“(1) A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section. For this purpose ‘dispute’ includes any difference… (3) The contract shall provide that the decision of the adjudicator is binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement. The parties may agree to accept the decision of the adjudicator as finally determining the dispute.”
“(1) A party to a construction contract may not withhold payment after the final date for payment of a sum due under the contract unless he has given an effective notice of intention to withhold payment. The notice mentioned in section 110(2) may suffice as a notice of intention to withhold payment if it complies with the requirements of this section. (2) To be effective such a notice must specify- (a) the amount proposed to be withheld and the ground for withholding payment, or (b) if there is more than one ground, each ground and the amount attributable to it, and must be given not later than the prescribed period before the final date for payment. (3) The parties are free to agree what that prescribed period is to be. In the absence of such agreement, the period shall be that provided by the Scheme for Construction Contracts.”
“The date by which practical completion is to be achieved, being 23 months from the commencement date as the same may be adjusted from time to time in accordance with clause 7 and Schedule 8 (Change).”
“The date on which the final release certificate in respect of the last new variable message sign to be installed by the Contractor has been issued by Serco.”
“Any change to the services initiated by Serco pursuant to Schedule 8 (Change).”
“Breaches of contract or Serco Changes, or other events on the part of Serco or those for whom Serco is responsible, which entitle Balfour Beatty to extension of time.”
“Any changes to the requirements within the scope of this Contract shall be made only in accordance with the procedures set out in Schedule 8 (Change).”
“If Serco requires payment or allowance of liquidated and ascertained damages pursuant to clause 30.1, it shall first serve notice to that effect on the Contractor. Provided a notice has been served, Serco shall not be obliged to serve further notices of its requirement where the period for which liquidated and ascertained damages are payable is ongoing.”
“Liquidated and ascertained damages shall be due and payable or allowed to Serco at the end of each month to which they relate.”
“The decision of the adjudicator shall be binding upon the parties, who shall forthwith give effect to the decision, unless and until the dispute is finally determined by the court or otherwise resolved by agreement between the parties.”
“The parties shall be entitled to the relief and remedies set out in the decision and to seek summary enforcement thereof subject to review by the courts. No issue decided by the adjudicator may subsequently be laid before another adjudicator unless so agreed by the parties.”
“Claim (1) Notices of determination. Claim (2) Additional traffic management. Claim (3) Network access. Claim (4) Additional design input. Claim (5) Godstone quality. Claim (6) Manchester piling cancellation. Claim (7) Shared access costs. Claim (8) Winter weather costs. Claim (10) Additional varioguard. Claim (11) Betterment. Claim (12) Entitlement. Claim (13) Prolongation up to29th February 2004 . Claim (14) Mitigation. Claim (15) Disruption. Claim (16) Finance Charges. Claim (17) VOP. Claim (18) Anticipated staff costs to completion.”
“As a result of the actions of Serco, the Contractor seeks the award of£8,839,825 and an extension of time of 48.71 weeks, or such other sums or periods as the adjudicator thinks fit.” (2) Paragraph 394 of the referral notice reads as follows: “The referring party asks the adjudicator to decide that the responding party grant to the referring party an extension of time of 48.71 weeks in respect of the delays caused by Serco or such period as the adjudicator may decide.” (3) At the very end of the referral notice Balfour Beatty formulates its overall claim in the following two paragraphs: “Summary of relief sought Time 464. The Contractor seeks the award of a total of 48.71 weeks’ extension of time or such other period as the adjudicator may decide. Quantum 465. The Contractor seeks the award of a total of£8,839,825 or such other sum as the adjudicator may decide.”
