“The existing and forecast shift in population demographics has resulted in a growing market which, together with on-going pressure on government budget spend, has produced significant opportunities for the Company to expand. As the population ages, and advances in medical technology facilitate care in the home, growth can reasonably be expected from existing contracts. In addition, visible tenders for further CES moving to the outsourced market signpost significant opportunities in the coming years. There are also expanding opportunities in the self-funding retail market and CES linked activities including Planned Preventative Maintenance, and Home Improvement & Minor Adaptations.”
“82 It is evident that the question of adequacy of damages does not depend solely on whether or not the court could and would do its best in difficult circumstances to assess damages. As Sachs LJ said in Evans Marshall v Bertolaat 380 C to D: “The courts have repeatedly recognised that there can be claims under contracts in which as here, it is unjust to confine a plaintiff to his damages for their breach. Great difficulty in estimating these damages is one factor that can be and has been taken into account. Another factor is the creation of certain areas of damage which cannot be taken into monetary account in a common law action for breach of contract: loss of goodwill and trade reputation are examples…” 83 In the present case I consider that there would be great difficulty in estimating the damages which would have to be assessed if the breach in terms of undisclosed, irrational and inappropriate criteria were to be proved. The court would have to assess what would be the impact if those criteria had been disclosed to the tenderers and what would be the impact if rational and appropriate criteria had been applied. Even with two tenderers the court will be left to speculate on a range of possibilities and, whilst it would do its best to come to a conclusion, the difficulty in estimating the damages is, as Sachs LJ said a factor to be taken into account in determining whether it would be unjust to confine a claimant to damages for breach”. “The courts have repeatedly recognised that there can be claims under contracts in which as here, it is unjust to confine a plaintiff to his damages for their breach. Great difficulty in estimating these damages is one factor that can be and has been taken into account. Another factor is the creation of certain areas of damage which cannot be taken into monetary account in a common law action for breach of contract: loss of goodwill and trade reputation are examples…”
“As a matter of principle, loss of reputation and market position may be relied on to establish that damages would not provide adequate compensation for a party seeking to maintain the automatic suspension in a procurement challenge; for example, where there is evidence that loss of a unique prestigious contract is likely to impact adversely upon a party's reputation so as to reduce its prospects of future profitable work…”
“Damage to reputation may be a relevant factor but requires cogent evidence showing that such loss of reputation would lead to financial losses that would be significant and irrecoverable as damages or very difficult to quantify fairly…”
“the impact of the lifting of the suspension on the Claimant …would be (in his words) “devastating and irreversible”
“… if the suspension is lifted, the Claimant will lose its highly and uniquely trained workforce under TUPE regulations, that workforce being predominantly engaged on the existing contract. It is a team that has taken years to develop; its skills are not available on the wider market. The Defendant ripostes by stating that in such circumstances the highly trained team would not be lost to the general public. But that ignores the irremedial harm to the Claimant which is the issue under consideration here. …”