“15. The Defendants make various prejudicial and highly contentious allegations in relation to Motorola’s conduct in performing and exiting the Lot 2 ESN Contract (paragraphs 2(3), 2(4), 2(9), 2(16), 2(18), 2(31), 20(8), 20(9), 27(4), 36). The allegations should be withdrawn. They are of no legal relevance to the Claim and they have been raised in breach of a settlement agreement relating to a dispute which is outside the scope of the Claim. For completeness and the avoidance of doubt, they are denied. 16. The Defence identifies no basis as to how or why these allegations in relation to the performance and termination of the Lot 2 ESN Contract are of any relevance to the issues in the Claim, which concern the Defendants’ procurement law obligations. 17. The Defendants are in any event precluded by contract from making such allegations in the Claim. A number of disputes arose between Motorola and the First Defendant, relating to dissatisfaction on the part of each party regarding performance and delivery by the other under the Lot 2 ESN Contract (“the Lot 2 Dispute”). Those parties settled their differences about the Lot 2 Dispute and agreed terms for the full and final settlement of the Lot 2 Dispute, including the early termination of the Lot 2 ESN Contract and any payments due to Motorola as a result, and they recorded the terms of settlement, on a binding basis, in the Lot 2 Settlement Agreement and Release dated19 December 2022 (the “Lot 2 Settlement Agreement”). The Lot 2 Settlement Agreement relevantly includes the following terms: a. Clause 6.3 provides […] b. Dispute is defined as: […] c. Reserved Claims is defined as: […] 18. In accordance with the Lot 2 Settlement Agreement, the Claimant makes no allegations against the Defendants in the Claim in relation to issues covered by the Lot 2 Dispute (but reserves the right to do so, and to take any other measures it deems appropriate, if the Defendants pursue their equivalent allegations in breach of the Lot 2 Settlement Agreement). 19. Without prejudice to the general objections set out above, the Claimant denies that the Defendants’ allegations, either overt or oblique, in relation to Motorola and the legality of its performance of and exit from the Lot 2 ESN Contract (paragraphs 2(3), 2(4), 2(9), 2(16), 2(18), 2(31), 20(8), 20(9), 27(4), 36) are justified.”
“(2) The negotiated procedure without prior publication may be used for public works contracts, public supply contracts and public service contracts in any of the following cases: … (c) insofar as is strictly necessary where, for reasons of extreme urgency brought about by events unforeseeable by the contracting authority, the time limits for the open or restricted procedures or competitive procedures with negotiation cannot be complied with. … (4) For the purposes of paragraph (2)(c), the circumstances invoked to justify extreme urgency must not in any event be attributable to the contracting authority.”
“… it may be necessary to consider, as Carr J [in Quah Su-Ling v Goldman Sachs International[2015] EWHC 759 (Comm) ] suggested: “a review of the nature of the proposed amendment, the quality of the explanation for its timing, and a fair appreciation of the consequences in terms of work wasted and consequential work to be done.”
“Unless the particular circumstances make it obviously unnecessary, a formal application to amend is ordinarily required, with a written document setting out the proposed amendments; and, again in general, there is a merits test to overcome in obtaining permission to amend. The pleading must not only be coherent and properly particularised, it must plead allegations which if true would establish a claim that has a real prospect of success. This means that the claim must carry a degree of conviction; and the pleading must be supported by evidence which establishes a factual basis which meets the merits test.”
“(a) The lateness by which an amendment is produced is a relative concept (Hague Plant). An amendment is late if it could have been advanced earlier, or involves the duplication of cost and effort, or if it requires the resisting party to revisit any of the significant steps in the litigation (such as disclosure or the provision of witness statements and expert’s reports) which have been completed by the time of the amendment. (b) An amendment can be regarded as ‘very late’ if permission to amend threatens the trial date (Swain-Mason), even if the application is made some months before the trial is due to start. Parties have a legitimate expectation that trial dates will be met and not adjourned without good reason (Brown). (c) The history of the amendment, together with an explanation for its lateness, is a matter for the amending party and is an important factor in the necessary balancing exercise (Brown; Wani). In essence, there must be a good reason for the delay (Brown). (d) The particularity and/or clarity of the proposed amendment then has to be considered, because different considerations may well apply to amendments which are not tightly-drawn or focused (Swain Mason; Hague Plant; Wani). (e) The prejudice to the resisting parties if the amendments are allowed will incorporate, at one end of the spectrum, the simple fact of being ‘mucked around’ (Worldwide), to the disruption of and additional pressure on their lawyers in the run-up to trial (Bourke), and the duplication of cost and effort (Hague Plant) at the other. If allowing the amendments would necessitate the adjournment of the trial, that may be an overwhelming reason to refuse the amendments (Swain Mason). (f) Prejudice to the amending party if the amendments are not allowed will, obviously, include its inability to advance its amended case, but that is just one factor to be considered (Swain Mason). Moreover, if that prejudice has come about by the amending party’s own conduct, then it is a much less important element of the balancing exercise (Archlane).”
