‘16. It has long been the law that a judge is entitled to reverse his decision at any time before his order is drawn up and perfected. … 19. Thus there is jurisdiction to change one’s mind up until the order is drawn up and perfected. UnderCPR r 40.2 (2)(b), an order is now perfected by being sealed by the court. There is no jurisdiction to change one’s mind thereafter unless the court has an express power to vary its own previous order. The proper route of challenge is by appeal. On any view, therefore, in the particular circumstances of this case, the judge did have power to change her mind. The question is whether she should have exercised it. … 27. This court is not bound by the Barrell case or by any of the previous cases to hold that there is any such limitation upon the acknowledged jurisdiction of the judge to revisit his own decision at any time up until his resulting order is perfected. I would agree with Clarke LJ in Stewart v Engel[2000] 1 WLR 2268 , 2282 that his overriding objective must be to deal with the case justly. A relevant factor must be whether any party has acted upon the decision to his detriment, especially in a case where it is expected that they may do so before the order is formally drawn up…..Every case is going to depend upon its particular circumstances.’
“…for the purposes of the Clause 7 analysis, TCS were never going to achieve the R1-D Milestone until between July and September 2018, if one assumes a period of around 9-12 months from Final SIT to Go-Live. (9 months is not an unreasonable planned period: for example, the4 October 2017 Microsoft update plan showed a period of 9 months from the start of Final SIT to Go-Live; the12 December 2017 ; the February 2018 POAP showed a duration for this period 8.5 months; Dr Hunt’s evidence referred to further below suggests 12 months).”
“As at7 September 2017 , but for the following delays, TCS would have, with no other interference, achieved the Go-Live Milestone for R1-D within about 1 year (I will assume a Go-Live Date of7 September 2018 , insofar as it may be relevant). The delays accrued to R1-D at this point were driven by preceding R1-B&B delays and were not matters for which TCS is entitled to relief or damages for the reasons set out in relation to R1-B&B”
“(4) For the period from14 June 2018 to19 September 2018 , TCS has established that the further accrued critical delays (day for day) were caused by ‘AUTHORITY Cause’. This is a period of 3 months and 5 days (98 days).”
‘Doing the best I can by a pro-rata of the days, the claimed sum for the period 13 June 20188 September to19 September 2018 would be a total of£1,640,562 £119,381.20 (constituting£666,7352 £50,279.60 verified costs and£69,101.60 £973,8273 unverified as to amount).’ (2) footnote 2 should be replaced with: ‘The total of the September top line (£125,699 ) multiplied by 12/30 (number of recoverable days 8 September-19 Sept/total number of days in September)’. (3) the first sentence in paragraph 388 should read: ‘In the circumstances, the claim for Period 2 succeeds in the sum of£666,735 £50,279.60 .’ (4) paragraph 397 should read (also correcting a typographical error in relation to a reference to 2018 which should be 2019): ‘On the basis of my analysis of delays as set out above, (a) TCS has established an entitlement to loss and expense for 12 98 days, and (b) but for the wrongful de-scoping, TCS would have delivered R1-D by19 September 2019 . It is usual that claims for prolongation costs are calculated by references to the expenses incurred during the period of relevant critical delay. However, in the circumstances of the present case, I consider that the fairest method of analysis which gives effect to the factual findings above, and takes DBS’s point about the timing of renewals into account, is that I should assess TCS’s entitlement by allowing all non-manpower costs incurred after 12 98 days prior to 19 September 201 8 9, i.e. after 13 June7 September 201 8 9. I therefore allow all of the sums claimed for the months of JulyOctober 2019 to the end, together with 1724/30 of the sum claimed for June September 2019 (£206,733 £173,831 ). That comes to£1,615,841 £1,083,652 plus£117,148.70 £139,064.80 , making£1,732,989.70 £1,222,716.80 .’ (5) footnote 4 should read: ‘£173,831 x 24/30’ (6) Paragraph 821(1) (a) and (b) should read: ‘(a) Manpower costs (R1-D):£666,735.00 £50,279.60 (b) Non-Manpower costs (R1-D):£1,732,989.70 £1,222,716.80 ’ (7) Paragraph 823 should read: ‘The net sum payable by DBS to TCS is therefore£4,808,752.70 £3,682,024.40 (subject to the remaining issue of applicable VAT).’
