“Q1.7 - Could you tell us where the landfill is to tip the products from the tunnel excavation and demolitions? If there is none, could you tell us where there are possible storage areas for later use and the additional cost of this storage? A1.7 - Disposal of material is the Contractor‟s responsibility under the contract and no off-site storage areas have been identified.”
“Our embedded walls do not reach the lower aquifer and there is no risk of contamination of the potable water…OHL guarantees that the potable water will not be contaminated in any way”
“Wherever these Conditions provide for the giving or issuing of consents, determinations, notices and requests, these communications shall be: (a) in writing and delivered by hand (HSE), sent by mail or courier, or transmitted using any of the agreed systems of electronic transmission as stated in the Appendix to tender; and (b) delivered, sent or transmitted to the address of the recipient‟s communications as stated in the Appendix A… Approvals, consents and determinations shall not be unreasonably withheld or delayed…”
“20.1 If the Contractor considers himself to be entitled to any extension of the Time for Completion and/or any additional payment under any Clause of these Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Engineer, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance. If the Contractor fails to give notice of a claim within such period of 28 days, the Time for Completion shall not be extended, the Contractor shall not be entitled to additional payment, and the Employer shall be discharged from all liability in connection with the claim. Otherwise, the following provisions of this Sub-Clause shall apply…”
“Part 1 “Part 1 1. The Works include the design and construction of a new dual carriageway connecting a point south of the existing commercial gate to a new roundabout on Devil‟s Tower Road. The scheme includes a tunnel to carry vehicles under the Gibraltar Airport runway, a subway to carry pedestrians and cyclists under the runway, approach ramps to the tunnel and two footbridges to accommodate a new pedestrian/cyclist route together with all associated mechanical and electrical installations drainage, street lighting, signing and connections to and adjustment of existing infrastructure… 7. The Contractor may adopt or modify the Illustrative Design to suit his own proposals, but must satisfy himself that any such proposals meet the Contract requirements. No guarantee is given as to the accuracy or completeness of the Illustrative Design. The Contractor must accept full ownership of, responsibility for and liability for his design solution whether or not he adopts or varies the Illustrative Design provided. 8. Contractor‟s Documents to be submitted for review in accordance with the Contract shall include, without limitation, the following: a. Approval in Principle (AIP) forms… 9. The Contractor shall submit the Contractor‟s Documents…for review. No data shall be submitted without the relevant Certificate in accordance with the Review and Certification Procedure… A minimum of 21 days, from receipt of hard copies, shall be allowed in the Programme for the Engineer to review each submission. The period given in Volume 3 Part 2 shall be allowed for Approved in Principle submissions… 11. The Engineer shall return one copy of each Certificate to the Contractor endorsed as appropriate and with any relevant comments attached:- a. “Accepted” means that the Contractor may proceed with the relevant work. b. “Accepted with comments” means that minor comments need to be incorporated. The Contractor shall revise the submission and resubmit to the Engineer with the relevant Certificate, but may then proceed with the relevant work as if the certificate were “Accepted”. c. “Returned not accepted” means that the submission fails (to the extent stated) to comply with the Contract. The Contractor shall revise the submission and resubmit to the Engineer with the relevant Certificate. A new review period shall commence on receipt of the resubmission… Part 2 3.1 …An Environmental Statement (ES) has been produced for the project. The ES provides an assessment of the potential effects of the project upon the environment, and recommends mitigation measures that shall be incorporated in to the Works. The Contractor shall use the ES in conjunction with the information provided in Volume 6 to guide the design development and to prepare a site specific Construction Environmental Management Plan (“CEMP”) for the construction activities… 3.5. The history of the site and the investigations carried out to date show that there is the potential for contaminated land and unexploded ordinance. The Contractor shall take precautions to manage these hazards, including without limitation the following measures:- • The Contractor shall conduct detailed contamination testing where required; • Personal Protection Equipment shall be used in areas identified with contamination… • Measures shall be taken to prevent accidental chemical releases, e.g. bunding, spill clean-up methods and covering of spoil; Contaminated material to be removed off-site shall be disposed of to a licensed site… 3.12. The Contractor shall adopt good working practice to limit the risk of pollution to receiving waters, including groundwater (particularly the protected aquifer resource) and marine waters. Where there may be excavation into the groundwater (i.e. the aquifers) the Contractor shall agree monitoring and mitigation to protect potential effects to the resource, as far as practicable, with the Engineer and appropriate regulatory authority. Where dewatering is required the Contractor shall agree a recharge management plan with the Engineer and regulatory authorities (including AquaGib) to protect the groundwater aquifer resource…”
“41.1.1 The Contractor shall be responsible for the testing for classification and assessment of acceptability of earthworks materials prior to excavation and import, leading to his making of decisions regarding methods and manner of excavation, deposition and compaction. 41.1.5 All disposal of material off-site shall be undertaken by the Contractor in accordance with the requirements of the relevant Waste Management Licensing Regulations. 41.2.1 The Contractor shall propose a system to control the flow of groundwater into any excavations made during the course of the Works. Groundwater control is necessary to maintain the stability of excavations…provide a safe working environment… 41.2.3 The site is located upon aquifers which are used for local water supply via pumped wells; the quality and quantity of this water shall not be affected by the groundwater control system. Water collected by a groundwater control system shall be disposed of via sewer or other location as agreed with the Environmental Agency and AquaGib.”