“a) whether to allow an amendment is a matter for the discretion of the court. In exercising that discretion, the overriding objective is of the greatest importance. Applications always involve the court striking a balance between injustice to the applicant if the amendment is refused, and injustice to the opposing party and other litigants in general, if the amendment is permitted; b) where a very late application to amend is made the correct approach is not that the amendments ought, in general, to be allowed so that the real dispute between the parties can be adjudicated upon. Rather, a heavy burden lies on a party seeking a very late amendment to show the strength of the new case and why justice to him, his opponent and other court users requires him to be able to pursue it. The risk to a trial date may mean that the lateness of the application to amend will of itself cause the balance to be loaded heavily against the grant of permission; c) a very late amendment is one made when the trial date has been fixed and where permitting the amendments would cause the trial date to be lost. Parties and the court have a legitimate expectation that trial fixtures will be kept; d) lateness is not an absolute, but a relative concept. It depends on a review of the nature of the proposed amendment, the quality of the explanation for its timing, and a fair appreciation of the consequences in terms of work wasted and consequential work to be done; e) gone are the days when it was sufficient for the amending party to argue that no prejudice had been suffered, save as to costs. In the modern era it is more readily recognised that the payment of costs may not be adequate compensation; f) it is incumbent on a party seeking the indulgence of the court to be allowed to raise a late claim to provide a good explanation for the delay; g) a much stricter view is taken nowadays of non-compliance with the CPR and directions of the Court. The achievement of justice means something different now. Parties can no longer expect indulgence if they fail to comply with their procedural obligations because those obligations not only serve the purpose of ensuring that they conduct the litigation proportionately in order to ensure their own costs are kept within proportionate bounds but also the wider public interest of ensuring that other litigants can obtain justice efficiently and proportionately, and that the courts enable them to do so.”” b. And at [96]: “Very late applications for permission to amend in circumstances where a) there is no good reason for the delay and b) amendment would result in real disruption or prejudice to the parties and/or the Court are unlikely to be allowed, irrespective of the merits of the proposed amendment.”
“CPR 16.4 (1)(a) requires that a particulars of claim must include "a concise statement of the facts on which the claimant relies". Thus, where the particulars of claim contain an allegation of breach of contract and/or negligence, it must be pleaded in such a way as to allow the defendant to know the case that it has to meet. The pleading needs to set out clearly what it is that the defendant failed to do that it should have done, and/or what the defendant did that it should not have done, what would have happened but for those acts or omissions, and the loss that eventuated. Those are 'the facts' relied on in support of the allegation, and are required in order that proper witness statements (and if necessary an expert's report) can be obtained by both sides which address the specific allegations made.”
“The Defendants make various prejudicial and highly contentious allegations in relation to Motorola’s conduct in performing and exiting the Lot 2 ESN Contract (paragraphs 2(3), 2(4), 2(9), 2(16), 2(18), 2(31), 20(8), 20(9), 27(4), 36).”
“(4) At trial, the Defendants will refer to the CMA’s Report, and facts and matters referred to therein, addressing (inter alia): a. The previous arrangements and extensions in respect of the relevant Blue Light Contracts which demonstrate that Defendants’ conduct was reasonable, that there was no relevant “failure” on the part of the Defendants and that the cause (and/or principal and/or material cause) of the need for the previous arrangements and extensions following the original procurement of the ESN was (and is) the conduct, failures and defaults of the Claimant and/or Motorola (and the other appointed ESN providers). b. The economic and technical reasons why a change of contractor would, inter alia, result in incompatibility and/or disproportionate technical difficulties. c. The reasons why a change of contractor would cause significant inconvenience and duplication of costs.”
“Whether the asserted need for extensions to the Blue Light Contracts is attributable to any conduct of [the Claimant] rather than [the Defendants], including (i) the change of the technology to deliver the ESN Lot 2 Contract; (ii) representations by the Claimant to the Defendants as to the timeline of its delivery of the ESN Lot 2 Contract; and (iii) the limited utility of the technology used to deliver the ESN Lot 2 Contract following the Lot 2 Termination Agreement.”