“We agreed that Sprunt consequentially acknowledge and agree our contention that the contractual relationship in respect of phases 2, 3, 4 (now phase B) is Sprunt’s general consultancy agreement is and that the Godwin, Crowndale Ampthill agreement is specific to phases 1 and 1A”
“1…Sprunt was engaged by…Camden to provide ‘Building Consultancy Services for the period 2001-2004/6’… 6. It is provided in the Pricing Document [within the original tender document] that Sprunt will provide the services required for a fee of 5.5% against the total value of the Construction Contract (being over£1,250,000 ). It is noted that Sprunt reduced their fee percentage from 6.659% to 5.5% in or around June 2006 in order to assist Camden being able to appoint Sprunt for the Phase B works within the existing framework arrangements. 28. In consideration of the above Contract Conditions it is evident that: …(v) There is no dispute that [Camden] has instructed Sprunt to carry out and provide the services that are the subject of the Building Consultancy Services Agreement referred to herein… (vii) By agreement of the Parties [Sprunt letter to Camden dated12 June 2006 ] the applicable fee for the Phase B works at Ampthill Square is 5.5%...”
“1. Paragraph 1 is admitted. 6. It is admitted that the Pricing Document referred to in Paragraph 6 stated that Sprunt would provide the services required for the fee of 5.5% against the total value of the Construction Contract (being over£1,250,000 ). It is denied that Sprunt reduced their percentage fee from 6.659% in or around June 2006 in order to assist [Camden] to appoint Sprunt for the Phase B works within the existing framework arrangements. 28…(v) Paragraph 28 (v) is admitted… (vii) It is admitted that the fee rate between the parties referred to in Paragraph 28 (vii) is 5.5%, but this is in accordance with the rate in the Agreement. It is denied that the rates relate to the letter dated12 June 2006 from Sprunt to [Camden]…”
“In and around June 2006 Sprunt were in negotiation with Camden for the provision of services with respect to the works to the Ampthill Square Estate Phase B. Sprunt’s letter dated12 June 2006 evidences Sprunt’s agreement to reduce their fee to 5.5% plus the additional payments as set out in the aforementioned letter. The Adjudicator will note that the letter of12 June 2006 also provided for Camden reimbursing Sprunt for other services not included in the 5.5% fee, which services are being provided and the associated sums had been paid and are therefore not in dispute. Importantly, the further additional costs claimed in this Adjudication arising from the Services to be provided under the [Framework Agreement] are entirely separate to the additional services referred to in the said letter of12 June 2006 .”
“9. The material commission relates to property referred to as Ampthill Square Estate (phase B).The commission in respect of the phase B works at that property was not in writing. The only potentially contractual document identified by the referring party is specific to this commission is a letter dated12 June 2006 …That document does not contain all of the terms of the commission: it simply refers to an agreement to provide the services for a fee of 5.5% which, contrary to the terms of that letter, is in fact the fee set by the framework agreement for a building contract of this value. 10. In the circumstances the parties’ agreement was not in writing for the purposes of section 107 of the [HGCRA].”
“28(2) The referring party refers at paragraph 4 of the referring notice to "the Building Consultancy Services 2001-2004/6 Agreement" or "the Agreement”…[Camden] refers to this agreement between the parties as "the framework agreement"… (3) In addition, pursuant to the framework agreement Camden engaged Sprunt to provide professional services in relation to phase B of works carried out at the Ampthill Estate, in other words in relation to the works required of Apollo under the building contract. This contract, made under the framework agreement in relation to the Ampthill B works, is referred to as "the commission". Notwithstanding the requirements of the framework agreement the commission was not in writing as has been acknowledged by Sprunt in writing. 29. For completeness the adjudicator should also note the following: …(3) Sprunt provided the same professional services in relation to works required at the Ampthill Square estate under phase A (albeit not under the framework agreement) as were required in connection with phase B which is the subject of this adjudication. 30. (The reason why Sprunt’s work for phase B was procured under the framework agreement but provided not under the framework agreement for phase A need not concern the adjudicator…) 32. The adjudicator should also note that there is no issue between the parties but that the services required of Sprunt in relation to Ampthill B were provided pursuant to a commission given under the framework agreement (albeit not in writing). That is apparent from the terms of the referral notice and all prior correspondence…”