“…OHL propose an additional geotechnical investigation in order to check the [works] done for improving geotechnical data are available for geotechnical design. Although several data are available from geotechnical site investigations, some more information should be obtained in order to ensure the best design for the tunnel. The scope of the new site investigation is filling the gaps in the original investigation by doing some new tests that help us to understand the geotechnical behaviour of the existing soil. Due to the nature of the soil, sampling is really difficult so in situ testing is the best way of obtaining the necessary data… Some new borehole should be done in the tunnel area for assessing the tunnel design. Once [these] borehole had been done, laboratory testing could be realised… As the water level is one of the main points of the work, as [much] information about water level as possible is desired. In all the new boreholes, piezometric pipes at different depths are to be installed in order to study upper and lower water table variation." Paragraph 9.3 relating to "removal of spoil": “The documentation received no information on the waste dumps sign for this construction by the Property. This is important information needed to plan the demolition and to obtain the specific authorisations, in previous arrangements, since it is among the first phases of the construction.”
“The trial shall be split with matters of liability relevant to termination tried first and if necessary, all other matters (including quantum) to be tried subsequently…”
“1 (a) Which of the parties (Claimant or Defendant) lawfully terminated the Contract and on what date did that termination occur? (b) What are the correct principles to be applied to the quantification of each party‟s loss as a consequence of termination? 2. In respect of the question in paragraph 1(b) above, the purpose is to examine the bases each party has pleaded for quantifying its claims for termination and determine which of those bases are correct. It is not intended to include an examination of the actual quantification itself or any matters regarding betterment, mitigation or any other factors that may limit or reduce the quantum of any damages payable.”
“OHL would like to dispose of excavated material in Gibraltar but were informed that there is currently no tip currently open. It was agreed that further discussion with the Chief Technical Officer would be beneficial in order to explore alternatives.”
“…Wastes • Correct separation of wastes • Storage of wastes in prepared places • Transport of wastes to authorised treatment plants by authorised transporters… Dump sites No disposals out of authorised dump sites…” • Correct separation of wastes • Storage of wastes in prepared places • Transport of wastes to authorised treatment plants by authorised transporters… No disposals out of authorised dump sites…”
“If contaminated ground is encountered during construction works, all personnel will use the appropriate personal protective equipment and dust suppression techniques will be employed… Contaminated materials should be removed offsite, stored, and disposed of through a licensed site…”
“For a correct waste management it is necessary to estimate the type and quantity of waste generated by the works Waste Hierarchy principles shall be applied in the waste management. It means that waste management shall be focused on prevention and most of alternative, followed by minimisation, reuse, recycling, energy recovery, and ending with disposal and landfill like the worst option available… Hazardous waste generated on-site will be explored and disposed in order to minimise the impacts of the place on the environment, including appropriate segregation the storage and disposal by an authorised waste transporter… Waste will be stored neatly in appropriate bins or stockpile, with hazardous waste stored in such a manner that storm water run off does not come into contact with the waste. It is expected that most of the material excavated from the tunnel will be clean sands. In this case, the re-use and recycling of these stands in further projects like the regeneration shall be considered. All wastes acceptable to be reused will be kept at Gibraltar, while hazardous waste will be disclosed by authorised transporters to Spain…”
“Should this be of interest to you, kindly revert to me so that we can agree the arrangements so that these fit with your intended method of working.”
