" Our tender is subject to adequate sup- " plies of material and labour being available as and when required to " carry out the work within the time specified "
" (6) At the time of entering into the said agreement the Claimants " and the Respondents anticipated that there would be available in the " building industry a sufficient labour force and a sufficient supply of " materials to enable the work specified in the agreement to be carried " out substantially within the time stipulated in the agreement. " (7) The conditions in which the work had to be carried out were " different from those anticipated by the Claimants and the Respondents "in that: " (a) At all times there was a serious shortage of skilled labour " in the industry and the Claimants were unable to obtain an " adequate supply of such skilled labour ; " (b) There was difficulty in obtaining adequate supplies of bricks, " timber and plumbers' goods ; " (c) There was an adequate supply of unskilled labour in the " industry but not at all times within the locality of Fareham where " the Claimants were required under the General Conditions of "
" When do you say that the contract came to an end?", and they replied that they were unable to specify any time. I think that this answer was correct and inevitable, but it reveals the inherent weakness of the Appellants' case. 6 The facts in the case of Bush v. Whitehaven are very briefly stated in the report, but I think it is clear that the judgments of the Court of Appeal in that case were based upon the findings of the jury, and in particular the fifth finding. The question put to the jury was: "
" Our tender is subject to adequate sup- " plies of material and labour being available as and when required to " carry out the work within the time specified "
" (6) At the time of entering into the said agreement the Claimants " and the Respondents anticipated that there would be available in the " building industry a sufficient labour force and a sufficient supply of " materials to enable the work specified in the agreement to be carried " out substantially within the time stipulated in the agreement. " (7) The conditions in which the work had to be carried out were " different from those anticipated by the Claimants and the Respondents "in that: " (a) At all times there was a serious shortage of skilled labour " in the industry and the Claimants were unable to obtain an " adequate supply of such skilled labour ; " (b) There was difficulty in obtaining adequate supplies of bricks, " timber and plumbers' goods ; " (c) There was an adequate supply of unskilled labour in the " industry but not at all times within the locality of Fareham where " the Claimants were required under the General Conditions of "
" Were the conditions of the " contract so completely changed, in consequence of the defendant's inability " to hand over the sites of the work as required, as to make the special pro- " visions of the contract inapplicable?", and the jury replied: "
" Whether this result follows from a true construc- " tion of the contract or whether it is necessary to imply a term or whether " again it is more accurate to say that the result follows because the basis " of the contract is overthrown, it is not necessary to decide "
" That seems to me another " way of saying that from the nature of the contract it cannot be supposed " the parties, as reasonable men, intended it to be binding on them under " such altered conditions. Were the altered conditions such that, had they " thought of them, they would have taken their chance of them, or such " that as sensible men they would have said: ' If that happens, of course, "
" The parties did not anticipate fully and completely, " if at all, or provide for what actually happened. It is not possible, to my " mind, to say that, if they had thought of it, they would have said: ' Well, if "
" If, on the other " hand, a consideration of the terms of the contract, in the light of the circum- " stances existing when it was made, shews that they never agreed to be bound " in a fundamentally different situation which has now unexpectedly emerged, " the contract ceases to bind at that point—not because the court in its " discretion thinks it just and reasonable to qualify the terms of the contract, " but because on its true construction it does not apply in that situation "
" In each case a delay or interruption was fundamental " enough to transmute the job the contractor had undertaken into a job of a " different kind, which the contract did not contemplate and to which it "could not apply, although there was nothing in the express language of " either contract to limit its operation in this way "
" A court can " and ought to examine the contract and the circumstances in which it was " made, not of course to vary, but only to explain it, in order to see whether or " not from the nature of it the parties must have made their bargain on the " footing that a particular thing or state of things would continue to exist. "
" In effect most forward contracts can be regarded " as a form of commercial insurance, in which every event is intended to be " at the risk of one party or another."
" No one can tell " how long a spell of commercial depression may last; no suspense can be " more harrying than the vagaries of foreign exchanges, but contracts are " made for the purpose of fixing the incidence of such risks in advance, and " their occurrence only makes it the more necessary to uphold a contract " and not to make them the ground for discharging it."