“107(1) The provisions of this Part apply only where the construction contract is in writing, and any other agreement between the parties as to any matter is effective for the purposes of this Part only if in writing. The expressions “agreement”, “agree” and “agreed” shall be construed accordingly. (2) There is an agreement in writing— (a) if the agreement is made in writing (whether or not it is signed by the parties), (b) if the agreement is made by exchange of communications in writing, or (c) if the agreement is evidenced in writing. (3) Where parties agree otherwise than in writing by reference to terms which are in writing, they make an agreement in writing. (4) An agreement is evidenced in writing if an agreement made otherwise than in writing is recorded by one of the parties, or by a third party, with the authority of the parties to the agreement. (5) An exchange of written submissions in adjudication proceedings, or in arbitral or legal proceedings in which the existence of an agreement otherwise than in writing is alleged by one party against another party and not denied by the other party in his response constitutes as between those parties an agreement in writing to the effect alleged. (6) References in this Part to anything being written or in writing include its being recorded by any means. 108 (1) A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section. For this purpose “dispute” includes any difference. (2) The contract shall— (a) enable a party to give notice at any time of his intention to refer a dispute to adjudication; (b) provide a timetable with the object of securing the appointment of the adjudicator and referral of the dispute to him within 7 days of such notice; (c) require the adjudicator to reach a decision within 28 days of referral or such longer period as is agreed by the parties after the dispute has been referred; (d) allow the adjudicator to extend the period of 28 days by up to 14 days, with the consent of the party by whom the dispute was referred; (e) impose a duty on the adjudicator to act impartially; and (f) enable the adjudicator to take the initiative in ascertaining the facts and the law. (3) The contract shall provide that the decision of the adjudicator is binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement. The parties may agree to accept the decision of the adjudicator as finally determining the dispute. (4) The contract shall also provide that the adjudicator is not liable for anything done or omitted in the discharge or purported discharge of his functions as adjudicator unless the act or omission is in bad faith, and that any employee or agent of the adjudicator is similarly protected from liability. (5) If the contract does not comply with the requirements of subsections (1) to (4), the adjudication provisions of the Scheme for Construction Contracts apply. 114 (1) The Minister shall by regulations make a scheme (“the Scheme for Construction Contracts”) containing provision about the matters referred to in the preceding provisions of this Part… (4) Where any provisions of the Scheme for Construction Contracts apply by virtue of this Part in default of contractual provision agreed by the parties, they have effect as implied terms of the contract concerned.”
“1. (1) Any party to a construction contract (the “referring party”) may give written notice (the “notice of adjudication”) of his intention to refer any dispute arising under the contract, to adjudication. 2. (1) Following the giving of a notice of adjudication and subject to any agreement between the parties to the dispute as to who shall act as adjudicator— (a) the referring party shall request the person (if any) specified in the contract to act as adjudicator, or (b) if no person is named in the contract or the person named has already indicated that he is unwilling or unable to act, and the contract provides for a specified nominating body to select a person, the referring party shall request the nominating body named in the contract to select a person to act as adjudicator, or (c) where neither paragraph (a) nor (b) above applies, or where the person referred to in (a) has already indicated that he is unwilling or unable to act and (b) does not apply, the referring party shall request an adjudicator nominating body to select a person to act as adjudicator… (3) In this paragraph, and in paragraphs 5 and 6 below, an “adjudicator nominating body” shall mean a body (not being a natural person and not being a party to the dispute) which holds itself out publicly as a body which will select an adjudicator when requested to do so by a referring party… 5. (1) The nominating body referred to in paragraphs 2(1)(b) and 6(1)(b) or the adjudicator nominating body referred to in paragraphs 2(1)(c), 5(2)(b) and 6(1)(c) must communicate the selection of an adjudicator to the referring party within five days of receiving a request to do so. (2) Where the nominating body or the adjudicator nominating body fails to comply with paragraph (1), the referring party may— (a) agree with the other party to the dispute to request a specified person to act as adjudicator, or (b) request any other adjudicator nominating body to select a person to act as adjudicator. (3) The person requested to act as adjudicator in accordance with the provisions of paragraphs (1) or (2) shall indicate whether or not he is willing to act within two days of receiving the request. 6. (1) Where an adjudicator who is named in the contract indicates to the parties that he is unable or unwilling to act, or where he fails to respond in accordance with paragraph 2(2), the referring party may— (a) request another person (if any) specified in the contract to act as adjudicator, or (b) request the nominating body (if any) referred to in the contract to select a person to act as adjudicator, or (c) request any other adjudicator nominating body to select a person to act as adjudicator. (2) The person requested to act in accordance with the provisions of paragraph (1) shall indicate whether or not he is willing to act within two days of receiving the request.”