“As you reminded me, the risk for ground contamination rests with the Employer...the Employer would have to pay for the disposal of 170,000m3 of contaminated material…a closer examination of the contractor‟s report on the investigation showed it to be fundamentally flawed and we all agreed we had no confidence in the Contractor to do further testing and we decided to do it ourselves. Whilst we do not doubt that there would be some hydrocarbon and lead contamination we are of the view that it is likely to be localised and hopefully near the surface. If we are able to confirm through further testing, we would not only save ourselves the extremely high cost of disposing of 170,000m3 of contaminated material but equally important to the Government, we can use the greater part of that material to replenish Sandy Bay.”
“a) OHL would start extracting spoil in October 2010. They would need to deliver to a stockpile area to sift into clean, contaminated (treatable) and contaminated (untreatable). These would respectively go to Sandy Bay directly, to a cleaning operation or disposed of in Spain. b) [The DoE] had sought quote for cleaning of contaminated rubble which came to between€40 -€50 per tonne all inclusive. c) In order to deal with contaminated tunnel spoil and proceed with processing rubble mound simultaneously, needed to have two separate sites…the cleaning operation would be sited at Catalan Bay car park. d) Cost of treating anticipated spoil from tunnel excavations was£4M -£5M …proposed and agreed that this could be offered to OHL as a contract variation… [Mr Pardo] concerned that this would further complicate the contractual position given the numerous claims already tabled by [OHL]. GOG instruction for [Mr Pardo] and GLRC to approach OHL with a view to agreeing a way forward.”
“Historically, the site has been influenced environmentally by two factors. The first its military use which could be a source of contamination from heavy metals and trace elements and the second as an airport area, where it would be expected to find evidence of the presence of hydrocarbons and their derivatives.”
“A laboratory accredited for soil analysis took samples with the aim of identifying certain organic compounds and heavy metals (both in the soil and in groundwater) these analyses were complemented by a second laboratory confirming the presence of said compounds.”
“Therefore, in accordance with the studies that have been conducted an analysis of the soil, the following was included: 1. The presence of aromatic hydrocarbons, polycyclic aromatic hydrocarbons, and other organic compounds, their physical and chemical properties and their adverse effect on workers‟ health under the envisaged working conditions (excavation and extraction in tunnel), and given the determining factors inherent to this type of work (extreme thermo- hygometric [sic] conditions with high temperature and humidity), implies that the aforementioned compounds would pose a serious risk. 2. Given the presence of heavy metals (chromium, lead, copper, nickel, zinc, mercury, arsenic, etc) both in the soil and in the water, problems associated with bioaccumulation within the human body and the potential disorders and pathologies resulting from exposure to these substances under the above mentioned working conditions; The following courses of actions [sic] are recommended: a) Given that one of the collective protective measure [sic] to be applied is the forced ventilation of the tunnel and given the characteristics of these organic compounds (vapour pressure and volatility, among others), such a measure would pose a serious risk to the workers‟ health, and their work should be allowed to take place under such conditions. b) Given the working methods within the tunnel the inhalation of these heavy metals would pose a severe health risk, it is not advisable to work without first carrying out the corresponding decontamination.”
“In view the values found in the site where works are to be carried out (construction of the tunnel under the airport) and of current legislation on contaminated soils, as far as the CRITERIA FOR IDENTIFYING SITES THAT REQUIRE RISK ASSESSMENT is concerned, it is evident that the maximum values have been exceeded for certain chemical compounds that were analysed. The table below [sic] only shows a number of chemical compounds and only three had been identified on account of their characteristics. Nevertheless, there are other substances that could be considered. Furthermore, section a) of Annex IV, establishing the criteria for identifying sites that require risk assessment, has been complied with in as far as: The site under study shows concentrations of total oil hydrocarbons inexcess of 50 mg/kg and LEAD (Pb) CONCENTRATIONS of 9900mg/kg. In light of the above, a Risk Assessment of the site under study is deemed necessary.”
“The laboratories accredited for soil analysis (GAMASUR Y SERGEYCOANDALUCIA) took some samples for determining certain organic compounds and heavy metals (both in the soil and in underground waters). These analyses were complemented by a second laboratory confirming the presence of set compounds.”
