“In the case of tenderers which have been excluded from the tendering procedure, Article 2a of Directive 89/665 makes clear that these are no longer to be deemed to be concerned and the contract award decision must not therefore be communicated to them if their exclusion has become definitive. However, where those tenderers have not yet been definitively excluded, the contract award decision, accompanied by a summary of the relevant reasons and a statement of the standstill period for conclusion of the contract following that decision, must be communicated to them. It is apparent from reading paragraphs 1 and 2 of that article together that compliance with those minimum conditions is intended to enable such tenderers to seek an effective review of that decision. 74 The fact that the exclusion decision is not yet definitive thus determines, for those tenderers, their standing to challenge the contract award decision […].”
“the delay of the plaintiff severely impedes the court in the practical act of doing justice on this application. In a procurement case such as this, delay will mean that substantial benefits are denied to the public for a period of time, 6 months at a minimum, which will have adverse public interest consequences, which I have discussed above. The court is entitled to take this delay into account, and who is responsible for that delay in determining whether to grant an interim injunction. In this case the court has concluded that the majority of the delay was occasioned by the plaintiff and that the consequences for this delay must be borne by the plaintiff. In the court’s view the public interest is the decisive factor in considering “the balance of doing an injustice”
“(a) If damages are an adequate remedy, that will normally be sufficient to defeat an application for an interim injunction, but that will not always be so (American Cyanamid, Fellowes [v Fisher[1976] 1 QB 122 (CA)], National Bank [v Olint Corp[2009] 1 WLR 1405 ]); (b) In more recent times, the simple concept of the adequacy of damages has been modified at least to an extent, so that the court must assess whether it is just, in all the circumstances, that the claimant be confined to his remedy of damages (as in Evans Marshall [[1973] 1 WLR 349 ] and the passage from Chitty); … ”
“I accept Mr Jones’ evidence that the loss of this contract is likely to have a substantial adverse effect on [DHL’s] reputation which would be very difficult properly to quantify. The logistics contract is prestigious and high value. [DHL] is the incumbent provider of the logistics services. The fact that the MSA has been broken into a number of separate contracts does not detract from the fact that [DHL] will be seen in the marketplace as having lost a valuable contract for the provision of these services in a procurement exercise where the outcome is not determined solely on price. [DHL] will lose a unique selling point when bidding for other, similar projects that is likely to affect its ability to win them.”
‘There are a number of reasons why that might be so….’
“It is fundamentally wrong in principle to say that an award of damages would not restore a reputation lost because of the rejection of a tender, but the award of the contract itself would. What would matter in those circumstances would be the public acknowledgement that their bid had been wrongly rejected, not the precise remedy which the court provides in consequence of that finding.”
“30. The Court has not been deterred by difficulty of assessment as such. But it has recognised that the more variables are fed into a "loss of chance" calculation, the more likely it becomes that the compensation recovered by the aggrieved party will not match the outcome after the features that were uncertain in prospect have resolved themselves and determined what in fact happens. One example illustrates the problem: if the procurement is limited to two tenderers there may be circumstances in which, even at the interim suspension stage, the Court can be confident that if the impugned successful tenderer had not been awarded the contract, the aggrieved one would have been. However, the more tenderers there are, the less certain this may be – leading to a discounting of the aggrieved tenderer's chance when calculating damages.”
‘I accept for present purposes that there may be circumstances where the number of uncertainties or variables that have to be brought into the calculation of the aggrieved tenderer's lost chance may persuade the Court that damages would not be an adequate remedy. However, the mere fact that the damages will be for loss of a chance and will be assessed as such is not of itself evidence that the damages are an inadequate remedy. The reverse is likely to be true in many or most cases because the principles that have been developed have been designed to reflect the true commercial value of the chance that has been lost.’
“44. In Alstom, O'Farrell J had said that, if a breach was not sufficiently serious enough to justify the Francovich conditions, it was unlikely to be sufficiently serious to justify setting aside the contract under challenge, Constable J said in Boxxe that there was force in that observation. I agree. In my experience, the present case is therefore unusual, if not unique, because of the vast gap the judge found between the very low culpability on the part of the respondent, and the extreme consequences of the single marking error. … 118. I acknowledge that there is some tension between the test to be applied at the interim stage, and the Francovich conditions. That tension was first identified by Fraser J in Lancashire Care, and ways to ameliorate the practical issues that can arise were noted in Bombardier and Boxxe. Furthermore, I acknowledge that, as per O'Farrell J in Alstom, it is not a tension that is likely to come to the surface very often, since in most cases, a breach that would have reversed the result of a tender process is more likely than not to be sufficiently serious to justify Francovich damages. 119. That of course brings us straight back to our starting point. This was a very unusual and, as the judge said, "most unfortunate", situation. It was also, in my experience, very rare. A single, inadvertent breach in an otherwise impressive and careful procurement exercise caused the wrong result. The judge agonised over the competing factors and in the end concluded that Francovich damages were not justified. Some judges might have come to a different view: that is not the point. The only issue is whether the judge erred in principle in undertaking that exercise. For the reasons that I have given, I conclude that he did not.”
“…it was noted that the Committee had considered the principal risk register in its most recent meeting and that 6 of the 11 principal risks were outside of the stated risk appetite for those risks. It was noted that the fragility of the existing IT system meant that the risk relating to IT stability had crystallised and was now creating wider issues for the Company meaning that it was suffering contagion between risks and the Committee felt that this position was intolerable….”
“The Supplier ADSM function will be responsible for the development of the technical roadmap that supports modernization/replacement of all legacy Logistics and transport applications and services. With changes being agreed through the Change Control process.”
“(1) Contracting authorities shall take appropriate measures to effectively prevent, identify and remedy conflicts of interest arising in the conduct of procurement procedures so as to avoid any distortion of competition and to ensure equal treatment of all economic operators. (2) For the purposes of paragraph (1), the concept of conflicts of interest shall at least cover any situation where relevant staff members have, directly or indirectly, a financial, economic or other personal interest which might be perceived to compromise their impartiality and independence in the context of the procurement procedure.” 41: “(1) Where a candidate or tenderer, or an undertaking related to a candidate or tenderer - (a) has advised the contracting authority, whether in the context of regulation 40 or not, or (b) has otherwise been involved in the preparation of the procurement procedure, the contracting authority shall take appropriate measures to ensure that competition is not distorted by the participation of that candidate or tenderer. (2) Such measures shall include— (a) the communication to the other candidates and tenderers of relevant information exchanged in the context of or resulting from the involvement of the candidate or tenderer in the preparation of the procurement procedure; and (b) the fixing of adequate time limits for the receipt of tenders.”