“If the contract does not comply with the requirements of subsections (1) to (4), the adjudication provisions of the Scheme for Construction Contracts apply”
“If or to the extent that a contract does not contain such provision as is mentioned in subsection (1) or (2), the relevant provisions of the Scheme for Construction Contracts apply”
“(a) C&B Concept v Isobars [2001] CILL 1781 (1st instance);[2002] 1 BLR 93 . The Recorder decided the whole payment provisions fell and were replaced by Scheme. On appeal the Court of Appeal felt it was not necessary to decide whether that point was correct because the appeal could be decided without it, but was content to assume the Recorder was right. (b) Ballast plc v The Burrell Company[2001] BLR 529 – Court of Session. A Scottish case in which an adjudicator decided he was unable to reach a decision. The Court of Session said the decision was a nullity and it was unacceptable for the adjudicator to refuse to decide the dispute. Lord Reid indicated in the course of his judgment that he considered adjudication might be governed in part by the contractual terms and in part by statute since the Scheme may fill gaps where there was non-compliance with s108(1)(2)(4). (c) John Mowlem v Hydratight [2002] 17 Const LJ 358. In this case HHJ Toulmin CMG QC concluded that the clauses 90.1 to 90.4 of Option Y(UK) 2 of the NEC2 standard form did not comply with parts of section 108. The Judge concluded at paragraph 31 of his judgment: 'I have considered whether, if some parts of the subcontract comply with the Act, they can be retained and the Act can be used in substitution for or to fill in those parts of the subcontract which are contrary to the Act. But the words of the Act are clear. Either a party complies in its own terms and conditions with the requirements of sections 108(1) to (4) of the Act or the provisions of the Scheme apply.' (d) Hills Electrical &Mechanical v Dawn Construction Ltd[2004] SLT 477 . In this Scottish case the court was concerned with payment terms. It was held the Scheme only applied to the extent that there were gaps in the express terms (e) Aveat Heating v Jerram Falkus Construction[2007] EWHC 131 . HHJ Havery QC followed the approach of Mowlem, and decided that where the adjudication provisions were non-compliant they were replaced wholesale by the Scheme, and indicated that the contractual provisions must be void. The Judge expressly disapproved the text of Keating 8th edition paragraph 17.014 (all but the first sentence) and approved the footnote to it, namely: "the extent to which the contractual mechanism does not comply with the Act is irrelevant. If it does not comply the whole contractual mechanism is tainted and falls by the wayside to be replaced by the provisions of the Scheme". (f) Banner Holdings v Colchester Borough Council[2010] EWHC 139 (TCC) , per Coulson J at paragraphs 42 and 43, where Coulson J said that there appeared to be a conflict of authorities although it was unnecessary to decide the point before saying "I would offer the tentative view that, at least in relation to the adjudication provisions in s108, the wording of section 108(5) suggests that the whole Scheme replaces the express terms, regardless of how many (or how few) of those express terms fail to comply with the Act. More generally, I do not believe that it should be for the court to have to piece together a compliant set of provisions from two different sources. That would not make for certainty." (g) See also Construction Adjudication (Coulson) paragraphs 3.01-3.10, and 3.97 (the analogy with UCTA).”
“Where non-compliance with the adjudication provisions arises, that is to say non-compliance with section 108 of HGCRA, the position seems to me to be reasonably clear. The words of the section should be taken to mean what they say, namely that if the contract does not comply – in any respect – with the requirements of subsections (1) to (4), the adjudication provisions of the Scheme apply. As we have already seen, the adjudication provisions in the Scheme are those contained in Part I. So if there is any non-compliance, the adjudication provisions in Part I of the Scheme are brought in – lock, stock and barrel.”
“In July 1993, the government appointed Sir Michael Latham to undertake a review of Procurement and Contractual Arrangements in the United Kingdom construction industry. One of the recommendations in his report was that legislation should provide for the speedy resolution of disputes, including disputes as to payment by adjudication, referee or expert. This recommendation resulted inPart II of the Housing Grants, Construction and Regeneration Act 1996 . This provides that every written construction contract has to contain the right to refer disputes to adjudication under a procedure which complies with section 108. If the written construction contract itself contains provisions for such a right, those provisions will apply. If and to the extent that it does not, the adjudication provisions of the Scheme for Construction Contracts apply - see section 108(5). Section 114 provides for the minister to make a Scheme by regulations. Section 114(4) provides that where any provision of the Scheme applies by virtue of this part of the Act in default of contractual provisions agreed by the parties, they have effect as implied terms of the contract concerned.”
“19. On the point of construction of section 107, what has to be evidenced in writing is, literally, the agreement, which means all of it, not part of it. A record of the agreement also suggests a complete agreement, not a partial one. The only exception to the generality of that construction is the instance falling within sub-section 5 where the material or relevant parts alleged and not denied in the written submissions in the adjudication proceedings are sufficient. Unfortunately, I do not think sub-section 5 can so dominate the interpretation of the section as a whole so as to limit what needs to be evidenced in writing simply to the material terms raised in the arbitration. It must be remembered that by virtue of section 107(1) the need for an agreement in writing is the precondition for the application of the other provisions of Part II of the Act, not just the jurisdictional threshold for a reference to adjudication. I say "unfortunately" because, like Auld L.J. whose judgment I have now read in draft, I would regard it as a pity if too much "jurisdictional wrangling" were to limit the opportunities for expeditious adjudication having an interim effect only. No doubt adjudicators will be robust in excluding the trivial from the ambit of the agreement and the matter must be entrusted to their common sense. Here we have a comparatively simple oral agreement about the terms of which there may be very little, if any, dispute...”
“47. The principle of law which I derive from the majority judgments in RJT is this: an agreement is only evidenced in writing for the purposes of section 107, subsections (2), (3) and (4), if all the express terms of that agreement are recorded in writing. It is not sufficient to show that all terms material to the issues under adjudication have been recorded in writing.”