“The presence of pollutants is itself a reason for conducting an assessment of the risk implied by their presence in the soil as set down in the European legislation.” (g) There then followed the “Conclusions and Recommendations” which bore little or no relationship to the earlier ones: “Bearing in mind the geographical characteristics of the place where this investigation is being conducted, the legislation applicable in default is English legislation, which is the transposition of Community regulations, applicable throughout the entire territory of the European Union. At the end of this study, and seeing the analysis of the soil that has been carried out, it is concluded that 1.- From the values found in the soil where the actions are going to be carried out (construction of the tunnel beneath the airport) and that set down by the existing legislation with regard to polluted soils as far as the CRITERIA FOR THE IDENTIFICATION OF SOILS REQUIRING RISK ASSESSMENT are concerned it can be seen that the limit values are exceeded in respect of certain chemical compounds, which are being determined on account of their characteristics, nevertheless, they exist more substances that could be borne in mind. 2.- With the presence of aromatic hydrocarbons, polycyclic aromatic hydrocarbons and other organic compounds, and given their physical and chemical properties and their negative influence on the health of workers under the working conditions they are going to be subject to (excavation extraction in tunnel), when the conditioning factors that are inherent to this type of work (extreme thermo-hygrometric conditions with high temperature and humidity), all this means that the presence of the aforementioned, would imply a serious risk. 3.- Due to the presence of heavy metals (chromium, lead, copper, nickel, zinc, mercury, arsenic, etc.) both in the soil and in the water, and with the problem implied by bioaccumulation in the human body and the disturbances and pathologies that could result from human exposure to these substances under the working conditions stated above. 4.- The soil analysis discovered the presence of PCB. Polychlorobiphenyls all polychlorinated biphenyls (PCBs) are a family of 209 substances…According to the United Nations Environment Programme, polychlorinated biphenyl is considered to be one of the 12 most poisonous pollutants manufactured by human beings. Its use is currently prohibited in almost the entire world. FINDING PCB IN THE WORKPLACE WHERE THE TUNNEL IS BEING CONSTRUCTED IS A VERY WORRYING ASPECT. 5. - Moreover, in the corresponding annexe of the European legislation, the criteria for the identification of soils requiring a Risk Assessment is also met, in that: That the soil under study shows concentrations of total petroleum hydrocarbons greater than 50 mg/kg. The recommended actions are as follows: a) Given that one of the collective protection measures to use is the forced ventilation of the tunnel and bearing in mind the characteristics of these organic compounds (among others, vapour pressure and volatility), this would imply a serious risk for the health of the workers who are going to be carrying out such works, and no labour activity ought to be allowed under such conditions. b) Owing to the way of working in the tunnel, the inhalation of these heavy metals would imply a severe risk for health, and therefore it is not advisable to carry out any labour activity without first undertaking the pertinent decontamination.”
“At no time the established exposure limits are exceeded. However personnel protective equipment must be used in greater Operators safety. Recommended equipments are…”
“Due to the presence of organic compounds, especially considering the presence of Polycyclic Aromatic Hydrocarbons…and heavy metals, the use of convenient PPE (Personal Protection Equipment) adequate for the level of risk exposure required [sic]. It is to be highlighted that the soil is "impregnated" with mutagenic chemical substances (as shown on the Ames mutagenicity test) and which are also ecotoxic.”
“We hereby give you notice to correct under Sub-clause 15.1 that you are failing to carry out a number of obligations under the Contract and that we require you to make good those failures by remedying them with the specified reasonable times”
“Thank you for your letter of31 May 2011 . As you are well aware owing to your failure to avail yourselves of the facility instructed in our letter of22 December 2010 and referred to in our letter of11 January 2011 , the contractor Befesa, who the Employer had arranged to handle the excavated material, has demobilised and the land has been put to other temporary uses. The failure to proceed with the excavation and utilise the excavated material facility is entirely attributable to Contractor-risk reasons as we have made clear in numerous letters. Accordingly the instruction of22 December 2010 is withdrawn and you are instructed to proceed in accordance with the contract and, as per Employer‟s Requirements Volume 3, part 2 at paragraph 3.5, you are required to remove contaminated material off-site for disposal at a licenced site. No doubt you will keep in mind that your claim under clause 4.12 in relation to contamination has been rejected but that you are nevertheless required to maintain full records of costs incurred. You will also recall that the rates for disposal previously quoted by you were far in excess of reasonable market rates. A proportion of the excavated material will be “clean” by which we mean material from areas of the site identified as not contaminated by the site investigation surveys and which upon inspection during excavation appears not to be contaminated. This material will be disposed of by you in Spain unless directed by the Engineer to dispose of it in Gibraltar. The degree of contamination is to be verified by tests in accordance with method statements to be submitted by you and reviewed and accepted by the Engineer. Meanwhile, we will discuss with the Employer the possibility of arranging a disposal facility in Gibraltar of the sort arranged last year. However, you should not assume that it will be possible or that there will be any other change to your strict obligations under the contract in this regard.” change to your strict obligations under the contract in this regard.”
