“In such instances [late handover by ISG] EWNs were not issued by FK, but we relied on the written email exchanges and/or progress reports and/or DABS meeting minutes as providing notice of delays pursuant to clause 9(5).”
“ISG held daily, weekly and monthly progress meetings to review and coordinate the works where it was made clear the requirements of both the preceding and proceeding trades. Dates were agreed which in turn led to works being programmed in with the following trades. FK continually failed to meet the agreed dates and durations and, in an attempt to mitigate further delays, disruption and abortive costs to follow on trades ISG were left with no alternative but to allow follow on trades to proceed when they were left with no other option.”
“In general Part 8 proceedings are wholly unsuitable for the trial of an issue of estoppel. Once such a claim is disputed, save in exceptional cases, the proceedings will cease to comply withCPR r 8.1 (2)(a), since they will cease to be proceedings in which the parties do not seek the court's decision only on questions which are ‘unlikely to involve a substantial dispute of fact’. A disputed claim of estoppel should be carefully pleaded.”
"(i) It is not enough that the common assumption upon which the estoppel is based is merely understood by the parties in the same way. It must be expressly shared between them. (ii) The expression of the common assumption by the party alleged to be estopped must be such that he may properly be said to have assumed some element of responsibility for it, in the sense of conveying to the other party an understanding that he expected the other party to rely on it. (iii) The person alleging the estoppel must in fact have relied upon the common assumption, to a sufficient extent, rather than merely forming his own independent view of the matter. (iv)That reliance must have occurred in connection with some subsequent mutual dealing between the parties. (v) Some detriment must thereby have been suffered by the person alleging the estoppel, or benefit thereby have been conferred upon the person alleged to be estopped, sufficient to make it unjust or unconscionable for the latter to assert the true legal (or factual) position."
“It is well established that if a party to a contract who is entitled to receive performance of an obligation by a stipulated date represents to the other that he is willing to accept performance out of time and the other relies on that representation, he cannot insist on performance by the date originally stipulated. If the representation is made before the time for performance has come, the waiver will operate by way of equitable estoppel. If it is made after the time for performance is past it may also take effect as an election to affirm the contract.”
“To the best of my knowledge and belief, ISG did not and has never claimed (at least up until the date of the Molloy Adjudication), that FK was in breach of clause 9(5) of the subcontract (or any other clause) because of failings/ inadequacies in the EWNs… FK issued over 100 of these notices and [ISG] therefore had ample opportunity to point this out to FK upon receipt if they believed this to be the case. Further I had numerous conversations with [ISG’s] Martin Melges (commercial manager), Paul Jones (commercial director), Martin Fletcher (operations director), Mark Cesnek (managing director) during the course of the works and nobody ever questioned or disputed the practice of notifying of delays or potential delays via EWNs. On that basis, the position on the EWNs that ISG took in the Molloy Adjudication and now in these proceedings is entirely contrived; there was simply no issue with FK using EWNs to notify ISG in a timely manner of delays and potential delays at that time.”