‘Further, the Claimant claims interest on such sums as are found to be due to it pursuant to theLate Payment of Commercial Debts (Interest) Act 1998 for the unpaid Transaction Charges plus VAT; andsection 35A of the Senior Courts Act 1981 for sums due in damages (and, in the alternative, for the unpaid Transaction Charges plus VAT), for such periods and at such rate as the Court thinks fit.’
“In essence, the court must, taking account of the overriding objective, balance the injustice to the party seeking to amend if it is refused permission, against the need for finality in litigation and the injustice to the other parties and other litigants, if the amendment is permitted. There is a heavy burden on the party seeking a late amendment to justify the lateness of the application and to show the strength of the new case and why justice requires him to be able to pursue it. These principles apply with even greater rigour to an amendment made after the trial and in the course of an appeal.”
‘3.— Qualifying debts. (1) A debt created by virtue of an obligation under a contract to which this Act applies to pay the whole or any part of the contract price is a “qualifying debt” for the purposes of this Act, unless (when created) the whole of the debt is prevented from carrying statutory interest by this section.’
‘16.1 In consideration of the CONTRACTOR carrying out its obligations, including the provision of the Services under this Agreement, the AUTHORITY shall pay the Charges to the CONTRACTOR in accordance with the payment profile and the invoicingprocedure specified in schedule 2-3 (The Charges and Charges Variation Procedure) and schedule 2-4 (Invoicing Procedure).’
‘16.3 The CONTRACTOR shall not suspend the supply of the Services unless the CONTRACTOR is entitled to terminate this Agreement under clause 55.16 for failure to pay undisputed Charges. Interest shall be payable on the late payment of any undisputed Charges properly invoiced in accordance with theLate Payment of Commercial Debts (Interest) Act 1998 .’
‘3.1. The AUTHORITY shall pay all valid invoices submitted by the CONTRACTOR in accordance with the provisions of this Schedule in accordance with the provisions of Clause 16 of this Agreement. 3.2. Invoices shall be due for payment within 30 elapsed days of receipt of a valid invoice. 3.3. In the event of a disputed invoice, the AUTHORITY shall make payment in respect of any undisputed amount in accordance with the provisions of Clause 16 of this Agreement and return the invoice to the CONTRACTOR within ten (10) Working Days of receipt with a covering statement proposing amendments to the invoice and/or the reason for any non-payment. The CONTRACTOR shall respond within ten (10) Working Days of receipt of the returned invoice stating whether or not the CONTRACTOR accepts the AUTHORITY’s proposed amendments. If it does then the CONTRACTOR shall supply with the response a replacement valid invoice. If it does not then the matter shall be dealt with in accordance with the provisions of Clause 27 of this Agreement.’
‘in accordance with the provisions of this Schedule…’
‘This letter therefore constitutes written notice that DBS is in breach of its payment obligations under the Contract and that TCS requires payment of the Overdue Invoices on an urgent basis. In the meantime, TCS reserves all of its rights in respect of the Overdue Invoices, including the right to charge interest on the outstanding amounts in accordance with theLate Payment of Commercial Debts (Interest) Act 1998 pursuant to Clause 16.3 of the Contract.’
‘We refer to your letter of31 July 2018 enclosing an Appendix containing a list of the sums claimed by TCS in respect of invoices dated29 September 2017 to11 April 2018 (the “Disputed Invoices”). In each case, DBS has paid the undisputed amounts. TCS is well aware of the fact that the balance of£3,158,283.95 (the “Outstanding Sum”) is disputed. In response to that letter, please find below a Notice of Dispute in accordance with paragraph 1.2 of Schedule 2-9 of the Agreement dated4 October 2012 ’
‘8(3) The parties may not agree to vary the right to statutory interest in relation to the debt unless either the right to statutory interest as varied or the overall remedy for late payment of the debt is a substantial remedy. (4) Any contract terms are void to the extent that they purport to— (a) confer a contractual right to interest that is not a substantial remedy for late payment of the debt, or (b) vary the right to statutory interest so as to provide for a right to statutory interest that is not a substantial remedy for late payment of the debt, unless the overall remedy for late payment of the debt is a substantial remedy. (5) Subject to this section, the parties are free to agree contract terms which deal with the consequences of late payment of the debt. 9(1) A remedy for the late payment of the debt shall be regarded as a substantial remedy unless— (a) the remedy is insufficient either for the purpose of compensating the supplier for late payment or for deterring late payment; and (b) it would not be fair or reasonable to allow the remedy to be relied on to oust or (as the case may be) to vary the right to statutory interest that would otherwise apply in relation to the debt. (2) In determining whether a remedy is not a substantial remedy, regard shall be had to all the relevant circumstances at the time the terms in question are agreed. (3) In determining whether subsection (1)(b) applies, regard shall be had (without prejudice to the generality of subsection (2)) to the following matters— (a) the benefits of commercial certainty; (b) the strength of the bargaining positions of the parties relative to each other; (c) whether the term was imposed by one party to the detriment of the other (whether by the use of standard terms or otherwise); and (d) whether the supplier received an inducement to agree to the term.’