“30. At the same time as addressing Balfour Beatty’s claim for extensions of time set out in claim 1, it is convenient also to address Balfour Beatty’s other claims to extensions of time. The overall position is as follows: (1) In claim 1 Balfour Beatty claims an extension of time of 34 weeks by reason of (a) the need to provide environmental reports in a revised format and (b) the need for NODs to be published by the HA. (2) In claim 12 Balfour Beatty claims an extension of time of 29 weeks by reason of delays to the publication of NODs in the northern area of the contract. (3) Also in claim 12 Balfour Beatty claims an extension of time of 48.71 weeks in consequence of various events summarised under the heading ‘Actual delays’. (4) In various other claims Balfour Beatty advances various extensions of time claims related to specific matters. Largely these reflect the events summarised under the heading, ‘Actual delays’ referred to above. 31. The point has been made that these claims are expressed in a confusing way. Mr Kaletka did little to clarify matters in his report. However, I note from Serco’s response at paragraphs 66 and 68 that it has read Balfour Beatty’s claims for extensions of time of 29 weeks and 34 weeks as cumulative. I also read them that way. If granted, the completion date would be extended by 63 weeks to7th June 2004 . 32. The claim for 48.71 weeks set out in claim 12 appears to me to be a claim that the completion date should be extended by 341 days from24th March 2003 to29th February 2004 . Accordingly, I read Balfour Beatty’s claim for extensions of time as being essentially two in number, viz (1) a claim for extension of time to7th June 2004 in respect of the requirements to comply with the NOD regime and (2) a claim for an extension of time to29th February 2004 in respect of the events summarised under the heading ‘Actual delays’. I note that it is common ground between the programming experts, Mr Kaletka and Mr Dedha that, in the event, the critical aspect of the works has turned out to be the installation of two signs, known as ‘19TO3’ and ‘19TO4’ at Penrith. These signs have yet to be installed. In these circumstances it seems to me that, for the purposes of assessing Balfour Beatty’s entitlement to an extension of time, it is necessary to focus on these two signs and examine the effect of the requirement to comply with the NOD regime upon them. In these circumstances I ignore, for these purposes, the events summarised in claim 12 under the heading, ‘Actual delays’ and Balfour Beatty’s other extension of time claims on the footing that those events were non-critical. 33. In respect of 19TO3 and 19TO4 my findings are as follows: (1) According to Balfour Beatty’s implementation plan the environmental report in respect of the three signs at Penrith was due on19th November 2001 . (2) Balfour Beatty submitted its original environmental reports on17th October 2001 . (3) Following receipt of comments, Balfour Beatty submitted its revised environmental report in respect of Penrith (Environmental Report 2) on21st March 2002 . (4) Subsequently, Balfour Beatty was instructed to produce separate environmental reports for the signs at Penrith. That which covered 19TO3 and 19TO4 was to be environmental report 2B. In the event that report was submitted on4th June 2003 . (5) Following submittal of that report the earliest possible date for reaching practical completion for 19TO3 and 19TO4 was4th September 2003 . (6) However, in the event the NOD, in respect of 19TO3 and 19TO4, was not published until3rd September 2004 . (7) In consequence, following publication of that NOD, the earliest possible start date for Balfour Beatty’s installation works on site was15th October 2004 . I am conscious that it is Serco’s case that at least part of the delay in the finalisation of Balfour Beatty’s environmental reports is to be attributed to failures on the part of Balfour Beatty to draw up the earlier versions ni a competent manner. In his report Mr Dedha criticises Balfour Beatty for significant delays during the drafting stage and suggests that insufficient time was allowed for that activity. Such observations appear to be of general application. In relation to Penrith specifically, Mr Dedha says, ‘The decision to split Hadrian’s Wall from report 2 was undoubtedly delayed in itself because of the need to deal with significant comments on the reports’ (paragraph 1.54). I calculate the delays in submitting the report to be at least the period31st October 2001 to the submission of report 2A on25th March 2003 less 35 days, which is 510 days. Once again, there are unexplained gaps that may be other delays or float between the effective commencement date and sign erection. I am aware of some of the possible reasons for delay but have not had time to factor them into my analysis (paragraph 6.6.3).’ There was no other evidence which directly linked the delay in preparation of the Penrith reports with default on the part of Balfour Beatty. On the basis of this evidence I am not satisfied that the extension of time in respect of 19TO3 and 19TO4 should be adjusted in Serco’s favour to allow for default on the part of Balfour Beatty. In any event, I note that Balfour Beatty’s claim in these proceedings is not for a full extension of time but rather for an extension of time to7th June 2004 , which is some five and a half months short of a full extension of time. Even if some allowance were to be made for default on the part of Balfour Beatty, it seems to me most unlikely that the necessary adjustment could be as much as five and a half months. 34. In these circumstances I think it right to allow Balfour Beatty’s claim for extension of time and to revise the completion date to7th June 2004 . I propose to dismiss Balfour Beatty’s other extension of time claims. For this reason I do not refer to those other extension of time claims when addressing the claims under separate headings below.”
“However, Balfour Beatty was prevented from completing its installation works until at least7th June 2004 .”
“…comply, without recourse to defences or crossclaims not raised in the adjudication.”