that Topevent accepts some payment is due, at no stage in these discussions, or indeed in these proceedings, has Topevent agreed to pay any part of the sums invoiced. 118. WDL claims£160,415.12 less the sums paid on the basis of a revaluation of the Works and a contractual analysis which assumes the Contract was made on April 2014 and all Works were comprised in one of seven different variations thereafter. I have already found against WDL in relation to the contractual anaysis. 119. It has been very difficult to reconcile the figures claimed and Topevent’s responses. This is no doubt complicated by the fact that WDL’s claim is based upon a contract formed on8 April 2014 . 120. Topevent bases its response on the original CSA. Whilst Topevent’s analysis probably more closely reflects the contractual position, it is not at all clear and almost entirely unsupported by any evidence, as previously noted. 121. I did seek to clarify the position by directing the Parties agree a Scott Schedule. This only served to complicate matters and encouraged Topevent to include a further counterclaim in relation to WDL’s alleged failure to complete the Works (which claim I have dismissed – see above). Whilst I am grateful for Mr Wilson’s attempt to reconcile the figures in his 18 page reply to Topevent’s Scott Schedule, I have given up trying to reconcile the figures and decided to revert to the sums invoiced by Mrs Hawes. 122. This most closely reflects my findings as to the agreement and relevant terms of the Contract. In addition Mrs Hawes’ valuations and invoices were the subject of extensive correspondence and challenge and such challenges were largely unsuccessful. In any event, for what it is worth, I suspect WDL would have obtained a similar result had I followed its contractual analysis. 123. Most of Topevent’s challenges relate to a misunderstanding as to the pricing of the Works. The Contract provided for fixed prices for the original Works and subsequent variations. These were provided and accepted either expressly or by Topevent’s conduct. It is not now open to Topevent to query the reasonableness or otherwise of such claims. 124. In any event, Mrs Hawes engaged at length in relation to the reasonableness of WDL’s claims and Topevent has been almost entirely unsuccessful in persuading me that they were anything other than reasonable… 126. In the light of my findings above I find the invoices generally properly reflect the sums due. 127. I therefore attach two appendices: (a) Appendix A – a summary of all invoices and my findings in relation thereto with brief comments as to the contractual entitlement under which I find they arise. (b) Appendix B – a summary of my interest calculations thereon (see my findings below).”
“A useful if not invariable rule of thumb is that if a disputed claim No 1 cannot be decided without deciding all or part of disputed claim No 2, that establishes such a clear link and points to there being only one dispute.”
“33…if a party does not effectively reserve its position on a given jurisdiction issue, of which it had actual or constructive knowledge, it cannot raise it as an effective objection to a claim for the enforcement of the relevant adjudication decision.”
“I suspect WDL would have obtained a similar result had I followed its contractual analysis”