“Accordingly, this letter constitutes notification pursuant to clause 15.1 of the Conditions that you are required to make good your failure to comply with Instruction No. 20. In particular, by commencing the excavation work indicated by Instruction 20 by7 July 2011 and completing the balance of the works set out in that by14 July 2011 .”
“3.1 You elected to attempt to terminate the Contract solely under its terms; you have not attempted to bring the Contract to an end by reason of repudiatory conduct on our part. Accordingly, you are required to comply strictly with the notice provisions in order for your termination pursuant to the Contract to be effective. 3.2 As stated in Section 1 above, your Purported Notice of Termination is not valid and it is ineffective under the terms of the Contract. 3.3 Nevertheless, the contents of your Purported Notice of Termination evince an intention no longer to be bound by the terms of the Contract, which is a repudiatory breach of the Contract. 3.4 We hereby notify you of the following: 3.4.1 We accept your repudiatory breach of the Contract; and 3.4.2 Thus, the Contract is at an end. 3.5 In the alternative to the matters set out in Section 1 at paragraphs 3.1 to 3.4 above, if, which is denied, your Purported Notice of Termination was validly served under the terms of the Contract, your termination under Sub-clause 15.2 of the Contract is wrongful for the reasons set out in Section 2 above and, thus, amounts to a repudiatory breach of the Contract. 3.6 We hereby notify you of the following: 3.6.1 We accept your repudiatory breach of the Contract; and 3.6.2 Thus, the Contract is at an end.”
“Land Contamination There is a low risk of exposing contaminated soils during excavation or accidental spillage of chemicals that may prove a hazard to human health and vegetation. Contaminated material, where found, will be separated and disposed of under license from the appropriate authority to a registered landfill… Waste and Material Resources It is predicted that up to 200,000m³ of waste will arise from the excavation during construction and the majority will be from the new tunnel. Most of the material is unlikely to be contaminated and it will be re-used wherever possible. Even if this material could not be re-used the quantity is unlikely to cause significant effects to landfill void space in the region. Any contaminated material will be either safely capped or removed off site under required regulatory controls to an approved disposal facility… Water Resources Construction activities have the potential to affect water quality through pollution from dust, accidental spills of fuel and suspended solids entering the sea and water beneath the ground. Construction activities may also disturb existing soils and result in new paths for contamination to move between soil and water. Good working practice and principles will be adopted during construction to reduce the risk of pollution from oils, contaminants and other pollutants. These will be agreed with the regulatory authorities.”
“Approximately 200,000m³ of spoil (excavated material) will be produced which will be made up of predominantly sand from excavating the tunnel and made ground from existing hard surfaces. This material will be reused wherever possible within the proposed scheme or for other development within Gibraltar limiting the requirement for waste transfer to Spain. From initial studies there appears to be little contaminated material to be excavated and what material there is will be disposed off to an appropriate waste handling facility or retained on site and appropriately capped to prevent the spread of the contaminant for their uptake by humans and plants and animals…”
“Existing Conditions 7.32 Soil and water samples were tested for a range of contaminants, including for volatile organic compounds (VOCs), total petroleum hydrocarbons (TPHs), polycyclic aromatic hydrocarbons (PAHs) and metals. The results of the contamination testing have been compared against current guidelines for contamination concentrations which affect human health (described in the Land Contamination Chapter: Technical Reports, Volume 2) 7.33 The contamination testing has found that there are low levels of contamination which are, in the main, below threshold levels of significance. There are limited areas of contamination including lead and hydrocarbons, which may give rise to potential risks to human health. Copper and zinc concentrations were identified in shallow ground at two locations at levels that may affect the growth of plants in landscaped areas. 7.34 No methane was present on site and all carbon dioxide concentrations were below 1%. Impact Assessment 7.35 Contaminated ground may give rise to potential health hazards to site workers by contact, inhalation or ingestion during construction. It is considered that there is a potential low to medium temporary significant adverse effect of ground contamination from lead and hydrocarbons. 7.36 Copper and zinc identified in shallow ground at two locations could inhibit plant growth in newly landscaped areas, leading to a potential low to medium significant adverse effect.”
