“1.1 Dispute over outstanding payment of£16,214.88 which [Magna] is due under contract for works completed…and invoiced to [Mr Horne]… Roland Horne sent a letter to [Magna] accusing [it] of not commencing with work ‘regularly and diligently’ and to return to site within 7 days or terminate the contract as per Clause 6.4.1 JCT Minor Works contract terms. [Magna] maintains that it did commence with work regularly and diligently, remained in communication during this period and was awaiting confirmation of payment and delivery of items which Roland Horne was aware of, as can be proven by correspondence between the parties. [Magna] return to site on 23/01/14 and 24/01/14 as requested within the 7 day period so that there were no grounds for Roland Horne to terminate the contract and withhold payment due for works completed and invoiced. Relevant Horne then instructed a solicitor to write a letter to [Magna] on 31/01/14 denying [Magna] return to site within that period, forcing [Magna] to respond and incur unnecessary legal fees…”
“.2 no further sum shall become due to the Contractor other than any amount that may become due to him under clause 6.7.4…”
"was [Magna’s] employment validly terminated?"
"(a) Where it follows logically from an adjudicator's decision that the employer is entitled to recover a specific sum by way of liquidated and ascertained damages, then the employer may set off that sum against monies payable to the contractor pursuant to the adjudicator's decision, provided that the employer has given proper notice (insofar as required). (b) Where the entitlement to liquidated and ascertained damages has not been determined either expressly or impliedly by the adjudicator's decision, then the question whether the employer is entitled to set off liquidated and ascertained damages against sums awarded by the adjudicator will depend upon the terms of the contract and the circumstances of the case." 21. The starting point for any consideration of jurisdiction is the Notice of Adjudication: see Jerome Engineering Limited v Lloyd Morris Electrical Limited [2002] CILR 1827. Here, the dispute set out in the Notice of Adjudication was said to be "the proper valuation of Certificate 27"
"…Workspace consistently claimed a net sum giving the result of the benefit of the payment made by YJL in compliance with the second adjudication decision. The Adjudicator's third decision, therefore, inevitably required him to take into account that payment made by YJL. If he had not done so, then he would still have concluded that a payment of£77,371.70 was due to Workspace. The Adjudicator was therefore addressing not only the valuation of Certificate 27 but also the balance of the account between the parties. Although he states that he cannot decide that the balance of£48,830.30 plus VAT was due, he has in fact done so in his decision. He clearly found that the payment of£126,192 was made and that the sum of£77,371.70 was due or he could not have deducted it against the negative valuation. There is no basis in his decision for distinguishing between any part of the payment made as a sum due."