“Accordingly, on behalf of [the Claimant] we hereby give notice pursuant to clause 9.2 of the Contract of [the Claimant’s] intention to refer, and hereby do refer, the dispute between [the Claimant]and you, the Employer, concerning [the Claimant’s] clause 8.12 Contractors Account dated8 August 2014 which you rejected ‘… in its entirety …’ under cover of PJ English Associates Ltd’s letter dated18 August 2014 . We shall request the Adjudicator to make the following declarations and give the following decisions: 1. A declaration that after taking into account amounts actually and physically previously paid to [the Claimant] under the Contract the amount properly due to [the Claimant] in respect of the account and that shall be paid by you to [the Claimant] on or before6 September 2014 , without deduction of any retention, (or any other sum for that matter), shall be the sum of£397,912.48 or such other sum as the Adjudicator shall decide; 2. A decision that you shall pay [the Claimant] the sum of£397,912.48 being the outstanding sum under the Contract or such other sum as the Adjudicator shall decide; …”
“We hereby give notice of our intention to refer the dispute to Adjudication in relation to the value of the works undertaken by [the Claimant] for works carried out at the above project and entitlement in relation to defects in [the Claimant’s] works. The dispute arose following [the Claimant’s] application for the sum of£397,912.48 on8 August 2014 and its subsequent rejection by us. We, therefore, seek a Decision from the Adjudicator: i. That the Value of the Contract Works (as per Priced Document: Contract Sum Analysis) is in the sum of£340,032.60 or such other sum as the Adjudicator shall decide; ii. …”
“where the Contractor’s employment is terminated under clause 8.9 …, the Contractor shall as soon as reasonably practicable prepare and submit an account …. The account shall set out the amount referred to in clauses 8.12.3.1 to 8.12.3.4 …, namely: 1 the total value of work properly executed at the date of termination of the Contractor’s employment, ascertained in accordance with these Conditions as if the employment had not been terminated, together with any other amounts due to the Contractor under these Conditions; …”
“An adjudicator must resign when the dispute is the same or substantially the same as one which has previously been referred to adjudication, and a decision has been taken in that adjudication.”
“More than one adjudication is permissible, provided a second adjudicator is not asked to decide again that which the first adjudicator has already decided.”
“(c) The extent to which a decision or a dispute is binding will depend on an analysis of the terms, scope and extent of the dispute or difference referred to adjudication and the terms, scope and extent of the decision made by the adjudicator.”