“The dispute is over Architects’ Certificate No. 27, dated16th October 2007 ; Sums to be repaid by the Respondent; Interest.” Interest.”
‘The amount included by the quantity surveyor against YJL prolongation/disruption and S/C prolongation/disruption in Architect’s Certificate No. 27 is£194,660 . Therefore, based on my calculation of the loss and expense which should have been included, Architect’s 27 should be increased by£277,599.30 (£474,259.30 -£194,660 ). This would revise the negative balance of Architect’s Certificate No. 27 from£356,971 to£77,371.70 (£356,971 -£277,599.30 ). As YJL has already repaid£126,192 in respect of “prolongation time, loss and expense”, it follows that Workspace is not entitled to repayment of sums pursuant to Architect’s Certificate No. 27.’
“Having considered the request, I confirm that the reason for my finding at paragraph 25 of my decision that Workspace is not entitled to repayment of sums pursuant to Architect’s Certificate No. 27 was as a result of the application of my finding in paragraph 21 that the calculation of the amount of loss and expense which should have been included in Architect’s Certificate No. 27. As a result, I found that Architect’s Certificate No. 27 should be increased by£277,599.30 . Whilst it follows from my finding that YJL should be entitled to a further amount of£48,820.30 , due to the scope of the Adjudication Notice and the redress sought, I considered that I was unable to decide or direct that the amount was due.”
“1. To what extension of time is YJL entitled under the building contract? 2. What sums are due to YJL under clause 26 of the building contract? 3. What sums are due to YJL in respect of variations which have been instructed under the contract? …”
“(a) Where it follows logically from an adjudicator's decision that the employer is entitled to recover a specific sum by way of liquidated and ascertained damages, then the employer may set off that sum against monies payable to the contractor pursuant to the adjudicator's decision, provided that the employer has given proper notice (insofar as required). (b) Where the entitlement to liquidated and ascertained damages has not been determined either expressly or impliedly by the adjudicator's decision, then the question whether the employer is entitled to set off liquidated and ascertained damages against sums awarded by the adjudicator will depend upon the terms of the contract and the circumstances of the case.”
“…the entitlement to extension of time is included as a necessary and indispensible precursor to the direct loss or expense and, as it may be, the establishment of a proper or new rate or price, to enable the rules for valuation of variation to be properly applied, or indeed, perhaps, for the adjustment of rates of prices for measured work.”
“… Workspace consistently claimed a net sum giving the result of the benefit of the payment made by YJL in compliance with the second adjudication decision. The Adjudicator’s third decision, therefore, inevitably required him to take into account that payment made by YJL. If he had not done so, then he would still have concluded that a payment of£77,371.70 was due to Workspace. The Adjudicator was therefore addressing not only the valuation of Certificate 27 but also the balance of the account between the parties. Although he states that he cannot decide that the balance of£48,830.30 plus VAT was due, he has in fact done so in his decision. He clearly found that the payment of£126,192 was made and that the sum of£77,371.70 was due or he could not have deducted it against the negative valuation. There is no basis in his decision for distinguishing between any part of the payment made as a sum due.”
“The adjudicator was entitled therefore to arrive at his decision about the extension of time as it affected the payment and, thus also, the amount of liquidated damages to which the defendant claimed to be entitled. The claimant has to accept the consequences of its own reference on this point.”
“No authority has been cited to me in which the existence of a counterclaim has been held to be a good reason for refusing to allow an award to be enforced as a judgment. I do not think that the existence of a counterclaim is a good reason. I think that it would be contrary to the purpose of Sect. 26 of the Arbitration Act, 1950, if, in a case where the validity of the award and the right to proceed upon it is beyond doubt, it should be given less effect than a judgment. I think that the cases in which an award will not be enforced as a judgment are correctly set out in Russell on the Law of Arbitration, 16th ed., at pp. 269 to 271, and that the existence of a prima facie counterclaim is not one of them. Even, therefore, if I thought that a prima facie counterclaim were established, I should not regard it as a good ground for refusing to allow the applicants to enforce the award in the same manner as a judgment, and, a fortiori , as a good ground for refusing to remit the award to the Board of Appeal so that it may be amended to a form in which the applicants can apply to some other Judge for leave to enforce it in that manner.”
“Once an award has been made — and not challenged in the court — it should be entered as a judgment and given effect accordingly. It should not be held up because the losing party says he wants to argue some point or other or wants to set up a counterclaim or anything on that sort. He would not be allowed to do so in the case of a judgment not appealed from. Nor should he do so in the case of an award that he has not challenged.”
“It is not every cross-claim which can be deducted. It is only cross-claims that arise out of the same transaction or are closely connected with it. And it is only cross-claims which go directly to impeach the plaintiff’s demands, that is, so closely connected with his demands that it would be manifestly unjust to allow him to enforce payment without taking into account the cross-claim.”