“47. In this context, when one looks at the evidence as a whole and objectively, it is clear that although the parties signed the agreement with the FIDIC terms incorporated, the management of the contract demonstrated some flexibility in its actual day to day operation. Hence, the approach of, after the fact, returning to the strict literalist language of the contract, without examining the evidence of how the contract was in fact performed, leads to an unfair outcome and not one that can be justified on the evidence. 48. There was strong evidence that the changes made to the project as detailed by UBC’s witnesses were in fact variations. The pipes were being laid on the roadway and not the verge. The excavated material was being removed instead of being reused. Significantly larger amounts of new material had to be sourced and brought in. Mr Thomas explained the change in quantities which resulted from this. Night work was being done instead of solely day work due to congestion and complaints of the residents. Most importantly, WASA’s site engineer approved these as variations. 49. Even if the contract provided for one method in the execution of the contract, the contract itself allowed for variations to be made. Parties are entitled to mutually agree a different method of performance. This is clearly what took place here based on the evidence before the judge. This is different from what clause 3 of the general FIDIC contract provided for, that the engineer had no authority to amend the contract. This was not an amendment of the contract. Variations and adjustments were contemplated by the contract. 50. Further, while the contract may have provided for notice in writing for changes, it is clear that WASA, through the site engineer, waived these requirements as explained by the witnesses. Discussions occurred on an on-going basis on site and adjustments were made. These were detailed by the witnesses in their evidence. As Mr Paul explained, his priority was in getting the project done. There was also clear evidence that WASA was given notice of the change of the prices for materials from the bill of quantities and that no objection was taken to those changes and in fact approval was given by Mr Paul. It would be fundamentally unfair in the circumstances after the engineer had approved the works being done and agreed they were variations for which additional payments were to be made later on, for WASA to seek, after the fact, to dispute that these additional payments did not arise… … 58. Mr Paul’s evidence was to the effect as well that the additional works were approved with the payments to be made later. The 28-day period for submission of claims was therefore waived. It is clear from the evidence that the FIDIC terms were varied and waived in several instances based on the stated intention to have the project proceed as quickly as possible. In particular, provisions for notices in writing and for specific periods for submissions were put aside. Decisions were taken onsite after discussions and instructions were given. Neither WASA nor UBC insisted on the procedures for notice of variations or the time frame for claims being complied with. The evidence was that instructions were given by the site engineer Mr Paul who was aware of the terms of the contract. The manner in which the contract was terminated also informed the submission of the claim at the time and in the manner it was done.”
“The Contractor shall be deemed to: (a) have satisfied himself as to the correctness and sufficiency of the Accepted Contract Amount, and (b) have based the Accepted Contract Amount on the data, interpretations, necessary information, inspections, examinations and satisfaction as to all relevant matters referred to in Sub-Clause 4.10 [Site Data] and any further data relevant to the Contractor’s design. Unless otherwise stated in the Contract, the Accepted Contract Amount covers all the Contractor’s obligations under the Contract (including those under Provisional Sums, if any) and all things necessary for the proper design, execution and completion of the Works and the remedying of any defects.”
“The Contractor shall be responsible for preparing and taking full responsibility for his own preliminary design and final design.” (ii) Sub-clause 4.10, which provided: “Site Data (General Conditions of Contract) The Contractor shall be deemed to have inspected and examined the Site, its surroundings, and other available information, and to have satisfied himself before submitting the Tender, as to: (a) The form and nature of the Site, including the sub-surface conditions through borehole data, (b) The hydrological and climatic conditions including environmental aspects, (c) The extent and nature of the work and materials necessary for the execution and completion of the works, and the remedying of any defects, and (d) The Contractor’s requirements for access, accommodation facilities, personnel, power transport, water and other services (e) The laws, procedures and labour practices of the Country The Contractor shall be deemed to have obtained all necessary information as to risks, contingencies, and all other circumstances, which may influence or affect the Tender. The Contractor shall carry out, at his own cost, any additional investigations and shall obtain during and/or after the Tender price, any further information which the Contractor considers to be necessary for the proper design and execution of the works or which the Contractor considers may influence or affect his tender.” (iii) Sub-clause 5.1, which provided: “General Obligations The Contractor shall carry out, and be responsible for, the design of the Works. Design shall be prepared by qualified designers who are professional engineers registered as such in their home countries, and eligible for registration in Trinidad and Tobago and who comply with criteria (if any) stated in the Employer’s Requirements… The Contractor holds himself, his designers, and design sub-contractors as having the experience and capability necessary for the design. The Contractor undertake that designers (whether or not part of a consortium) shall be available to attend discussions with the Employer’s Representative at all reasonable times during the contract period and extending to the defects liability period. No action or inaction on the part of the Employer and/or the Employer’s Representative will transfer the responsibility for the design, construction and execution of the works to the Employer or the Employer’s Representative”
“…Limited ground investigation work has been carried out and the available information is issued from these documents and shall not form part of the Contract. The Contractor is responsible for drawing his own conclusions from the information provided in so far as they may affect the works and for the determination of any existing services. The Contractor shall be deemed to have satisfied himself that he has sufficient information on the nature of the ground on which to base his rates and prices. The Contractor shall verify by trial hole the location, depth and nature of existing underground services indicated and where none are indicated to verify same prior to construction. Prices are to include for all excavations, backfilling, reinstatement and all other related aspects of carrying out these works.”
