“We therefore do not agree with your vexatious use of clause 4.2.1 of the main contract. We firmly state that we are not in breach of this clause and would remind you that should you take the course of action you intend under clause 4.1.2, you will be in breach of your obligations under the terms of the contract ... Your vexations actions are repudiatory breach of contract ... We therefore request you to withdraw your notice under clause 4.1.2.”
“the total value of the work notified to us in writing as not being in accordance with the contract is£80,431.22 and we have deducted a proportion of this amount ie£67,055.97 from the gross Valuation.”
“We hereby give you notice on behalf of WVL of its intention to refer to adjudication a dispute that has arisen in connection with its construction contract with you ... The dispute to be referred to adjudication concerns our client’s entitlement to the release and payment of the first half of the retention pursuant to clause 30.4.1.2 of the contract.”
“... any abatement or withholding of amounts otherwise due to the Referring Party can only be made from further sums due and not be retrospective to an amount decided in a previous adjudicator’s decision.”
“(a) enable a party to give a notice at any time of his intention to refer a dispute to adjudication; (b) provide a timetable with the object of securing the appointment of the adjudicator and referral of the dispute to him within 7 days of such notice; (c) require the adjudicator to reach a decision within 28 days of referral … (5) if the contract does not comply with the requirements of subsections (1) to (4), the adjudication provisions of the Scheme for Construction contracts apply.”
“When ... a Party requires a dispute or difference to be referred to adjudication then that Party shall give notice to the other Party of his intention to refer the dispute or difference, briefly identified in the notice, to adjudication. If an Adjudicator is agreed or appointed within 7 days of the notice then the Party giving the notice shall refer the dispute or difference to the Adjudicator (‘the referral’) within 7 days of the notice.”
“In reaching his decision the Adjudicator shall ... set his own procedure”
“require the adjudicator to reach a decision within 28 days of referral or such longer period as is agreed by the parties after the dispute has been referred.”
“Verry’s entitlement to the release and payment of the first half of the retention pursuant to clause 30.4.1.2 and/or 30.4.1.3 of the contract.”
“[NWLCM] asserted that I had no jurisdiction to revisit those items where the previous adjudicator made a decision on the value. I concur with this assertion, except in so far as the items concerned are not based on the same information, in instances where additional or new information has now been provided, I consider I have jurisdiction to consider the items afresh.”
“The effect of the relevant decisions relating to errors by an adjudicator is as follows: 1. The precise question giving rise to the dispute that has been referred to the adjudicator must be identified. 2. If the adjudicator has answered that referred question, even if erroneously or in the wrong way, the resulting decision is both valid and enforceable. If, on the other hand, the adjudicator had answered the wrong question, the resulting decision is a nullity.”