“3 Botes accepts that the Adjudicator’s decision was a valid decision and that the normal practice of the court would be to give summary judgment as the mechanism for enforcing the decision. For the reasons explained below, however, in the particular circumstances of this case, Botes submits that the court ought not to do so at this stage.”
“The adjudication shall be conducted in accordance with the Construction Industry Council’s Model Adjudication Procedure from time to time in force … which are hereby incorporated into this contract.”
“4. The Adjudicator’s decision shall be binding until the dispute is finally determined by legal proceedings, by arbitration … or by agreement. “6. The parties shall implement the Adjudicator’s decision without delay whether or not the dispute is to be referred to legal proceedings or arbitration.”
“108(3) The contract shall provide that the decision of the Adjudicator is binding until the dispute is finally determined by legal proceedings … or by agreement.”
“Where the parties to a construction contract engage in successive adjudications each focused upon the parties’ current rights and remedies, in my view the correct approach is as follows: at the end of each adjudication, absent special circumstances, the losing party must comply with the Adjudicator’s decision. He cannot withhold payment on the grounds of his anticipated recovery in a future adjudication based on different issues. I reach this conclusion both from the express terms of the Act and also from the line of authority referred to earlier in this judgment.”