“The mains are to be laid to the routes and grades shown on the Drawings. All excavation shall be carried out in whatever material may be found. Surplus sub-soil and excavated material unsuitable for reuse as backfill shall be disposed of to the Contractor’s tip unless otherwise directed by Employer’s Representative. When excavation trenches in carriageways or surfaced footpaths the Contractor shall first cut through the surface asphalt etc, to a straight accurate edge, by a method to be approved by the Employer’s Representative, excavated material, for re-use in reinstatement or disposal as directed by the Employer’s Representative. The Contractor shall not, without the express permission of the Employer’s Representative or his Representative, at any time excavate along excessive or unreasonable lengths of highway as appropriate to the site location. As a section of main is laid along such section, backfilling and reinstatement shall be completed and all excavated materials surplus to the requirements of the Contract removed from the proceeds, with the intent that the minimum of delay. The contractor must take all precautions that are necessary to prevent the breaking away of the trench edges and no extra payment will be made for either excavations or reinstatement in excess of the standard trench widths where this is as a result of ‘overbreak’ of the trench edges… When excavating trenches other than carriageways the Contractor shall first remove all turf and topsoil for re-bedding or, if the turf is non-existent, all topsoil to the width of the trench and deposit clear of general trench excavated material for use in reinstatement. All excavated material shall be deposited so that it is not stockpiled on topsoil and will do as little damage and cause as little inconvenience as possible.”
“Backfill to trenches, other than Class 1 fill, shall in general be obtained from trench excavation, after processing if necessary. Where backfill of the specified class is not available as dug and processing is, in the opinion of the Employer’s Representative, impracticable, the Contractor shall import the appropriate backfilling material.”
“13.1 Right to Vary Variations may be initiated by the Engineer at any time prior to issuing the Taking-Over Certificate for the Works, either by an instruction or a request for the Contractor to submit a proposal. A Variation shall not comprise the omission of any work which is to be carried out by others. The Contractor shall execute and be bound by each Variation, unless the Contractor promptly gives notice to the Engineer stating (with supporting particulars) that (i) the Contractor cannot readily obtain the Goods required for the Variation, (ii) it will reduce the safety or suitability of the Works, or (iii) it will have an adverse impact on the achievement of the Schedule of Guarantees. Upon receiving this notice, the Engineer shall cancel, confirm or vary the instruction. 13.2 Value Engineering The Contractor may, at any time, submit to the Engineer a written proposal which (in the Contractor’s opinion) will, if adopted (i) accelerate completion, (ii) reduce the cost to the Employer of executing, maintaining or operating the Works, (iii) improve the efficiency or value to the Employer of the completed Works, or (iv) otherwise be of benefit to the Employer. The proposal shall be prepared at the cost of the Contractor and shall include the items listed in Sub-Clause 13.3 [Variation Procedure]. 13.3 Variation Procedure If the Engineer requests a proposal, prior to instructing a Variation, the Contractor shall respond in writing as soon as practicable, either by giving reasons why he cannot comply (if this is the case) or by submitting: (a) a description of the proposed design and/or work to be performed and a programme for its execution, (b) the Contractor’s proposal for any necessary modifications to the programme according to Sub-Clause 8.3 [Programme] and to the Time for Completion, and (c) the Contractor’s proposal for adjustment to the Contract Price. The Engineer shall, as soon as practicable after receiving such proposal (under Sub-Clause 13.2 [Value Engineering] or otherwise), respond with approval, disapproval or comments. The Contractor shall not delay any work whilst awaiting a response. Each instruction to execute a Variation, with any requirements for the recording of Costs, shall be issued by the Engineer to the Contractor, who shall acknowledge receipt. Upon instructing or approving a Variation, the Engineer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree to determine adjustments to the Contract Price and the Schedule of Payments. These adjustments shall include reasonable profit, and shall take account of the Contractor’s submissions under Sub-Clause 13.2 [Value Engineering] if applicable.”
“Whenever these Conditions provide that the Engineer shall proceed in accordance with this Sub-Clause 3.5 to agree or determine any matter, the Engineer shall consult with each Party in an endeavour to reach agreement. If agreement is not achieved, the Engineer shall make a fair determination in accordance with the Contract, taking due regard of all relevant circumstances. The Engineer shall give notice to both Parties of each agreement or determination, with supporting particulars. Each Party shall give effect to each agreement or determination unless and until revised under Clause 20 [Claims, Disputes and Arbitration].”