“Existing Conditions 7.88 The assessment of waste and materials has considered the types and approximate volumes of material inputs and waste arising as shown in Table 7.1 and Table 7.2 Table 7-4 Waste Arising Type Quantity (Approximate) Source Demolition Waste 10,000m 3 Rubble/mudstone from demolition of buildings Excavation Materials 180,000m 3 10,000m 3 Sand mainly from tunnel excavation and made ground from existing road/hard standing areas Contaminated Land Total Waste 200,000m 3 Impact Assessment 7.89 The assessment of the effects of material resources required and waste arising from the proposed new road are provided in Table 7-3 and Table 7-4. Table 7-6 Evaluation of Significant effects for Waste Arising Type of Waste Quantity Significance Criteria Significant Demolition Waste 10,000m 3 200,000m 3 Not significant Excavation Materials 180,000m 3 10,000m 3 Not significant Not significant Total Waste Arising 200,000m 3 Low significant 7.90 There are no predicted significant effects from material resources. 7.91 There are no significant effects from individual types of waste arising. However, the estimated total quantity of waste arising from the proposed works just meets the significance criteria and this may therefore lead to a low significant adverse effect.”
“1.3 In Gibraltar, the Environmental Agency (EA) is responsible for protecting the water environment and holds data and information on the water environment. It has regulatory powers to protect watercourses and groundwater, for example, in terms of setting conditions for discharge consents… 3.8 The geology of Gibraltar comprises predominantly… limestone with substantial key systems. This deposit contains important aquifers. Investigations carried out in the 1830s indicated the presence of an aquifer in the Isthmus Sands. The location of the Isthmus Sands aquifer is shown on Figure WR3-1…An unconfined fresh/slightly brackish water aquifer lies about in the Upper Sands… 3.19 Groundwater analysis information or chloride and mercury is available from 1994 to 2007…It is likely that the high salinity results from where several wells…penetrate the and is on the ceiling of these wells to abstract water only from the Upper caps and maybe compromised... 3.22 Groundwater samples were collected from monitoring wells in the area of the new road as part of the site investigation… 3.23 Fifteen groundwater monitoring wells were installed… 3.24 Metals…PAHs, TPHs, phenols and chlorinated hydrocarbons were found above the laboratory detection limits. Experiences of threshold values were recorded for heavy metals, toluene and PAH contaminants only. 3.26 Metals/ metalloids in the groundwater including…lead… were found at concentrations higher than threshold values in groundwater from all areas of site investigation and a range of objects of 2 to 15m bgl. 3.27 Maximum recorded concentrations of…lead…in groundwater modelling exceed threshold values… 3.35 The 16 USEPA priority pollutant PAHs were tested for all groundwater samples. PAHs were detected in all locations, with the highest concentration of total PAH at WS105… Groundwater Quality Summary 3.39 Groundwater has been shown to contain elevated concentrations of the following elements: Metals across the development area… i. Toluene at four times the UK DWS in proposed area for tunnelling… 5.6 The development and construction of the new roads could result in disturbance of contamination in the ground and result in pathways being created along which contamination could migrate to the groundwater aquifer. This would be a risk if piling or deep excavation work to take place below the top level of groundwater. Deep excavation may be required for the tunnel construction down to approximately 10.5 m bgl. 5.7 Dewatering…will be required to enable construction to take place in a „dry‟ environment for the tunnel. The method used with the potential to impact on groundwater levels and quality in the Isthmus Sands aquifer… 5.9 There is much more potential for groundwater flows, levels and quality to be disrupted its dewatering is used to control groundwater during the time of excavations. Depending upon the volume of groundwater that needs to be extracted and the rate of natural recharge to the aquifer, the local groundwater level in the aquifer could reduce if a recharge did not occur quickly enough. 5.10 In addition, the water quality in the Isthmus Sands could be impacted as a result of dewatering. Parking of groundwater could detrimentally affect the natural balance of fresh and saline groundwater and as freshwater is pumped out, saline water intrusion to restore the groundwater level could occur if the freshwater discharge was not rapid enough… 5.12 The concentrations of contaminants above acceptable threshold in the soil sampled and analysed as part of the site investigation are limited. Therefore there is little chance of a major impact on groundwater quality its soil or groundwater pathways are created by finally or excavation. Additional unexpected hotspots of ground contamination that may be encountered during construction could result in impact to groundwater quality if not managed adequately.”
