“Payment for the subcontract work shall be made on the basis of the subcontract price as determined in accordance with the subcontract based on the target cost, subject to adjustments.”
“The subcontractor shall submit a draft statement in two hard copies and one electronic copy to the contractor within five days after the end of each month in a form approved by the contractor, showing in detail the amounts to which the subcontractor considers himself to be entitled together with all necessary supporting documentation (in accordance with the details of payment particulars as required by Exhibit E) and a comparative analysis against the target cost. The draft statement shall include the following items as applicable in the sequence listed … (d) all necessary adjustments as Exhibit E.”
“Full and concise details are presented in the agreed notes of commercial meetings Nos. 1 to 11 inclusive (signed by both parties) as contained in Exhibit F.”
“The risk/reward is limited to the costs relating to target labour hours and commensurate values only as set out in the schedule. For the purposes of clarity, the supervision, plant etc are not subject to the target cost and therefore do not form part of the risk/reward schedule.”
“The JV confirmed their understanding of the risk/reward as follows.”
“Ledwood set out the following for the JV review. Main board policy dictated the maximum overspend exceeding 20% of the subcontract target value be capped at£600,000 where Ledwood were 100% liable. Thereafter Ledwood require reimbursement without any addition of 10%. JV stated in consideration of this new departure they would reassess the savings relative to any capping. JV to review in the context of the original agreement.”
“JV still to review Ledwood capping.”
“For the purpose of absolute clarity, it was agreed the risk/reward was limited to the labour hours and commensurate values. JV still to review.”
“Ledwood agreed to adhere to the original risk/reward principles, ie no capping.”
“In the absence of any directions by the Adjudicator relating to the time for performance of his decision, the parties shall be required to comply with any decision of the Adjudicator immediately on delivery of the decision to the parties in accordance with this paragraph.”
“I derive two principles of law from the authorities, which are relevant for present purposes. (a) Where it follows logically from an adjudicator’s decision that the employer is entitled to recover a specific sum by way of liquidated and ascertained damages, then the employer may set off that sum against monies payable to the contractor pursuant to the adjudicator’s decision, provided that the employer has given proper notice (insofar as required). (b) Where the entitlement to liquidated and ascertained damages has not been determined either expressly or impliedly by the adjudicator’s decision, then the question whether the employer is entitled to set off liquidated and ascertained damages against sums awarded by the adjudicator will depend upon the terms of the contract and the circumstances of the case.”