“9.1 The Sub-Contractor shall commence the work on the date stated herein:26th September 2011 . 9.2 The Sub-Contractor shall complete the Works on or before the date stated herein or in the period stated herein: Period of 18 consecutive weeks maximum duration, to include demolition and asbestos removal and clearance of all materials from site. 10. Rates and Payment Terms 10.1 Valuations are to be submitted for the attention of the Contractor’s Commercial Director (Jonathan Ridgeway) 5 working days before month end. This Sub-Contractor is let on a credit basis, therefore the Contractor will invoice the Sub-Contractor for credit detailed in 10.2. Payment shall be the gross value of work properly carried out, and certified for payment, less the amount retained as retention, as stated in the appendix to these conditions, less the amount of any agreed discounts less total amounts previously certified in respect of the Sub-Contract Works. Any amounts retained shall be processed for payment after receipt of the Making Good Defects Certificate. Retention: 0% Discount: 0% 10.2 Payment Period: 30 days after receipt of invoice from the Contractor to the Sub-Contractor; invoices to be submitted week one, five and nine of the contract. Each invoice will be for£15,000 +VAT. 10.3 Liquidated and ascertained damages are applicable under this Sub-Contract and will be levied against the Sub-Contractor at£15,000 per week after the completion date in sections 9.1 and 9.2. 10.3 The Contractor reserves the right to deduct from any payments certified as due to the Sub-Contractor and/or otherwise recover the amount if [of] any bona fide contra accounts and/or claims which he, the Contractor, may have against the Sub-Contractor in connection with breach of this or any other contract, or by any tortuous act or by any breach of statutory duty… 12.2 The Main Conditions of Contract are the ICE Conditions of Contract Design and Construct, 2nd Edition with amendments. The Sub-Contractor is deemed to have full knowledge of the provisions of the Main Contract – a copy of such terms and conditions is available for inspection. These shall be deemed to be incorporated herein, provided always that if these differ from those embodied in this contract these conditions shall apply and be enforced accordingly. Any conditions contained in the Sub-Contractor’s quotations shall be excluded.”
“a) Where it follows logically from an adjudicator’s decision that the employer is entitled to recover a specific sum by way of liquidated and ascertained damages, then the employer may set-off that sum against monies payable to the contractor pursuant to the adjudicator’s decision, provided that the employer has given proper notice (insofar as is required). b) Where the entitlement to liquidated and ascertained damages has not been determined, either expressly or impliedly, by the adjudicator’s decision, then the question whether the employer is entitled to ser-off liquated and ascertained damages against sums awarded by the adjudicator will depend upon the terms of the contract and the circumstances of the case.”