“1.2 An evaluation of the importance of the geology, soil resource and the levels of contamination are presented. An assessment of the potential for the construction of the proposed new road to expose unacceptable levels of contamination is discussed, together with appropriate mitigation resources and any residual significant effects… 2.2 The scoping exercise indicated that there could potentially be contaminated soil present which may have an effect on receptors as a result of the proposed redevelopment. Therefore…a land contamination assessment has been undertaken to determine potential impacts and effects during construction and operation of the proposed redevelopment… 2.16 An initial Tier 1 risk assessment has been used that compares results concentrations of chemicals of concern (COC) in soils against conservative threshold values for those chemicals. This level of assessment assumes there is no significant risk where the thresholds are not exceeded. Tables of Tier 1 soil target values (STVs) are provided in Appendix LC-1… 2.26 completions are based on the findings of the investigation. Fieldwork consisted of discrete sampling across the site where access was available to assess the character and degree of contamination. Conditions of the intervening ground may be different from the tested locations… 3.8 Visual field evidence of contamination [was] observed in soils at BH109 -0.15-0.3m deep in the ground. It is noted however that laboratory testing did not indicate elevated concentrations of contamination at this location. 3.9 No evidence for fuel hydrocarbon odours were noted during the investigation… 3.10 The test results obtained from the investigations are presented in Appendix LC-2. Soil contaminant concentrations exceed STV values relevant to the planned development for a range of contaminants including metals, and hydrocarbons. Each group of soil contaminants is addressed separately below. 3.11 Ten priority metals were tested for all locations. The only contaminant for which the STV was exceeded in a sample analysed was lead (STV 750 mg/kg). All tested in playground at BH 104…and BH moderate concentrations were recorded at 1,500 and 3,000 milligrams/kilograms respectively… 3.20 Hydrocarbons were detected at the majority obligations. However, concentrations were there and the only recorded exceedance of a STV was for the aliphatic range C10-C12 at WS111… 5.3 Further unsuspected contaminated ground could be discovered during intrusive works, potentially exposing ground workers to unacceptable levels of contamination…”
“7.1.2 From a search of historic maps (Appendix 3) and an historic model of Gibraltar at Gibraltar Museum, it is apparent that pre-First World War times the area of the site was occupied by a racecourse which stretched northwards to within around 150 m of the Spanish border… [there was] a rifle range to the east of the racecourse… 7.5.1 The following potentially polluting activities relate to the site‟s current use as an airport: • Fuel storage of aviation kerosene aviation gasoline, usually stored in containers at the oil fuel depot • Diesel fuel storage for use by airport supplying vehicles and boiler fuel - locations of storage area is unknown. 7.5.4 The racecourse was later developed by the British military for use as an airfield…The character of MoD land is such that the nature of activities is often unclear, however the airfield is known to have been extensively bombed used [sic] during World Wars I and II…As such, the possibility of discovering unsuspected contamination and ordnance should be borne in mind… 8.2.1 Groundwater is a sensitive receptor for the site, given that groundwater is pumped from this area of for potable water supply. As such the risks to groundwater, both during and placed construction of the new road require adequate consideration… 8.5.2 A potential for contamination arises from the site current and former uses as an airport and by the MoD…”
“(i) Unforeseen ground conditions. I am aware that the SI has shown more or less consistent ground conditions and at depth this is to be expected. The top layers however are all man-made ground, with most of this having been done during the construction of the airfield and in a hurry. It is possible to find almost anything within this layer. (ii) The whole area of the airfield has the potential to contain some ground contamination, i.e. hydrocarbons. There have been some spills in the not too distant past and there may well have been more that we are not aware of. Likewise, there are existing fuel lines along the line of the road that have been there for some considerable time….”
