“1. The Member States shall take the measures necessary to ensure that, as regards contract award procedures falling within the scope of Directives 71/305/EEC and 77/62/EEC, decisions taken by the contracting authorities may be reviewed effectively and, in particular, as rapidly as possible in accordance with the conditions set out in the following Articles, and, in particular, Article 2(7) on the grounds that such decisions have infringed Community law in the field of public procurement or national rules implementing that law. 2. Member States shall ensure that there is no discrimination between undertakings claiming injury in the context of a procedure for the award of a contract as a result of the distinction made by this Directive between national rules implementing Community law and other national rules.”
“1. The Member States shall ensure that the measures taken concerning the review procedures specified in Article 1 include provision for the powers to: ” (a) take, at the earliest opportunity and by way of interlocutory procedures, interim measures with the aim of correcting the alleged infringement or preventing further damage to the interests concerned, including measures to suspend or to ensure the suspension of the procedure for the award of a public contract or the implementation of any decision taken by the contracting authority; (b) either set aside or ensure the setting aside of decisions taken unlawfully, including the removal of discriminatory technical, economic or financial specifications in the invitation to tender, the contract documents or in any other document relating to the contract award procedure…”
“29. By its first question, the national court is asking essentially whether the combined provisions of Article 2(1)(a) and (b) and the second subparagraph of Article 2(6) of Directive 89/665 must be interpreted as meaning that the Member States are required to ensure that the contracting authority's decision, prior to the conclusion of the contract, as to the bidder in a tender procedure with which it will conclude the contract is in all cases open to review in a procedure whereby an applicant may have that decision set aside if the relevant conditions are met, regardless of the possibility, once the contract has been concluded, of obtaining an award of damages. … 33. As is clear from the first and second recitals in the preamble to Directive 89/665, the directive reinforces existing arrangements at both national and Community level for ensuring effective application of Community directives on the award of public contracts, in particular at the stage where infringements can still be rectified … 38. Moreover, the interpretation proposed … might lead to the systematic removal of the most important decision of the contracting authority, that is to say the award of the contract, from the purview of the measures which, under Article 2(1) of Directive 89/665, must be taken concerning the review procedures referred to in Article 1, thereby undermining the purpose of Directive 89/665 which, as noted in paragraph 34 of this judgment, is to establish effective and rapid procedures to review unlawful decisions of the contracting authority at a stage where infringements may still be rectified. … 43. It follows … Member States are required to ensure that the contracting authority's decision prior to the conclusion of the contract as to the bidder in a tender procedure with which it will conclude the contract is in all cases open to review in a procedure whereby an applicant may have that decision set aside if the relevant conditions are met, notwithstanding the possibility, once the contract has been concluded, of obtaining an award of damages.”
“(3) Consultations of the interested parties and the case law of the Court of Justice have revealed a certain number of weaknesses in the review mechanisms in the Member States. As a result of these weaknesses, the mechanisms established by Directives 89/665/EEC and 92/13/EEC do not always make it possible to ensure compliance with Community law, especially at a time when infringements can still be corrected… (4) The weaknesses which were noted include in particular the absence of a period allowing an effective review between the decision to award a contract and the conclusion of the contract in question. This sometimes results in contracting authorities and contracting entities who wish to make irreversible the consequences of the disputed award decision proceeding very quickly to the signature of the contract. In order to remedy this weakness, which is a serious obstacle to effective judicial protection for the tenderers concerned, namely those tenderers who have not yet been definitively excluded, it is necessary to provide for a minimum standstill period during which the conclusion of the contract in question is suspended, irrespective of whether conclusion occurs at the time of signature of the contract or not… (12) Seeking review shortly before the end of the minimum standstill period should not have the effect of depriving the body responsible for review procedures of the minimum time needed to act, in particular to extend the standstill period for the conclusion of the contract. It is thus necessary to provide for an independent minimum standstill period that should not end before the review body has taken a decision on the application. This should not prevent the review body from making a prior assessment of whether the review as such is admissible… (18) In order to prevent serious infringements of the standstill obligation and automatic suspension, which are prerequisites for effective review, effective sanctions should apply. Contracts that are concluded in breach of the standstill period or automatic suspension should therefore be considered ineffective in principle… (36) This Directive respects fundamental rights and observes the principles recognised in particular by the Charter of Fundamental Rights of the European Union. In particular, this Directive seeks to ensure full respect for the right to an effective remedy and to a fair hearing, in accordance with the first and second subparagraphs of Article 47 of the Charter.”
“47H.—(1) In proceedings, the Court may, where relevant, make an interim order— (a) bringing to an end the requirement imposed by regulation 47G(1); (b) restoring or modifying that requirement; (c) suspending the procedure leading to— (i) the award of the contract; or (ii) the determination of the design contest, in relation to which the breach of the duty owed in accordance with regulation 47A or 47B is alleged; (d) suspending the implementation of any decision or action taken by the contracting authority in the course of following such a procedure.
“11. (1) Nothing in these Regulations affects any contract award procedure commenced before20th December 2009 .”
“For reasons of legal certainty and coherence, the general rule should be that decisions made pursuant to a procedure properly launched need follow only the legal rules in force at the time the procedure is launched.”
“The overriding consideration is which course is likely to involve the least risk of injustice if it turns out to be ‘wrong’ in the sense of granting an interlocutory injunction to a party who fails to establish his rights at trial (or would fail if there was a trial) or, alternatively, in failing to grant an injunction to a party who succeeds (or would succeed) at trail.”
“The question is not whether damages are an ‘adequate’ remedy, but whether specific performance will ‘do more perfect and complete justice than an award of damages’.”
‘Is it just, in all the circumstances, that a claimant should be confined to his remedy in damages?’
“33. I turn first, then, to consider the adequacy of a remedy in damages. Mr Giffin's principal submission was that if the contractor is confined to a remedy in damages, as it will be if the present order is discharged, the quantification of its loss would prove very problematical. That is because it will have to take account not only that the claim will for the loss of a chance of being successful in a fairly operated tender process (which will have to take account of how other bidders would have acted under those circumstances), but also the consequential loss of the chance of being called on by the council to provide services pursuant to the framework contract… 35. To some extent I have already dealt with Miss Holmes' [counsel for the authority] points, which in my view tend, if anything, to reinforce the contractor's argument that, since loss is likely to be so difficult to assess, damages are not an adequate remedy as far as it is concerned. However, they also overlook the fact that the tender procedure is not yet complete and no contract has yet been awarded… 36. A loss of an opportunity to take part in a fair tendering process on equal terms with other bidders may be difficult to evaluate in monetary terms but cannot be said to be on no commercial value at all.” (b) Morrisons Facilities Services Ltd v Norwich City Council[2010] EWHC 487 (Ch) where Arnold J concluded that damages would not be an adequate remedy in part because of the difficulty in assessing those damages. He accepted the submission that “in a case where one of the complaints is that of undisclosed criteria, it is very difficult indeed for the court at trial, to assess damages because assessment of what chance has been lost by the claimant, in those circumstances, is virtually impossible.”
“33…quantification of the profits which would be earned by Indigo over the period of the contract would be inherently difficult, and necessarily very imprecise, though of course an operation which the court can, if required, carry out. 34. Some might consider a discounted monetary remedy is in principal preferable to an all-or-nothing gamble possibly obtaining the contract on a re-run of all or part of the tender process. I do not however consider that this evaluation is one with which the court should be involved. 35. I have therefore concluded that a claim for damages would not be intrinsically an adequate remedy and that in that regard failure to continue the standstill could properly be regarded as a prejudice to Indigo.”