“The Contractor’s Representative shall notify the Employer’s Representative at the earliest opportunity of specific likely future events or circumstances which may adversely affect the work, increase the Contract Price, or delay the execution of the works. The Employer’s Representative may require the Contractor to submit an estimate of the anticipated effect of the future events or circumstances and/or a proposal under Sub-Clause 13.3. The Contractor shall submit such estimate and or proposal as soon as practicable. The Contractor’s Representative shall cooperate with the Employer’s Representative in making and considering proposals to mitigate the effect of any such event or circumstances in carrying out instructions of the Employer’s Representative.”
“If the Contractor considers himself to be entitled to any extension of the Time for Completion and/or any additional payment, under any Clause of these conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Engineer, describing the event or circumstances giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware of the events or circumstances. If the Contractor fails to give notice of a claim within such period of 28 days, the Time for Completion shall not be extended, the Contractor shall not be entitled to additional payment, and the Employer shall be discharged from all liability in connection with the claim. Otherwise, the following provisions of this Sub-Clause shall apply… The requirements of the Sub-Clause are in addition to those of any other sub-clause which may apply to a claim. If the Contractor fails to comply with this or another Sub-Clause in relation to any claim, any extension of time and/or additional payment shall take account of the extent (if any) to which the failure has prevented or prejudiced proper investigation of the claim, unless the claim is excluded under the second paragraph of this Sub-Clause.”
“if the Contractor fails to give notice within 28 days of it becoming apparent that a claim had arisen…the Contractor shall not be entitled to additional payment and the Employer shall be discharged of any further liability…”
“This is not the place to explore the circumstances in which a person can be estopped from relying on a contractual provision laying down conditions for the formal validity of a variation. The courts below rightly held that the minimal steps taken by Rock Advertising were not enough to support any estoppel defences. I would merely point out that the scope of estoppel cannot be so broad as to destroy the whole advantage of certainty for which the parties stipulated when they agreed upon terms including the No Oral Modification clause. At the very least, (i) there would have to be some words or conduct unequivocally representing that the variation was valid notwithstanding its informality; and (ii) something more would be required for this purpose than the informal promise itself: see Actionstrength Ltd v International Glass Engineering IN.GL.EN SpA[2003] 2 AC 541 , paras 9, 51, per Lord Bingham of Cornhill and Lord Walker of Gestingthorpe.”
“The Employer shall appoint the Engineer who shall carry out the duties assigned to him in the Contract. The Engineer’s staff shall include suitable qualified engineers and other professionals who are competent to carry out these duties. The Engineer shall have no authority to amend the Contract. The Engineer may exercise the authority attributable to the Engineer as specified in or necessarily to be implied from the Contract. If the Engineer is required to obtain the approval of the Employer before exercising a specified authority, the requirements shall be as stated in the Particular Conditions. The Employer undertakes not to impose further constraints on the Engineer’s authority, except as agreed with the Contractor. However, whenever the Engineer exercises a specified authority for which the Employer’s approval is required, then (for the purpose of the Contract) the Employer shall be deemed to have given approval. Except as otherwise stated in these Conditions: (a) whenever carrying out duties or exercising authority, specified in or implied by the contract, the Engineer shall be deemed to act for the Employer; (b) the Engineer has no authority to relieve either Party of any duties, obligations or responsibilities under the Contract; and (c) any approval, check, certificate, consent, examination, inspection, instruction, notice, proposal, request, test, or similar act by the Engineer (including absence of notice, proposal, request, test, or similar act by the Engineer (including absence of disapproval) shall not relieve the Contractor from any responsibility he has under the Contract, including responsibility for errors, omissions, discrepancies and non-compliances.” (a) whenever carrying out duties or exercising authority, specified in or implied by the contract, the Engineer shall be deemed to act for the Employer; (b) the Engineer has no authority to relieve either Party of any duties, obligations or responsibilities under the Contract; and (c) any approval, check, certificate, consent, examination, inspection, instruction, notice, proposal, request, test, or similar act by the Engineer (including absence of notice, proposal, request, test, or similar act by the Engineer (including absence of disapproval) shall not relieve the Contractor from any responsibility he has under the Contract, including responsibility for errors, omissions, discrepancies and non-compliances.”
“The first is that it prevents attempts to undermine written agreements by informal means, a possibility which is open to abuse, for example in raising defences to summary judgment. Secondly, in circumstances where oral discussions can easily give rise to misunderstandings and crossed purposes, it avoids disputes not just about whether a variation was intended but also about its exact terms. Thirdly, a measure of formality in recording variations makes it easier for corporations to police internal rules restricting the authority to agree them. These are all legitimate commercial reasons for agreeing a clause like clause 7.6. I make these points because the law of contract does not normally obstruct the legitimate intentions of businessmen, except for overriding reasons of public policy. Yet there is no mischief in No Oral Modification clauses, nor do they frustrate or contravene any policy of the law.”
“Whilst there is, in principle, a difference between a variation to the terms of a contract and a variation in the work to be carried out under a contract, a strict approach to a contractual provision as to the form of changes might consistently be applied to both.”