“One has to remember, when looking at issues about the factual matrix, that although reference for that matrix is not limited to cases where the words are clearly ambiguous, the first place where one expects to find the meaning of the words and the intention of the draftsmen is in the words themselves. If they yield a fairly clear conclusion…then one has to pause long before concluding that at that point the draftsman has used words with a meaning do not fit in with the objective he was seeking to attain.”
“ 2. The Highway Works are described as follows; (a) the construction of a signal control junction at the junction of the Link Road with Broom Way [referred to in the documents as the Northern Junction] (b) the construction of the Link Road and; (c) the construction of a roundabout junction on the northern section of the Link Road as the northern access to the Site and a major/minor priority junction on the southern section of the Link Road at the southern access to the Site; (d) the construction of a signal control junction at the junction of the Link Road with Portsmouth Road [referred to in the documents as the Southern Junction].”
“The purchase price for the sale is£29,892,372 . This is to paid in 7 instalments. It is based on a Gross Land Price of£45,830,872 , which equates to£587,500 per net acre (78.01 net acres)… The Purchaser’s costs are to be deducted from the Gross Land Price. These are to be calculated within 6 months of the sale agreement. An estimation has been made of these in Schedule 5 of the Agreement of£15,938,500 to give the purchase price. If the costs are different after 6 months then there will be an adjustment of price. The schedule 5 costs are deliberately low so as to focus everyone’s minds to keeping them low. However I do anticipate them increasing to near the Persimmon’s figures of£19.7m , which would reduce the price by about£3.8m i.e. the purchase price will be approximately£26 million . The majority of the costs will be calculated by either going out to tender to contractors or they will be figures supplied by statutory undertakers providing services and so will be the lowest achievable. The remaining costs will be calculated with the assistance of Quantity Surveyors…. The above summarises the sale contract with Persimmon. I believe that it is a very good deal for RMC and I would recommend progressing. I should be grateful to receive your approval…”
“…. together with and subject to the rights covenants obligations conditions and other matters contained or referred to in the 106 Agreement and in the transfer of each Parcel…..the Purchaser will covenant to observe and perform the covenants obligations conditions and other matters therein contained and will fully and effectively indemnify the Vendors against all actions proceedings damages, claims and expenses which maybe suffered or incurred by the Vendors or their successors entitled in respect of any breach or non-performance or non-observant thereof”
“7A.1. Within 6 months of the date hereof the parties shall endeavour to agree final figures for the Costs (the figures in the table of Costs being provisional estimated figures) and the parties shall have regard to any projected increase in the Costs due to the time period for the incurring of Costs in any such agreement and if such figures are not agreed by the end of such period of 6 months then the determination of the outstanding Costs (any projected increase thereof as above) shall be referred to an Independent Engineer…”
“13.1. The Purchaser agrees with the Vendors to carry out the development in accordance with the Planning Permission and the 106 Agreement subject to the variations agreed with the Vendors (acting reasonably). 13.2. The Purchasers shall keep their Vendors fully informed in connection with its applications for approval by the appropriate authority of any reserved matters required by the Planning Permission or the 106 Agreement.”
“The Vendors shall indemnify the Purchaser from and against all matters actions proceedings damages costs claims expenses and liabilities whatsoever and howsoever arising from the Vendors’ continuing operations at the property as from the date of this agreement.”
“Provision of public utilities for the Development to the Development site boundary at point x as shown on the Plan. Provision of foul and surface water connections (including any pumping stations and balancing facilities) connected to all points on the boundary to the Development west of the Link Road to service the Development the positions to be in accordance with drawings approved by Southern Water. Public Utilities are water, electricity, gas, telecom, cable and service diversions as provided by any statutory undertaking where appropriate”
“We confirm that in accordance with clause 7A of the Agreement the figure of the Costs (as defined in the Agreement but excluding those in relation to the Link Road (as also defined in the Agreement) and the siting of the balancing ponds and the foul pumping station) has been agreed at£19,4000,000 and that for the purposes of clause 7A.6 of the Agreement the Price has been reduced by£3,461,500 provided that a further adjustment shall remain to be agreed or determined pursuant to clause 7A of the Agreement in relation to; i) the siting and specification of the balancing ponds and the foul pumping station; and ii) any re-siting of or amendment to the specification for the Link Road arsing from the grant of technical approval/planning permission for the Link Road”
“During 1999 there were numerous meetings between our two company’s regarding the calculation of abnormal deductions at the Cherque Farm Development. In December 1999 costs as estimated by Persimmon Homes amounted to£19,893,080 . This figure included a contingency of 5%. It is my recollection that as a number of the items costed on the Persimmon Homes schedule were still the subject of negotiation and a number of major items still needed technical approval. It was agreed that the total figure for the costs deductibles to be included in the purchase contract would amount to£15,938,500 . The contract allowed for an adjustment to the deductible costs in relation to the balancing pond, the Link Road and the main pumping station and associated off-site drainage. It has taken a considerable amount of time to gain technical approval of these three major infrastructure items and indeed we are still waiting for full technical approval of the southern section of the Link Road. During the course of 2003 Mark Cooper has been in regular contact with Andrew Tate of Courdrouys, your appointed surveyors. As a result of these discussions, it has been our understanding that Andrew Tate had agreed figures for the additional costs in relation to the balance of the pond and the pumping station and sewers which he was prepared to submit to you for your approval. The agreed settlement figure in relation to these two items was£657,617 and we therefore submitted an invoice to you for the sum of£650,000 on basis that the balance could be settled at a later date when we have reached agreement over the Link Road. I enclose schedules which explain the thought process behind the agreement reached with Andrew Tate. You will note that within the schedules are exclusions which were made following an agreement with Andrew that such items could be dealt with when the final figure for the Link Road is agreed. I understand that you have expressed an interest in agreeing a figure for the Link Road this year. However, I am reluctant to do this as we are still awaiting final technical approval on the southern section and achieving this technical approval could result in considerable and additional costs. Whilst we have not reached agreement with Andrew over the final cost for the Link Road it has been subject to a considerable discussion with him and I enclose a schedule of costings that have been accepted in principal but I must stress do not form the basis of a final settlement….”
“On the question of costs, the final figure for the Link Road cannot be determined until the southern junction has been constructed, but as a ball-part figure the current estimated bill cost is approximately£3.1million . In addition, whilst certain costs in respect of the balancing pond and the pumping station/foul sewer network had been taken into account and paid, these figures do not represent the final costs as was acknowledged by your surveyor. There could be additional costs of approximately£50,000 , in respect of the balancing pond, and of£30,000 in respect of the pumping stations/foul sewer network.”
“The Link Road as defined and set out in the 106 Agreement (for the avoidance of doubt the Link Road between Broom Way (B3385) and Privett Road (B3333)) constructed to a specification which accords with any approval which is required by the Highways Authority.”
“Provision of foul and surface water connections (including any pumping stations and balancing facilities) connected all points on the boundaries to the Development west of the Link Road to service the Development, the positions to be in accordance with the drawings approved by Southern Water...”
“extra over costs for footpaths; maintenance of Heras Fencing (2004 plus); landscaping maintenance (2004 plus); and commuted sum for balancing pond transfer”
“more tankerage removal; electricity usage; water usage; BT usage; and E.O. maintenance to pump”