“In the present case extra work was ordered by Shawton. It is also perfectly clear that Shawton was prepared to and did give DGP substantially more time in which to complete the work. It accepted a series of revised programmes from DGP for the production of drawings. Among these were what have been referred to as the close out programmes issued on22nd November 2000 showing completion dates for S511, S512 and S514 in March, February and April respectively. Further Mr Platt and Mr Shaw in January 2001 also entered into an agreement extending time until the end of March 2001 and agreeing that Shawton should pay for variations claimed by DGP.”
“If the defendant, as he did, led the plaintiff to believe that he would not insist on the stipulation as to time and that if they carried out the work, he would accept it, and they did it, he could not afterwards set up the stipulation as to time against them. Whether it be called waiver or forbearance on his part or an agreed variation or substituted performance does not matter. It is a kind of estoppel. By his conduct he evinced an intention to affect their legal relations. He made in effect a promise not to insist upon his strict legal rights. That promise was intended to be acted upon and was in fact acted upon. He cannot afterwards go back on it.”
“These passages are in my judgment inconsistent with the view that a reasonable time is to be measured by the original contractual period as extended by the time it might require to carry out the variations. The approach in these passages is that when a person ordering the work continues to seek performance of the contract after the agreed delivery date has passed, reasonable notice must be given if the contract is to be subsequently terminated for delay. Reasonable notice in these circumstances is clearly different from the originally agreed period although the original period is a factor which may be taken into account when deciding what is a reasonable period or a reasonable notice. It is however not the only factor. Likewise it is clear that the time it actually takes to carry out the work is not determinative. It was submitted that the fact that the experts had agreed what was an appropriate extension of time together with the originally agreed period was a fair indication of what should be regarded as a reasonable time for completion of the work, but that is in effect to treat the originally agreed period as being a reasonable period, notwithstanding that that period was agreed to under a misapprehension by DGP of what was involved. It should also be borne in mind that Shawton itself contracted with KAT on the same basis. KAT however never seems to have suggested that Shawton was in breach of contract in not completing all its works by the original dates.”
“Shawton by instructing a variation has in my judgment indicated that it will accept performance of the whole contract as varied within a reasonable time from the giving of the instruction and the consequence is that Shawton cannot in my judgment continue to hold DGP to its previous time obligations.”
“We regret that in the event that you do not agree to carry out your contractual obligations we will place the matter in the hands of our solicitors with the view to considering options which may [include] determining the contract and obtaining completion by an alternative supplier. In the event this proves necessary we shall seek redress for all additional costs incurred, both in the process and resulting from engaging a third party to complete the works originally contracted to you.”
“In principle it is in my judgment open to a party to a contract when the other party is in breach of its time obligations to ask the party in breach to state when he will complete the contract and if he makes clear that the contract will be liable to be terminated if the party in breach fails to adhere to the time by which he states he will complete the contract, then that is in law capable of making time of the essence in respect of the time which is given by the contract breaker. Mr Platt’s evidence in cross-examination does show in my judgment that DGP must have realised when it provided the completion dates for the four specified contracts on 23rd November and provided the first set of close out programmes that it was at risk of being dismissed from the contracts if it did not adhere to those dates and programmes.”
“It is difficult to see how Shawton can really have thought that DGP was in breach of its obligation to complete the work within a reasonable time because it was actively pursuing in conjunction with DGP a claim that it was entitled to an additional payment from KAT because of all the extra work which DGP had said it had had to do because of the poor quality of the DPDs. Mr Walker’s letter to KAT dated 8 November to which I have already referred clearly seeks additional payment on the basis that there had been significant variations. All that actually occurred in my judgment is that KAT were now asking Shawton for the work to be completed as soon as possible. Mr Walker’s letter dated 7 November to DGP significantly in my view does not assert that DGP was already in breach of its obligations and it is difficult to see how Mr Walker could have done so when he states explicitly that KAT had allowed Shawton an extension of time. Any extension of time allowed by KAT to Shawton would in principle allow time for both design and manufacturing and Shawton could hardly say that if KAT had allowed it extra time DGP should not also be allowed extra time for the design element when their respective obligations would appear to have been the same, namely to complete the work within a reasonable time as a result of the variations which had occurred.”
“Further to our meeting today at your office, I confirm as agreed that both companies will proceed with the KAT contract on the basis of our letter dated21st December 2000 . As discussed, I will personally be involved in preparing a claim for both parties in an attempt to recover monies from KAT to recover costs incurred by us. Please find enclosed a cheque for£20,782.27 for payment as agreed today.”
“Having seen and heard Mr Shaw give this evidence, and although in many respects I consider that he was an unsatisfactory witness, I am satisfied and find that what he agreed with Mr Platt was that DGP would try to complete the drawings by the end of March and by the end of March was meant 31 March. Mr Platt did not say that DGP would supply all the drawings by the end of March and that is consistent with later programmes being submitted showing later dates.”
“It is correct that DGP did not keep to the programmes it submitted but there is a singular lack of evidence that KAT had been pressing Shawton for the completion of the work before KAT began pressing in October 2000 for the work to be completed. In the event that urgency does not seem to have lasted for long as doubts about the box encapsulation project were being mentioned by Mr Clarke and Mr Ley at the end of November. Mr Walker’s evidence was that KAT were not pressing (day 5 p.104). At no time until after DGP had been dismissed did KAT threaten to terminate Shawton’s contract and that was only because Shawton had failed to engage another contractor to replace DGP.”
“Even if I were wrong in finding that DGP had not been proved to be in breach of its obligation to complete the drawing work within a reasonable time, Shawton would not in my judgment have been entitled to terminate the contract on26th March 2001 on the grounds of delay. Although the contract had been delayed, any delay up to 26th March was not such as to deprive Shawton of substantially the whole benefit to which it was entitled under the contract. ”
“… that little credence may be put upon what is said in letters written by him or under his name on behalf of Shawton and that he is prepared to write things which he knows to be untrue or in whose truth he has no genuine belief if he thinks it is to be to the advantage of Shawton. His oral evidence likewise must be approached with caution when he is seeking to advance Shawton’s interests. The letter of termination dated26th March 2001 is in a similar category in my judgment. … I have no doubt but that he had considerable input into that letter and he certainly approved its content. It is not correct in my view as stated in the first paragraph that DGP’s “continual and repeated failures” had placed Shawton “in severe difficulties” with KAT. Up to November 2000 KAT had extended time for Shawton’s work including the design element and indeed there is some evidence in the correspondence that Shawton may also have been at fault itself on the manufacturing side. There is however no evidence to show that KAT were pressing during the first three months of 2001 or that Shawton was being criticised for any delays which were then occurring.”
“Shawton on his own admission had cash flow problems at this time and KAT on1 March 2001 had rejected the claim for additional payment which Mr English had prepared. The effect of what had been agreed with DGP on 8 January was to commit Shawton to make further payments to DGP and I consider that the probability is that Mr Shaw had come to regret what he had agreed and wished to find a way in which he could avoid Shawton having to make any further payments to DGP.”
“… the condition of a reasonable time has been frequently interpreted; and has invariably been held to mean that the party upon whom it is incumbent duly fulfils his obligation, notwithstanding protracted delay, so long as such delay is attributable to causes beyond his control and he has neither acted negligibly nor unreasonably.”