“…product shall have a proven performance track record in road tunnel environments and be resistant to chemical attack from heavy sulphur laden atmospheres. The passive fire protection shall have a design life of at least 50 years, be non-combustible and fully independently tested…”
“19…a general successionof made ground, over a predominantly loose to medium dense sand with some clay and gravel, over generally "stiff brown clay". In BH104, there was "stiff grey marly clay”
“20.1 If the Contractor considers himself to be entitled to any extension of the Time for Completion…under any Clause of these Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Engineer, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance. If the Contractor fails to give notice of a claim within such period of 28 days, the Time for Completion shall not be extended, the Contractor shall not be entitled to additional payment, and the Employer shall be discharged from all liability in connection with the claim. Otherwise, the following provisions of this Sub-Clause shall apply…”
“The Contractor shall be entitled subject to Sub-Clause 20.1…to an extension of the Time for Completion if and to the extent that the completion for the purposes of Sub-Clause 10.1…is or will be delayed by any of the following causes…” (a). A variation instruction is issued on 1 June to widen a part of the dual carriageway well away from the tunnel area in this case. (b). At the time of the instruction, that part of the carriageway is not on the critical path. (c). Although it is foreseeable that the variation will extend the period reasonably programmed for constructing the dual carriageway, it is not foreseeable that it will delay the work. (d). By the time that the dual carriageway is started in October, it is only then clear that the Works overall will be delayed by the variation. It is only however in November that it can be said that the Works are actually delayed. (e). Notice does not have to be given for the purposes of Clause 20.1 until there actually is delay (November) although the Contractor can give notice with impunity when it reasonably believes that it will be delayed (say, October). (f). The “event or circumstance” described in the first paragraph of Clause 20.1 in the appropriate context can mean either the incident (variation, exceptional weather or one of the other specified grounds for extension) or the delay which results or will inevitably result from the incident in question. The wording in Clause 8.4 is not: “is or will be delayed whichever is the earliest”
“In our opinion the excavation of all rock will entitle us to an extension of time…”
“The adverse weather condition (rain) have [sic] affected the works”, which is clearly nowhere near a notice under Clause 20.1. OHL also relies on a letter dated10 January 2011 to the Engineer which refers to the December rainfall which it says has flooded the site and thus “come into contact with the contaminated ground…and we are unable to discharge this rainfall from site…In our opinion the foregoing will entitle us to an extension of time…”
“…if a detailed semantic and syntactical analysis of a word in a commercial contract is going to lead to a conclusion that flouts common sense, it must be made to yield to business common sense.”
“Termination clauses occasionally allow termination on the ground of “any breach” or “any default”
“In determining the meaning of the language of a commercial contract, and unilateral contractual notices, the law therefore generally favours a commercially sensible construction. The reason for this approach is that a commercial construction is more likely to give effect to the intention of the parties. Words are therefore interpreted in a way in which a reasonable commercial person would construe them. And the standard of the reasonable commercial person is hostile to technical interpretations and undue emphasis on niceties of language…Nowadays one expects a notice to determine a commercial lease to be interpreted not as a “technical document” but in accordance with business common sense…”
“Hard copies of the correspondence that took place between you and the local licensed operators that were appointed before acquiring the services of the Spanish Barge “ARDENZA. I hope that you found the above written statement helpful and that it assists in acquiring a better understanding of our local laws and legislation.”
“9. The Contractor shall submit the Contractor‟s Documents…for review. No data shall be submitted without the relevant Certificate in accordance with the Review and Certification Procedure… 10. The Contractor shall operate a design certification procedure….Certificates shall be signed by both the Contractor and the relevant…Checker as appropriate. Certificates produced under this procedure shall constitute the Contractor‟s Notice required under Clause 5.2 of the Contract”
“…submitting an AIP for a Category 3 Structure, the Contractor shall at the same time submit a proposed Checker for that structure…The Category 3 Checker is subject to the Engineer‟s approval and may be rejected…”
“However: (i) if the recipient gives notice of another address, communications shall thereafter be delivered accordingly; and (ii) if the recipient has not stated otherwise when requesting an approval or consent, it may be sent to the address from which the request was issued.”
“It has been argued by buyers that this is a condition precedent to the seller‟s rights under that clause. I do not accept this argument. Had it been intended as a condition precedent, I should have expected the clause to state the precise time within which the notice was to be served, and to have made plain by express language that unless the notice was served within that time, the sellers would lose their rights under the clause”
“Whether or not that claim was made without delay is a question of fact on which there may be a dispute. If there was a breach by the sellers of this obligation, they may be liable in damages for loss incurred by the buyers in consequence but the contract does not in my opinion provide that cancellation is conditional upon the sellers complying with this obligation”
“Notices permitted or required to be given hereunder shall be in writing and shall be delivered by hand or despatched by registered airmail, facsimile, or cable, shall be deemed given upon receipt thereof, and shall be sent to the parties at the following address…”
“There is no provision for despatch by ordinary, recorded delivery or registered post. It would be quite wrong, in my view, to treat successful service by any of these means, or delivery by hand to the managing director of WorldPro, as having no effect. Regard must be had…to the subject matter and the object to be fulfilled.”
“15…A typical case of an "indispensable condition" is where the contract states that the relevant notice shall be in writing and shall contain particular information. Some clauses may expressly say that "the notice shall only be valid if…”