‘87. When construing this Act it seems to me that there are several factors that should be borne in mind: (1) Interest rates can vary significantly: I do not suppose that any member of Parliament would have foreseen in 1998 that a decade later the bank base rate would have fallen almost to zero. (2) The Act does not automatically substitute the statutory rate for any lower rate of interest for late payment provided in the contract: it does so only if the contractual rate does not afford a “substantial remedy”. (3) The statutory rate could be described as penal in that, when it was set, it produced a rate of interest that was more than double the base rate. (4) Historically, in commercial cases the courts have awarded interest on awards of damages at rates of between 1% and 3% over base, more commonly the former rather than the latter where there is no specific evidence as to the cost to the claimant in question of borrowing money. I accept, of course, that there is a divergence in principle between awarding interest on a sum that was disputed, usually both as to liability and as to amount, and awarding interest on a debt in respect of which there might often be no room for reasonable dispute. Nevertheless, I regard it as legitimate to take note of what the courts have traditionally regarded as the fair remedy for being kept out of one’s money. 88. …Putting it crudely, it seems to me that the imposition of the statutory rate is the penalty that a contracting party pays for failing to provide in its contracts a fair remedy for late payment to suppliers (Eady J referred to counsel’s description of it as “punitive” in Banham Marshalls Services Unlimited v Lincolnshire County Council[2007] EWHC 402 (QB) at [69])’
‘70. ...It is no doubt necessary to have in mind that the mischief to which the statute appears to be primarily directed is that of casual or feckless non-payment. The extent to which the "interests of justice" require that it shall be enforced also upon those who withhold payment because of a bona fide dispute requires careful consideration. 71. Mr Ramsden points to the considerable delay in bringing these proceedings (well over two years after the relevant debts accrued). Mr Lenon, on the other hand, unsurprisingly referred to the six year limitation period. I cannot accept, however, that it is appropriate for a creditor to delay without any particular reason for several years and then to expect to recover interest at the enhanced rate. I have little doubt that "conduct", as used in s.5 of the statute, would embrace conduct prior to or in the course of litigation to recover the debt. 72. Although I am conscious that there is, from a moral or public policy perspective, a distinction to be drawn between those who choose not to pay their outstanding debts and those who refuse to pay because of a genuine legal dispute, it would be wrong for me to approach the issue on the basis that the statutory interest is not to apply at all in cases of bona fide dispute. That would be to detract from the broad discretion which Parliament clearly intended when formulating s.5 in the terms set out above.’
‘In summary as regards the construction of s 4, I would say this: that my construction does not lead to any unfairness. A paying party can withhold payment for sums reasonably in doubt or not yet properly settled. The court will protect him by the use of s 5 remission because the uncertainty to that extent was created by the supplier. What he cannot do is to pay nothing at all and expect to escape the high rates of interest imposed by the 1998 Act on what on any view is due.’
‘But the use of the phrase in the ‘unascertained’ alternative, ‘the sum which the supplier claims is the amount of the debt’ shows that a provisional view of an amount due is within the section. Mr Acton Davis suggested that the alternative was aimed only at cases where you could not do a calculation, such as where the agreement was to pay a reasonable sum—so you could not calculate the exact sum due. That it covers such cases I accept, but I see no reason why it should be so limited. Unless the sum has been determined already in a way binding on the parties, it is likely to depend on calculations which the supplier may have got right, or may have got wrong. In such a case it is not ascertained and what the supplier has to give notice of is what he claims to be due. He may or may not have got it right. In either case he is within the second half of the section.’