“…a heavy onus lies on a party seeking to make a very late amendment to justify it, as regards his own position, that of the other parties to the litigation, and that of other litigants in other cases before the court.”
“(1) the history as regards the amendment and the explanation as to why it is being made late; (2) the prejudice which will be caused to the applicant if the amendment is refused; (3) the prejudice which will be caused to the resisting party if the amendment is allowed; (4) whether the text of the amendment is satisfactory in terms of clarity and particularity.”
“32. In that succinct passage the judge clearly distinguished between the “very late” amendment cases such as Swain-Mason where the risk to a trial date may mean that the lateness of the application to amend will of itself cause the balance to be heavily loaded against the grant of permission, and “late” amendments in which the consequence of the large scale reformulation of the Particulars of Claim, after the completion of Defences and Part 18 exchanges, will risk undermining work already done on response to the original Particulars of Claim, and causing a duplication of cost and effort. It is evident, for example from paragraph 60 and 61, and elsewhere in the judgment, that it was this aspect of lateness, namely the consequence that, if permitted, the amendments would cause existing work to be wasted and substantial further work and expense incurred, that weighed in the judge’s mind. 33. I consider that the judge was entitled to approach the relevance of lateness in this way. Lateness is not an absolute but a relative concept. As Mr. Randall put it, a tightly focussed, properly explained and fully particularised short amendment in August may not be too late, whereas a lengthy, ill-defined, unfocussed and unexplained amendment proffered in the previous March may be too late. It all depends upon a careful review of the nature of the proposed amendment, the quality of the explanation for its timing, and a fair appreciation of its consequences in terms of work wasted and consequential work to be done.”
“41. In circumstances where the amendment is made late; where no good explanation has been given for so late an amendment; where to permit the amendment might force the defendants to ask for an adjournment but where, even if it does not, it would require a significant amount of extra work and would put the defendants at the disadvantage that I have referred to, as compared to the claimants - a disadvantage entirely down, it seems to me, to the claimants’ decision not to apply to amend before exchange of witness statements - it is, in my judgment, more consistent with the overriding objective to refuse the amendment. This may indeed cause prejudice to the claimants but, if so, they only really have themselves to blame.”
“5. During the past 24 months I have seen water leaks develop in various roof locations. During patch repairs roofing contractors have commented to me that the construction was poor. The number of leaks being notified got to a point where I considered it was necessary to do some further investigations. 6. The roof areas that have suffered leaks during the past 24 months are: [15 separate locations identified]. 7. The most recent roof repairs were to Purple Apartment 38 notified to me by email on the19 September 2014 by the residential managing agents Remus Management and to Unit 17 Nuffield Health Gym above windows in the original façade. … 10. Following exposure of the roof above Unit 17 on20 January 2015 the Central Group Roofing Building Contractor commented to myself and the C & W building surveyor that the existing flashing did not conform to industry standards in respect of overlaps or cutting into the brickwork. He also showed us that the hot melt roof covering had not adhered to the concrete and was lifting in numerous areas, he also commented that the hot melt layer thickness was inadequate. This work was completed in January 2015…”
Showing the 50 most senior of 88.